scholarly journals Redesign Road Project Using Critical Chain Project Management Method and Crashing Method

OPSI ◽  
2021 ◽  
Vol 14 (2) ◽  
pp. 262
Author(s):  
Arif Budi Sulistyo ◽  
Ilpan Ilpan ◽  
Afni Khadijah
Author(s):  
Jose Finocchio Junior ◽  
Marcelo Ramos Martins

The present study discusses the adequacy of the Critical Chain Project Management Method (CCPM) — also known as the Critical Chain Method — for scheduling projects involving shutdowns on oil platforms, as such projects involve decision-making processes under risk conditions. The CCPM is based on the Theory of Constraints and aims at providing more precise and more clearly focused control instruments than those traditionally used in the Critical Path Method (CPM). The CCPM also indicates the best moments to act and where and how the action should be directed. The hypothesis underlying the research is that the CCPM portrays, more adequately than the CPM, the uncertainty that exists in a platform shutdown. This characteristic also makes it possible to draw up a schedule that is both more realistic and more challenging, as it addresses the goal of causing less interruption of production. On the basis of this hypothesis, the two main questions that oriented the entire investigation were: 1) Is the CCPM suitable for scheduling the shutdown of an offshore oil platform and, 2) What advantages might it have over the traditional methods in use? To answer these questions the authors reviewed the existing bibliography on the topic and made direct on-site observations during an actual shutdown. In addition, interviews were held with a number of specialists in the area using qualitative approaches, namely, semi-structured interviews, focus groups, and action research.


2019 ◽  
Vol 50 (3) ◽  
pp. 322-334 ◽  
Author(s):  
Robert Eduardo Cooper Ordoñez ◽  
Mario Vanhoucke ◽  
José Coelho ◽  
Rosley Anholon ◽  
Olívio Novaski

In 1997, Eliyahu Goldratt proposed a method called critical chain project management (CCPM) to minimize the inefficiencies identified in traditional project management. The project management community accepted the proposed method as a viable alternative. However, to allow its implementation with a multiproject system, more research was necessary. Seeking to identify the key factors that influence the performance of the multiproject system applying the CCPM method, we performed a case study. Logistic regression analysis showed that applying the CCPM method in a multiproject system allows for better time estimation of activities and facilitates the allocation of critical resources.


2021 ◽  
Vol ahead-of-print (ahead-of-print) ◽  
Author(s):  
Tarek Salama ◽  
Ahmad Salah ◽  
Osama Moselhi

Purpose The purpose of this paper is to present a new method for project tracking and control of integrated offsite and onsite activities in modular construction considering practical characteristics associated with this type of construction. Design/methodology/approach The design embraces building information modelling and integrates last planner system (LPS), linear scheduling method (LSM) and critical chain project management (CCPM) to develop tracking and control procedures for modular construction projects. The developed method accounts for constraints of resources continuity and uncertainties associated with activity duration. Features of proposed method are illustrated in a case example for tracking and control of modular projects. Findings Comparison between developed schedule and Monte Carlo simulation showed that baseline duration generated from simulation exceeds that produced by developed method by 12% and 10% for schedules with 50% and 90% confidence level, respectively. These percentages decrease based on interventions of members of project team in the LPS sessions. The case example results indicate that project is delayed 5% and experienced cost overrun of 2.5%. Originality/value Developed method integrated LPS, LSM and CCPM while using metrics for reliability assessment of linear schedules, namely, critical percent plan complete (PPCcr) and buffer index (BI). PPCcr and BI measure percentage of plan completion for critical activities and buffer consumption, respectively. The developed method provides a systematic procedure for forecasting look-ahead schedules using forecasting correction factor Δt and a newly developed tracking and control procedure that uses PPCcr and BI. Quantitative cost analysis is also provided to forecast and monitor project costs to prove the robustness of proposed framework.


2019 ◽  
Vol 12 (2) ◽  
pp. 423-443 ◽  
Author(s):  
Octaviano Rojas Luiz ◽  
Fernando Bernardi de Souza ◽  
João Victor Rojas Luiz ◽  
Daniel Jugend

PurposeThe purpose of this paper is to analyze the state of the art in Critical Chain Project Management (CCPM), outlining the CCPM literature to date, in an effort to guide future studies.Design/methodology/approachThe paper is based on a bibliometric analysis using Scopus and Web of Science databases. The authors identified the principal journals, articles and authors regarding the research theme, as well as the authors elaborated co-citation and co-occurrence network maps to support the analysis.FindingsThe authors described five co-citation clusters: Fundamentals of Critical Chain, Scheduling, Operations Research, Multi-project and Network, and General Project Management. The most frequently occurring keywords were: “project management,” “critical chain,” “scheduling” and “theory of constraints.” Observing the distribution, the expression “project management” occupied a central position, connecting two other clusters, represented by the keywords “scheduling” and “critical chain.” The authors proposed an evolutive framework for the CCPM state of the art in three stages, according to the most frequent topics identified: Conceptual, Deepening of Applications and Methodological Maturity.Originality/valueThis research adopts a systematic approach based on bibliometric tools, which allows a more rigorous organization of the literature. Co-citation and keyword co-occurrence maps provide evidence of how the main themes in CCPM relate. Besides, the presented historical framework allows new research in CCPM to be directed to the most recent topics of interest that have gaps to be explored.


Sign in / Sign up

Export Citation Format

Share Document