Probabilistic network analysis for project completion time∗

1991 ◽  
Vol 8 (3) ◽  
pp. 179-184 ◽  
Author(s):  
Chandra S. Putcha ◽  
Sridhar J. K. Rao
2015 ◽  
Vol 31 (5) ◽  
pp. 04014086 ◽  
Author(s):  
Seyed Taha Hossein Mortaji ◽  
Rassoul Noorossana ◽  
Morteza Bagherpour

2021 ◽  
Vol 14 (2) ◽  
pp. 19
Author(s):  
Faris Rizal Andardi

PERT is a simplified software, to produce the expected project completion probability based on the duration or duration of a particular contract. In developing the PERT method a lot of research was carried out to perfect this method. The purpose of this study is to determine the overall duration of project completion, the magnitude of the project probability that can be completed in less than 170 days and more than 170 days, and the project completion time with the highest probability. Results of Analysis of Implementation of Scheduling System with PERT Method in Rehabilitation and Improvement of Traditional Market Infrastructure Projects in Malang City is the total duration of simulation results obtained 168 days faster than the 172 day plan. The probability of completing the 168 day project is 50%, while the probability of completing the 172 day project is 85.31%. The highest chance of the project being completed is 99.97%, with a duration of 181 days.


2020 ◽  
Vol 24 (10) ◽  
pp. 2861-2875
Author(s):  
Hsien-Kuan Chang ◽  
Wen-Der Yu ◽  
Tao-Ming Cheng

2017 ◽  
Vol 6 (4) ◽  
pp. 1-14 ◽  
Author(s):  
Enobong Udoumoh ◽  
Daniel Ebong ◽  
Iberedem Iwok

2014 ◽  
Vol 2014 ◽  
pp. 1-12 ◽  
Author(s):  
Jianxun Qi ◽  
Zhixiong Su

One fundamental axiom for project plan and schedule relates to the notion that time float will be reduced following its consumption. However, an anomalous scenario can emerge in which an activity’s time float increases following its consumption. By exploring the associations between time float and paths in activity networks, we (a) reveal the conditions under which the anomaly occurs and (b) summarize laws related to total float. An activity’s total float increases in parallel with its duration prolongation within a given boundary but remains constant or decreases in parallel with a prolongation outside the boundary. Furthermore, whereas a prolongation of an activity’s duration in excess of classic total float does not delay project completion time, a lag of its start time to a degree slightly greater than the total float does. This analysis reveals different types of total float that correspond to different ways of usage. From this, we offer definitions for translation total float and prolongation total float that deviate from traditional conventions regarding the uniqueness of total float.


Sign in / Sign up

Export Citation Format

Share Document