Study of ground collapse induced by large-diameter horizontal directional drilling in a sand layer using numerical modeling

2015 ◽  
Vol 52 (10) ◽  
pp. 1562-1574 ◽  
Author(s):  
Biao Shu ◽  
Baosong Ma

With large-diameter horizontal directional drilling (HDD) becoming the preferred method to construct oil and gas pipelines and utility pipelines beneath rivers, the issue of potential ground collapse arises when drilling in loose geological layers such as sand. Ground collapse is a result of borehole collapse and may cause significant damage to the topography and nearby facilities. The present investigation considered the potential causes of ground collapse induced by an actual 1.219 m diameter HDD river-crossing project, using the FLAC3D numerical modeling tool. The analysis showed that the failure zone first developed at the crown of the borehole, resulting in subsequent borehole collapse due to instability of the sand above, and eventually leading to ground collapse. Sequential reaming cycles have been simulated and the results indicate very little effect in comparison with a single reaming cycle. The risk of borehole collapse, and consequent ground collapse, increases with borehole diameter. Parametric numerical modelling has also been conducted to study the influence of soil parameters and drilling mud pressure on the stability of the ground surface above the borehole. The results show that soil cohesion and friction angle have a large influence on stability of the borehole and ground surface, while elastic modulus and Poisson’s ratio have relatively little effect. It was also determined that mud pressure is a very important factor in maintaining stability of the borehole, and therefore the ground surface as well.

2021 ◽  
Vol 117 ◽  
pp. 104159
Author(s):  
Sheng Huang ◽  
Chao Kang ◽  
Alireza Bayat ◽  
Kent Heath ◽  
Cainan Trovato ◽  
...  

Author(s):  
Robson Santana Nóbrega Alves ◽  
Byron Gonçalves de Souza Filho

Horizontal Directional Drilling, as known as HDD, is a method of construction that requires few trenches or no continuous trenches, used for making crossings under rivers, roads and existing structures. In the oil and gas industry, it is most commonly used in offshore and onshore well drilling activities to better explore the reservoir from a single well. It is also very much used when laying pipelines, where no other feasible option is possible. This technology was widely applied in the Urucu-Manaus natural-gas pipeline construction by Petrobras, and Transpetro has been responsible for the operation and maintenance of this pipeline since November 2009, flowing Natural Gas from the heart of the Amazon forest mainly to the growing market of thermoelectric plants. Due to its extension in the forest, the crossing of numerous wide navigable rivers and other natural obstacles was unavoidable, and no other construction methods were more suitable than the HDD technology. This work shows the application of this method in the 1777m long crossing of the Solimões River during the construction of this 662km Natural Gas pipeline. It also shows the challenges faced due to the logistical adversities in the rainforest, as well as the operations by Transpetro.


2004 ◽  
Vol 41 (4) ◽  
pp. 672-685 ◽  
Author(s):  
Michael E Baumert ◽  
Erez N Allouche ◽  
Ian D Moore

Installation loads during 19 commercial horizontal directional drilling (HDD) installations were monitored using new in-hole monitoring cell technology. Fifteen of these installations were part of an 8.3 km section of 203 mm diameter by 4 mm wall thickness steel gas distribution line. The predominant soil type was silty clay, and similar construction practices were employed for all installations. The resistance to pipe advancement within the bore was found to increase in an approximately linear manner, varying from 0.20 to 0.31 kN/m, with a mean of 0.26 kN/m and standard deviation σx = 0.03 kN/m. Local peaks caused by borehole curvature or borehole anomalies were found to dissipate, usually within 10 m, before the underlying linear trend resumed. The remaining four installations were evaluated to determine the relationship between measured pull head load and borehole pressure. The correlation observed provides new insight into the factors that contribute to pulling forces during HDD installations. Based on the findings, a conceptual framework is proposed for an improved HDD design model. The framework outlines two development stages: stage 1, based on tabulated measurements of pulling force per length of pipe inserted; and stage 2, involving significant modifications to an existing prediction model to better represent field conditions.Key words: pipelines, tensile loads, mud pressure, directional drilling, load monitoring, pressure monitoring.


2016 ◽  
Vol 20 (1) ◽  
pp. 1-5
Author(s):  
Li Guohui ◽  
Ma Xiaocheng ◽  
Yang Chunling

<p>The Yangtze River Crossing Project, which is part of the Chinese gas pipeline trunk network and aims to transmit the natural gas to the Yangtze River Delta area, sets up a record for the length of Horizontal Directional Drilling (HDD) in the world. The term of pipeline installed is 3300m, and the diameter is 40in. Many technical difficulties have been inevitably encountered in a large diameter hole reaming in fine sand, the calculation of section scour depth which determines the minimum buried depth of the pipe, protection of outside coating and the method of long distance pilot hole drilling, such other challenges. In view of this, it was recommended that two pipelines of 711mm should be installed to replace the existing one of 1016mm in diameter and 1% flooding scour depth obtained by reliable statistical analysis. In period of installation, application glass fiber reinforced epoxy resin as a protective coating, executing the pilot hole by Intersect Method. As a result, this super project is finished successfully on May 21.2013. The experience can be applied to any pipeline engineering the installed by horizontal directional drilling or similar works.</p>


Sign in / Sign up

Export Citation Format

Share Document