scholarly journals A Robust Two-Machine Flow-Shop Scheduling Model with Scenario-Dependent Processing Times

2020 ◽  
Vol 2020 ◽  
pp. 1-16
Author(s):  
Chia-Lun Hsu ◽  
Win-Chin Lin ◽  
Lini Duan ◽  
Jan-Ray Liao ◽  
Chin-Chia Wu ◽  
...  

In many scheduling studies, researchers consider the processing times of jobs as constant numbers. This assumption sometimes is at odds with practical manufacturing process due to several sources of uncertainties arising from real-life situations. Examples are the changing working environments, machine breakdowns, tool quality variations and unavailability, and so on. In light of the phenomenon of scenario-dependent processing times existing in many applications, this paper proposes to incorporate scenario-dependent processing times into a two-machine flow-shop environment with the objective of minimizing the total completion time. The problem under consideration is never explored. To solve it, we first derive a lower bound and two optimality properties to enhance the searching efficiency of a branch-and-bound method. Then, we propose 12 simple heuristics and their corresponding counterparts improved by a pairwise interchange method. Furthermore, we set proposed 12 simple heuristics as the 12 initial seeds to design 12 variants of a cloud theory-based simulated annealing (CSA) algorithm. Finally, we conduct simulations and report the performances of the proposed branch-and-bound method, the 12 heuristics, and the 12 variants of CSA algorithm.

2016 ◽  
Vol 33 (04) ◽  
pp. 1650032 ◽  
Author(s):  
Zhenyou Wang ◽  
Cai-Min Wei ◽  
Yuan-Yuan Lu

In this paper, we consider a three-machine makespan minimization permutation flow shop scheduling problem with shortening job processing times. Shortening job processing times means that its processing time is a nonincreasing function of its execution start time. Optimal solutions are obtained for some special cases. For the general case, several dominance properties and two lower bounds are developed to construct a branch-and-bound (B&B) algorithm. Furthermore, we propose a heuristic algorithm to overcome the inefficiency of the branch-and-bound algorithm.


2009 ◽  
Vol 57 (2) ◽  
pp. 550-562
Author(s):  
Kenzo Kurihara ◽  
Yann-Liang Li ◽  
Nobuyuki Nishiuchi ◽  
Kazuaki Masuda

1967 ◽  
Vol 15 (3) ◽  
pp. 473-481 ◽  
Author(s):  
G. B. McMahon ◽  
P. G. Burton

2010 ◽  
Vol 139-141 ◽  
pp. 1530-1534 ◽  
Author(s):  
Zhan Tao Li ◽  
Fu Hong ◽  
Qing Xin Chen ◽  
Ning Mao

This paper deals with an optimal method for solving a 2-stage flexible flow shop scheduling problem with group constraint, batch released dates. This problem is known to be NP-hard. In this paper, first of all, we construct a mathematical model for the problem. Then, we develop a branch and bound method with heuristic algorithm for the optimal solution of the problem. During the initialization, we use a heuristic algorithm H’ as the initial solution. We propose two branching algorithms in the branching procedure and two algorithms for the lower bound. We also propose a set of instances for this type of problem. The results are shown that our branch and bound method is effective for small and medium-sized problem but large-sized problem.


OR Spectrum ◽  
2018 ◽  
Vol 40 (3) ◽  
pp. 809-829 ◽  
Author(s):  
Matthias Bultmann ◽  
Sigrid Knust ◽  
Stefan Waldherr

2020 ◽  
pp. 1-25
Author(s):  
Hoang Thanh Le ◽  
Philine Geser ◽  
Martin Middendorf

The two-machine permutation flow shop scheduling problem with buffer is studied for the special case that all processing times on one of the two machines are equal to a constant c. This case is interesting because it occurs in various applications, e.g., when one machine is a packing machine or when materials have to be transported. Different types of buffers and buffer usage are considered. It is shown that all considered buffer flow shop problems remain NP-hard for the makespan criterion even with the restriction to equal processing times on one machine. However, the special case where the constant c is larger or smaller than all processing times on the other machine is shown to be polynomially solvable by presenting an algorithm (2BF-OPT) that calculates optimal schedules in [Formula: see text] steps. Two heuristics for solving the NP-hard flow shop problems are proposed: i) a modification of the commonly used NEH heuristic (mNEH) and ii) an Iterated Local Search heuristic (2BF-ILS) that uses the mNEH heuristic for computing its initial solution. It is shown experimentally that the proposed 2BF-ILS heuristic obtains better results than two state-of-the-art algorithms for buffered flow shop problems from the literature and an Ant Colony Optimization algorithm. In addition, it is shown experimentally that 2BF-ILS obtains the same solution quality as the standard NEH heuristic, however, with a smaller number of function evaluations.