scholarly journals Optimization of Phasor Measurement Unit Placement Using Several Proposed Case Factors for Power Network Monitoring

Energies ◽  
2021 ◽  
Vol 14 (18) ◽  
pp. 5596
Author(s):  
Maveeya Baba ◽  
Nursyarizal B. M. Nor ◽  
M. Aman Sheikh ◽  
A. Momin Baba ◽  
Muhammad Irfan ◽  
...  

Recent developments in electrical power systems are concerned not only with static power flow control but also with their control during dynamic processes. Smart Grids came into being when it was noticed that the traditional electrical power system structure was lacking in reliability, power flow control, and consistency in the monitoring of phasor quantities. The Phasor Measurement Unit (PMU) is one of the main critical factors for Smart Grid (SG) operation. It has the ability to provide real-time synchronized measurement of phasor quantities with the help of a Global Positioning System (GPS). However, when considering the installation costs of a PMU device, it is far too expensive to equip on every busbar in all grid stations. Therefore, this paper proposes a new approach for the Optimum Placement of the PMU problem (OPP problem) to minimize the installed number of PMUs and maximize the measurement redundancy of the network. Exclusion of the unwanted nodes technique is used in the proposed approach, in which only the most desirable buses consisting of generator bus and load bus are selected, without considering Pure Transit Nodes (PTNs) in the optimum PMU placement sets. The focal point of the proposed work considers, most importantly, the case factor of the exclusion technique of PTNs from the optimum PMU locations, as prior approaches concerning almost every algorithm have taken PTNs as their optimal PMU placement sets. Furthermore, other case factors of the proposed approach, namely, PMU channel limits, radial bus, and single PMU outage, are also considered for the OPP problem. The proposed work is tested on standard Institute of Electrical and Electronics Engineering (IEEE)-case studies from MATPOWER on the MATLAB software. To show the success of the proposed work, the outputs are compared with the existing techniques.

Symmetry ◽  
2020 ◽  
Vol 12 (12) ◽  
pp. 2021
Author(s):  
Ahmad Asrul Ibrahim ◽  
Khairuddin Khalid ◽  
Hussain Shareef ◽  
Nor Azwan Mohamed Kamari

This paper proposes a technique to determine the possible optimal placement of the phasor measurement unit (PMU) in power grids for normal operating conditions. All possible combinations of PMU placement, including infeasible combinations, are typically considered in finding the optimal solution, which could be a massive search space. An integer search algorithm called the bounded search technique is introduced to reduce the search space in solving a minimum number of PMU allocations whilst maintaining full system observability. The proposed technique is based on connectivity and symmetry constraints that can be derived from the observability matrix. As the technique is coupled with the exhaustive technique, the technique is called the bounded exhaustive search (BES) technique. Several IEEE test systems, namely, IEEE 9-bus, IEEE 14-bus, IEEE 24-bus and IEEE 30-bus, are considered to showcase the performance of the proposed technique. An initial Monte Carlo simulation was carried out to evaluate the capability of the bounded search technique in providing a smaller feasible search space. The effectiveness of the BES technique in terms of computational time is compared with the existing exhaustive technique. Results demonstrate that the search space can be reduced tremendously, and the computational burden can be eased, when finding the optimal PMU placement in power grids.


2019 ◽  
Vol 32 (3) ◽  
pp. 439-448
Author(s):  
Vladimir Vujicic ◽  
Dragan Pejic ◽  
Aleksandar Radonjic

This paper gives a brief overview of three instruments suitable for measuring the flow of electrical power and energy. The first instrument is a single-phase power analyzer, while the other two instruments are double and quadruple three-phase power analyzers. In addition to over viewing these instruments, the paper presents a possible improvement of a quadruple three-phase power analyzer. The implementation of this improvement would make it possible to use a quadruple three-phase power analyzer as support for the phasor measurement unit.


Author(s):  
Rachana Pandey ◽  
◽  
Dr. H.K. Verma ◽  
Dr. Arun Parakh ◽  
Dr. Cheshta Jain Khare ◽  
...  

In today’s world, a Phasor Measurement Unit (PMU) is a crucial component of our power network for managing, controlling, and monitoring. PMU can provide synchronized voltage current, and frequency measurements in real time. We can't put a PMU in every bus in the electrical grid because it's not viable from a productivity and economic standpoint, and it's also not practical for handling huge data. As a result, it's critical to reduce the amount of PMU in the power network while also increasing the power network's observability. The optimal PMU placement problem is solved using a variety of methodologies. The paper's main goal is to provide a brief overview of synchrophasor technology, phasor measurement units (PMU), and optimal PMU placement in order to reduce the number of PMUs in the system while maintaining complete observability and application in today's power systems.


Sign in / Sign up

Export Citation Format

Share Document