Balanced Lift Method—A New Bridge Construction Technique

Author(s):  
J. Kollegger ◽  
S. Foremniak
Author(s):  
Elina Prajapati ◽  
Jin Ouk Choi

Accelerated bridge construction (ABC) is an innovative construction technique used to accelerate the construction of new bridges, as well as the renovation/replacement of existing bridges. Due to the benefits offered by ABC, transportation authorities have a higher preference in executing an accelerated approach over conventional bridge construction. The execution of an accelerated approach has differences when compared to the conventional approach, and it is important to identify such differences for the successful implementation of ABC projects. However, there have been no studies to identify such execution differences. Therefore, this study was conducted to identify execution plan differences relevant to ABC. For this purpose, an extensive literature review was conducted to prepare a preliminary list of execution plan differences. Then, a questionnaire survey was administered with the industry experts, who were previously involved in the execution of ABC projects, to validate the preliminary list. Based on the literature review and the responses from questionnaire survey, this study identified 61 execution plan differences relevant to ABC in different phases of execution. This study is expected to benefit owners, contractors, and road/bridge users for successful execution of ABC projects.


2015 ◽  
Vol 2 ◽  
pp. 35
Author(s):  
Junzhuang Wang

<p>Under the background of increasingly expanded road traffic network in China, it is highly necessary to construct bridges. Upgrading the bridge construction technique can upgrade the road quality to the maximum extent. In order to upgrade the construction technique, this article elaborates on the construction techniques of hanging basket in four aspects: definition and design principle of hanging basket; key application points of construction techniques of hanging basket in the bridge project; frequent quality accidents and preventive and curative measures of hanging basket; on-site management of hanging basket and upgrading of safety.</p>


2011 ◽  
Vol 243-249 ◽  
pp. 1848-1853 ◽  
Author(s):  
Qing Fu Li ◽  
Zhen Xin Li ◽  
Jie Niu

In this paper, the basic theory of factor analysis and the possibility of its application in the risk analysis of bridge construction was discussed. By making risk questionnaires, the basic data on the factor of bridge construction was summarized. On the basis of statistical processing of the data by SPSS 10.0 software, seven categories of main risk factors were pointed out , which are economy risk, contract and law risk , design risk, construction technique risk ,environment risk ,staff risk and material and equipment risk. Besides, the importance index and the correlation of the risk factors were calculated out. Sequentially, the risk of bridge construction can be evaluated quantitatively.


PCI Journal ◽  
2012 ◽  
Vol 57 (4) ◽  
pp. 34-49 ◽  
Author(s):  
Bijan Khaleghi ◽  
Eric Schultz ◽  
Stephen Seguirant ◽  
Lee Marsh ◽  
Olafur Haraldsson ◽  
...  

Sign in / Sign up

Export Citation Format

Share Document