Characterization of the Oxide Scale Formed on T12 Water Wall Tube After Long-term Service in Supercritical Power Plant

2019 ◽  
Vol 91 (5-6) ◽  
pp. 705-727 ◽  
Author(s):  
Xiangyu Zhong ◽  
Fethi Hamdani ◽  
Jian Xu ◽  
Tetsuo Shoji ◽  
Tadashi Tatsuki ◽  
...  
Author(s):  
Jun Si ◽  
Zhenrong Yan ◽  
Jianjun Chen

The efficiency of conventional boiler/steam turbine fossil power plants has strong relationship to the steam temperature and pressure. At present, steam temperatures of the most efficient fossil power plants are now in the 600°C range. Higher-strength materials are needed for upper water wall tube of boilers with steam pressure above 24 MPa. A high-strength 2.5%Cr steel recently approved by ASME code as T23 is the preferred candidate material for this application. Due to its superior properties, T23 steel is typically not post-weld heat treated. However, after several years running there are a lot of incident reports for T23 tubes especially the breakage of weldment in the ultra-supercritical power plant. This is cause for concern for T23 tubes weldment used under high temperature environments. Previous studies showed that the residual stress may play an important role to the performance of spiral water wall tube. In this paper, the distribution of residual stress in T23 tube weldment has been investigated in detail. Inner wall cracks were found at the butt-jointed seam region of spiral water wall tubes by radiographic testing after one year’s operation. Failure analysis of the spiral water wall tube cracking was conducted by chemical composition analysis, mechanical testing and finite element analysis in this paper. It was found that localized residual stress after the weld process caused concentrated stress, which is the primary reason for failure. Our studies illustrate the necessity of post weld heat treatment for the T23 tubes used under high temperature.


2021 ◽  
Vol 257 ◽  
pp. 01064
Author(s):  
Hai Zhao ◽  
Chong Jiang ◽  
Zhiwei Gao ◽  
Chengchuan Tian

The reason and mechanism of the failure of SA210-C steel liquid wall were analyzed by means of macro morphology analysis, chemical composition analysis, microstructure analysis and XRD phase analysis. The test results show that the main reason for the failure of SA210-C steel water wall tube is the corrosion under the inner wall scale, and the long-term unqualified boiler water quality is the main factor causing the corrosion of water wall.


2018 ◽  
Vol 37 (9-10) ◽  
pp. 995-999 ◽  
Author(s):  
Guohua Yang ◽  
Yuanbo Gou ◽  
Xinshi Liu ◽  
Xiaoming Zhang ◽  
Tuo Zhang

AbstractHigh temperature corrosion of the water wall tube in a 50 MW thermal power plant was investigated which caused several boiler accidents. X-ray diffraction (XRD) and scanning electron microscopy (SEM) equipped with energy dispersive spectrometer (EDS) were used to observe the cross-sectional morphology of the tube and analyze the oxide scales. Results show that the boiler water and the coal quality did not meet the requirements. High temperature corrosion of water wall tubes was attributed to the using of coal which had a higher ash content and lower received lower heating value. Higher dissolved oxygen and incrustation in the boiler water caused serious corrosion at the inner surface of water wall tube, which led to the possibility of decarburization and degradation of the steel. Suitable coal blending and stability of the thermal load were the effective means to prevent the high temperature corrosion of the tube.


Author(s):  
Yao Li ◽  
Chengming Liu ◽  
Fengyuan He ◽  
Fei Wang