An analysis of pattern and architectural aspects of diaphragm barrier for underground metro project

Author(s):  
P.R. Kalyana Chakravarthy ◽  
K. Gurusamy ◽  
T. Illango
Keyword(s):  
2014 ◽  
Vol 584-586 ◽  
pp. 2577-2580
Author(s):  
Jin Xian Zhao ◽  
Long Li ◽  
Min Liu

This paper establish the index system of metro project which included four control targets of the engineering project management that is quality, cost, construction period, safety into integrated dynamic system. We realizes the PCA dimension of the 17indexes in the set and gets four principal components by using PCA of multivariate statistical methods. According to the feature vector of four main components, the main ingredients are classified and reorganized. By comparing the scores ranking of four redefined main components and evaluation scores ranking, we conduct integrated dynamic analysis of metro project objectives. Finally, the results of case study shows the conclusion is in line with the possible situations of the metro project management.


Author(s):  
Paul-Emile Durand ◽  
Lucas Wise ◽  
Emmanuel Joy ◽  
Alain Rossetto

<p>In June 2013, three consortia were awarded the three construction packages that constitute the whole Riyadh Metro Project in Saudi Arabia for a total of 6 lines and 180 kilometres.</p><p>International Bridge Technologies was in charge, as a subconsultant of Idom, of the complete structural scope of services for the 25.6 km of elevated viaduct that Riyadh Metro Package 2 comprises (Line 3, around 41.6 km, out of which 25.6 km are elevated). This scope consisted of the full range of services from conceptual tender design to final detailed design, including shop drawings production, construction engineering and construction site support.</p><p>The Line 3 elevated viaduct consists of a three-cells precast segmental box-girder with typical simply-supported spans of 37 m and special continuous spans of 50 m. Six long span structures with spans varying from 60 m to 95 m were required for the special crossings over existing interchanges. Typical and continuous spans are erected span-by-span with an overhead truss while long spans are erected in balanced cantilever with cranes on the ground or lifting frames on the deck.</p><p>The present paper is centred on the design of the elevated viaduct and presents the different structures with key features and how they were constructed to permit large scale standardisation and speed of construction. Some key design aspects are developed, in particular the design approach for the 3-cells box-girder as the most effective solution to satisfy the imposed aesthetic criteria. This paper also exposes the design approach adopted to produce a “design-for-demand” by relying as much as practically possible on a realistic modelling of the alignment and by limiting parametric design. This allowed for an optimisation of material quantities.</p>


Author(s):  
Shutian Zhou ◽  
Guofang Zhai ◽  
Yuwen Lu ◽  
Yijun Shi

Since there has been a huge amount of transport infrastructure projects being proposed, planned and constructed over the past decades in China, this article aims to reveal the substantial dynamics of China’s rapid development of urban mega-projects. It analyzes Nantong’s metro project to use it as a case study – how it was being justified, approved and implemented, and what were the key driving forces within the whole process through official justifications and key informant interview materials. The urban metro system is supposedly an approach to achieve urban development objectives, a tool for growth and a way to a better urban life. We find inter-city competition as an underlying driving force that initiates such urban mega-projects with certain weight given to economic indicators in project appraisals within a largely local government-led and public-invested process. Furthermore, domestic economic performance and changing policy interventions also exert significant influence on project approval and long-term project development. Our findings echo some Western literature on mega-projects development and urban competition, while revealing other features and emerging issues relating to project initiation, proposal examination and implementation specific to the Chinese context.