Probabilistic Corrosion Modelling to Estimate the Design Life of Pipes

2020 ◽  
Author(s):  
Chris Atkins ◽  
Paul Lambert ◽  
Sean Greenwood ◽  
Mohssan Mahmood
2015 ◽  
Vol 105 (37) ◽  
pp. 1-8
Author(s):  
Yongjoo Jung ◽  
Chungyoung Cho ◽  
Hongsik Kim ◽  
Dongjin Lee ◽  
Heungbae Gil ◽  
...  
Keyword(s):  

Author(s):  
M. F. Bransby ◽  
D. O’Driscoll ◽  
H. Zhu ◽  
M. F. Randolph ◽  
T. Drummen

Increasing numbers of subsea structures related to wells and pipelines are being placed on the seabed as part of typical subsea or tie-back developments. Given the proliferation of these structures and the marginal cost of offshore developments, controlling installation and fabrication costs for subsea structures can be key to project viability. Skirted mudmats are often the most cost-effective foundation type, and particular additional design focuses on optimising their cost by minimising foundation weight and installation time. Subsea foundations must be designed to withstand all applied loads during their design life (e.g. during set-down, tie-in, hydrotest, operation etc.) with suitable reliability. Using skirts, peripheral or internal, to improve the sliding resistance is an efficient solution provided the self-weight of the subsea structure on set-down is sufficiently large to ensure installation of the skirts (even for the strongest likely seabed conditions), but can lead to significant cost increases if additional ballast is required to ensure this. The paper examines how foundation skirt geometries can be optimised in order to provide sufficient foundation in-place capacity whilst minimising the amount of self-weight required for their installation. Parametric studies are presented that show how the sliding capacity of individual skirts is affected by the weight of the structure, and also the spacing and position within the foundation plan.


2021 ◽  
Author(s):  
Egor Svechnikov ◽  
Johan Maljaars ◽  
Bert Snijder ◽  
Johan de Boon ◽  
Eize Drenth

<p>Many developed countries have a national road network including a significant number of bridges in need of renovation or replacement in the coming years. The reason for this is their technical and functional capacity becoming insufficient due to aging and changes in societal demands. Therefore, these bridges need to be adjusted or replaced. National authorities in The Netherlands currently require a design life of 100 years for new bridges, however nowadays it seems reasonable to have a certain flexibility for this parameter. Since the selected design life has its implications on structural solutions and choice of materials, the identification of the optimal design life for bridges seems necessary. This paper gives a summary on the issue regarding the optimum design life of bridges and it highlights the framework of the upcoming research activities.</p>


2021 ◽  
Author(s):  
Biramarta Isnadi ◽  
Luong Ann Lee ◽  
Sok Mooi Ng ◽  
Ave Suhendra Suhaili ◽  
Quailid Rezza M Nasir ◽  
...  

Abstract The objective of this paper is to demonstrate the best practices of Topside Structural Integrity Management for an aging fleet of more than 200 platforms with about 60% of which has exceeded the design life. PETRONAS as the operator, has established a Topside Structural Integrity Management (SIM) strategy to demonstrate fitness of the offshore topside structures through a hybrid philosophy of time-based inspection with risk-based maintenance, which is in compliance to API RP2SIM (2014) inspection requirements. This paper shares the data management, methodology, challenges and value creation of this strategy. The SIM process adopted in this work is in compliance with industry standards API RP2SIM, focusing on Data-Evaluation-Strategy-Program processes. The operator HSE Risk Matrix is adopted in risk ranking of the topside structures. The main elements considered in developing the risk ranking of the topside structures are the design and assessment compliance, inspection compliance and maintenance compliance. Effective methodology to register asset and inspection data capture was developed to expedite the readiness of Topside SIM for a large aging fleet. The Topside SIM is being codified in the operator web-based tool, Structural Integrity Compliance System (SICS). Identifying major hazards for topside structures were primarily achieved via data trending post implementation of Topside SIM. It was then concluded that metal loss as the major threat. Further study on effect of metal loss provides a strong basis to move from time-based maintenance towards risk-based maintenance. Risk ranking of the assets allow the operator to prioritize resources while managing the risk within ALARP level. Current technologies such as drone and mobile inspection tools are deployed to expedite inspection findings and reporting processes. The data from the mobile inspection tool is directly fed into the web based SICS to allow reclassification of asset risk and anomalies management.


2021 ◽  
Author(s):  
Andre Orcesi ◽  
Emilio Bastidas-Arteaga ◽  
Olga Markogiannaki ◽  
Yue Li ◽  
Franck Schoefs ◽  
...  

<p>One major issue when considering the effects of climate change is to understand, qualify and quantify how natural hazards and the changing climate will likely impact infrastructure assets and services as it strongly depends on current and future climate variability, location, asset design life, function and condition. So far, there is no well-defined and agreed performance indicator that isolates the effects of climate change for structures. Rather, one can mention some key considerations on how climate change may produce changes of vulnerability due to physical and chemical actions affecting structural durability or changes of the exposure in terms of intensity/frequency of extreme events. This paper considers these two aspects and associated challenges, considering some recent activities of members of the IABSE TG6.1.</p>


2021 ◽  
Author(s):  
Guy L. Larose ◽  
Pierre-Olivier Dallaire ◽  
Theresa Erskine ◽  
Chiara Pozzuoli ◽  
Emanuele Mattiello

<p>This paper introduces the methodology RWDI has developed, tested and consolidated over the years working in close collaboration with bridge designers, owners and operators, for the multi-hazard assessment of existing bridges and the ad hoc development of a structural health monitoring programme leading to enhanced resiliency. The work is highlighted through the presentation of a case study for a 2,725 m long cantilever bridge built in 1930. The dynamics of the structure in its current state were characterised and its capacity to today and future wind loading was assessed fully following the proposed methodology prior to the initiation of a structural rehabilitation program to extend the design life of the bridge beyond its 150th anniversary.</p>


Author(s):  
Chet Chie Voon ◽  
Hiang Miang Goh ◽  
Chuan Seng Koo

<p>The construction of the Pulau Poh cable-stayed bridge has been challenging both technically and environmentally. The curved pylon shape in two planes, with changing cross section and heavily congested reinforcement pose constructability concerns. Accurate geometry control and positioning of stay cable anchorages within the pylon is crucial to ensure the bridge meets its intended design life. Located in an area with high rainfall intensity presents additional environmental challenges, where working areas are constantly submerged. To address the challenges and meet the project deadline, innovative construction methodologies are being adopted. The bridge design was also revisited, taking into consideration the construction approach. This paper aims to explain the challenges faced and methods used to fast track the construction of the Pulau Poh cable-stayed bridge.</p>


Author(s):  
W. Sloterdijk ◽  
M. Hommes

In today’s challenging environment, the priority for many oil and gas operation companies is to design, build and safely operate facilities at optimum cost efficiency. This means that new facility designs must consider critical facility integrity and that existing facilities are operated well beyond their intended design life. Main gas transmission systems are now some 50 years old and operate for longer periods than anticipated during design and construction for reasons such as; the transition to renewables with another 50 years of service foreseen, and; gas transmission systems that operate satisfactorily, have very low failure rates and for which the planned safe life time extension is expected to be the lowest cost option.


Sign in / Sign up

Export Citation Format

Share Document