Causes of road projects' delays: a case of Blantyre, Malawi

2021 ◽  
Vol ahead-of-print (ahead-of-print) ◽  
Author(s):  
Henry Duncan John Mwamvani ◽  
Christopher Amoah ◽  
Emma Ayesu-Koranteng

PurposeThe study aims to find the causes of road projects implementation delays in Blantyre, one of the four city councils (CCs) in Malawi.Design/methodology/approachThe study followed a qualitative research approach using a Blantyre City Council (BCC) as a case study. This study combined in-depth, face-to-face interviews with councillors, secretariat staff, consultants, and contractors who worked on the city's road projects. Data gathered were analysed using thematic content analysis. Also, some road project documents were examined.FindingsThe findings from the case study revealed the primary cause of road project construction delays as the shortage of engineers in conducting detailed proposed projects surveys resulting in incomplete project scope definition before contractor's procurement. Other identified factors were service providers delaying the removal of existing public utility infrastructure from project sites, client funding issues, scope changes, and client delays in issuing instructions to the contractors during project implementation. Another factor was the shortage of construction equipment and construction materials experienced by some appointed contractors.Research limitations/implicationsOnly road construction projects and stakeholders operating from Blantyre city, Malawi, were contacted for the study; thus, the findings may not be generalizable.Practical implicationsThere is an urgent need to increase technical employees, especially engineers and other critical technical staff such as quantity surveyors in Blantyre. Employees' conditions of service should be conducive to attract qualified people to undertake effective management and assessment of projects before commencement to identify the feasibility of proposed projects to decrease the rate of road construction project delays.Originality/valueThe study has established Blantyre city's core challenges in implementing its road projects seamlessly and has provided mitigation measures for dealing with the shortcomings.

2017 ◽  
Vol 15 (2) ◽  
pp. 110-127 ◽  
Author(s):  
Charles Teye Amoatey ◽  
Alfred Nii Okanta Ankrah

Purpose The purpose of this paper is to investigate the causes of road construction delays in Ghana and identify appropriate mitigation measures. Design/methodology/approach The initial approach involved an empirical analysis of 48 road projects to quantify the extent of time. This was followed by a survey of the perception of road agency and donor partner officials of the critical causes of road project delays. Findings About 70 per cent of road projects experience delays and 52 per cent experience cost overruns. The average time overrun and cost overruns of road projects in Ghana was 17 months and US$1.15m (or 22.5 per cent), respectively. The five most critical causes of road construction delays were delay in finance and payment of completed work by owner (client-related); inadequate contractor experience (contractor-related); changes in scope by the owner during construction (client-related); delay to furnish and deliver the site to the contractor (client-related); and inflexible funding allocation for project items (donor-related). Research limitations/implications The most critical constraint of this study is the fact that findings are based on only the views of industry professional experts. It may be assumed that despite using broadly used terminology to refer to the causes of project delays, the interpretations by respondents may have differed from those intended. Further research could look at the correlation between time overrun and cost overrun using principle component analysis. Practical implications The identified delay factors are not unique to the road sector. From both academic and practical perspectives, the results emphasizes on the need for a holistic and integrated risk management model for the entire construction industry in Ghana. Originality/value The paper examined the causes of road project delays in the Ghanaian context and recommended remedial measures.


2017 ◽  
Vol 10 (1) ◽  
pp. 5-31 ◽  
Author(s):  
Anna-Maija Hietajärvi ◽  
Kirsi Aaltonen ◽  
Harri Haapasalo

Purpose The effective management of inter-organizational integration is central to complex projects. Such projects pose significant challenges for integration, as organizations struggle with constantly changing inter-organizational interdependencies and must develop and adapt integration mechanisms to meet new demands. The purpose of this paper is to understand what kinds of integration mechanisms are used and how they are developed and adjusted during the infrastructure alliance projects. Design/methodology/approach This study provides empirical evidence of integration dynamics in project alliancing by analyzing two infrastructure alliance projects – a complex tunnel construction project and a railway renovation project. The research approach is an inductive case study. Findings This paper identifies integration mechanisms adopted in two case projects and three central triggers that led to changes in the integration mechanisms: project lifecycle phase, unexpected events and project team’s learning during the project. Practical implications Integration capability should be a precondition for alliance project organizations and requires the adoption of a wide range of integration mechanisms, as well as an ability to adjust those mechanisms in response to everyday dynamics and emergent situations. Originality/value Although unplanned contingencies and the responses to them represent important influences in organizations, there is limited amount of research on the dynamics of integration. The findings will be of value in supporting the management of inter-organizational integration in complex, uncertain and time-critical construction projects.


2014 ◽  
Vol 10 (2) ◽  
pp. 61-72 ◽  
Author(s):  
Jennifer Clarke

Purpose – The purpose of this paper is to explore the value of the “capability approach” as an alternative framework for understanding and conceptualising the role of Refugee Community Organisations (RCOs) and other providers for groups conventionally considered “hard to reach”. Design/methodology/approach – A study of the education services of RCOs, drawing primarily on semi-structured interviews with 71 users, is put forward as a case study for how the capability approach can be operationalised. Findings – The capability approach is found to offer various valuable insights, relating to its appreciation of the multi-dimensional nature of human wellbeing, the significance of individual diversity, and the importance of human agency. Research limitations/implications – The case study is based on a relatively small purposive sample, and may have limited external validity. As the research design proved strong for exploring how RCOs develop their users’ capabilities but weak for exploring if and how they may also constrict them, further research in this area is required. Practical implications – A number of valuable attributes of the capability approach are highlighted for broadening the understanding, the role of RCOs and other service providers. Social implications – The paper outlines the potential of the capability approach to contribute to policymaking related to RCOs and other providers, and to debates relating to social exclusion, cohesion and integration. Originality/value – The paper draws attention to the value of the capability approach within the field of migration research.


2017 ◽  
Vol 30 (6) ◽  
pp. 545-553 ◽  
Author(s):  
Frank Bonsu ◽  
Felix Afutu ◽  
Nii Nortey Hanson-Nortey ◽  
Mary-Anne Ahiabu ◽  
Joshua Amo-Adjei

Purpose Within human services, client satisfaction is highly prioritised and considered a mark of responsiveness in service delivery. A large body of research has examined the concept of satisfaction from the perspective of service users. However, not much is known about how service providers construct client satisfaction. The purpose of this paper is to throw light on healthcare professionals’ perspectives on patient satisfaction, using tuberculosis (TB) clinics as a case study. Design/methodology/approach In-depth interviews were conducted with 35 TB clinic supervisors purposively sampled from six out of the ten regions of Ghana. An unstructured interview guide was employed. The recorded IDIs were transcribed, edited and entered into QSR NVivo 10.0 and analysed inductively. Findings Respondents defined service satisfaction as involving education/counselling (on drugs, nature of condition, sputum production, caregivers and contacts of patients), patient follow-up, assignment of reliable treatment supporters as well as being attentive and receptive to patients, service availability (e.g. punctuality at work, availability of commodities), positive assurances about disease prognosis and respect for patients. Practical implications Complementing opinions of health service users with those of providers can offer key performance improvement areas for health managers. Originality/value To the best of the authors’ knowledge, this is a first study that has examined healthcare providers’ views on what makes their clients satisfied with the services they provide.


2021 ◽  
Vol ahead-of-print (ahead-of-print) ◽  
Author(s):  
Yi-An Chen ◽  
Chun Liang Chen

Purpose The purpose of this study is to explore how creative-cultural hotels can achieve sustainable service design through the development of a holistic conceptual framework. Design/methodology/approach The authors created this framework using a qualitative exploratory multi-case study of four creative-cultural hotels in Taiwan. The framework comprises strategic, organizational and interface levels to describe the design process and implementation of service offerings that co-create value within a multifaceted network of actors. Findings The findings of this study show that incorporating local arts and culture into sustainable service design can generate unique value and experiences for customers. From the perspective of sustainable development, these hotels seek to add value by using local creative and cultural resources to ensure that they have a sound commercial base from which to showcase their cultural features. As such, this study recommends that the hotel industry shift its focus to a paradigm that provides a strategic and sustainability-framed vision to create value for society while protecting local natural and cultural resources. Originality/value This multilevel model reframes the development of customer value constellations through a holistic understanding of user experience, eco-design practice, service encounters aligned with user touchpoints and front-line employee capabilities. To integrate the perspectives of both service providers and their customers, the proposed model embeds these stakeholders within a single model through the vehicle of local value co-creation. This holistic framework can assist in designing sustainable service within the hospitality industry to deliver better services and customer experiences. The findings provide an illustration of how the proposed multilevel sustainable-development-oriented service design framework can serve as a useful tool in guiding hotels toward corporate sustainability.


2021 ◽  
Vol ahead-of-print (ahead-of-print) ◽  
Author(s):  
Vania Christy ◽  
Teck Hong Tan

Purpose The purpose of this study is to fill a knowledge gap by analyzing the motivations of tenants to co-living spaces in Klang Valley, Malaysia as the motives of co-living spaces are related to how well that space supports their needs. Design/methodology/approach Tenants’ behaviors were examined using a convergent parallel mixed-method approach, which included a survey and an in-depth interview. A total of 175 respondents were interviewed using purposive sampling. Findings The results show that the preference for co-living attributes has changed during the pandemic. User ratings of preference for physical and leasing attributes of co-living spaces are significant in terms of co-living motivations. The findings also revealed that tenants prefer twin-sharing and master bedrooms when choosing a co-living space to stay in. Research limitations/implications Identifying the factors that influence such motivations is critical for housing developers and co-living service providers to pay close attention to improving tenants’ living experiences. Originality/value There is interest in the co-living spaces that are available for rent. However, very little research is based on an understanding of how the tenants in Klang Valley, Malaysia perceive this type of living arrangement. A better understanding and prediction of tenants’ needs and preferences may lead to a better understanding of the attributes that influence their motivations for using co-living spaces.


2018 ◽  
Vol 19 (4) ◽  
pp. 327-342 ◽  
Author(s):  
Ruchi Agarwal ◽  
Sanjay Kallapur

PurposeThe purpose of this study is to explore the best practices for improving risk culture and defining the role of actors in risk governance.Design/methodology/approachThis paper presents an exemplar case of a British insurance company by using a qualitative case research approach.FindingsThe case study shows how the company was successful in changing from a compliance-based and defensive risk culture to a cognitive risk culture by using a systems thinking approach. Cognitive risk culture ensures that everybody understands risks and their own roles in risk governance. The change was accomplished by adding an operational layer between the first and second lines of defense and developing tools to better communicate risks throughout the organization.Practical implicationsPractitioners can potentially improve risk governance by using the company’s approach. The UK regulator’s initiative to improve risk culture can potentially be followed by other regulators.Originality/valueThis is among the few studies that describe actual examples of how a company can improve risk culture using the systems approach and how systems thinking simultaneously resolves several other issues such as poor risk reporting and lack of clarity in roles and responsibilities.


2015 ◽  
Vol 16 (1) ◽  
pp. 199-223 ◽  
Author(s):  
Enrique Claver-Cortés ◽  
Patrocinio Carmen Zaragoza-Sáez ◽  
Hipólito Molina-Manchón ◽  
Mercedes Úbeda-García

Purpose – Based on the literature devoted to family firms and the intellectual capital-based view of the firm, the purpose of this paper is not only to identify the most important human capital intangibles owned by family firms but also to show a number of indicators that can help measure them. Design/methodology/approach – A qualitative case-study-based research approach was adopted taking as reference: 25 family firms belonging to different sectors; previous works existing in the literature; and the intellectus model. Findings – The present study identifies ten intangibles associated with the human capital of family firms and shows 60 indicators that can be used to measure them. It additionally provides empirical evidence and gives examples of these intangibles through the analysis of 25 international family firms. Research limitations/implications – The difficulty in collecting all the human capital intangibles of family firms; the problems associated with the creation of accurate indicators; and those specific to the research methodology adopted. Practical implications – Identifying the human capital intangibles of family firms and their indicators can help managers become aware of their importance, and this will consequently help them improve their management. This could be an interesting starting point to value these intangibles in the balance sheet as well as to draw comparisons between family and non-family organisations. Originality/value – The framework provided by family firms sheds light on several intangibles specific to these firms – precisely for their condition as “family” firms. Those intangibles – human capital intangibles being especially highlighted in this study – provide the basis for the achievement of competitive advantages.


2015 ◽  
Vol 26 (4) ◽  
pp. 518-537 ◽  
Author(s):  
Amarilis Lucia Casteli Figueiredo Gallardo ◽  
Caio Pompeu Cavalhieri ◽  
Sofia Julia Alves Macedo Campos ◽  
Omar Yazbek Bitar

Purpose – The purpose of this paper is to investigate the effectiveness of mitigation measures adopted in a scheme of EIA follow-up by examining their performance in reducing geo-environmental impacts in earthwork activities during the Rodoanel southern section construction in São Paulo, Brazil. This environment is fragile in terms of affected watersheds because the highway crosses two important reservoirs that supply most of the metropolitan water demand. Therefore, this research also aims at promoting water quality control. Design/methodology/approach – This study combines complementary sources as evidences in the literature and field checks, tests and monitoring. The methodology was supported by criteria for evaluating the effectiveness of mitigation measures in the case study approach. Findings – The EIA follow-up activities contributed to the maintenance of environmental conditions in the majority of the control points at the end of the construction phase. Water quality parameters were not statistically different before and during the construction of the highway. The choice and arrangement of mitigation measures were successful in ensuring water quality control by avoiding siltation. Practical implications – A robust scheme for designing and evaluating mitigation measures contributes to the improvement of their effectiveness and is pivotal to the success of the EIA follow-up. Originality/value – This case study serves as an example for extending EIA follow-up practice in special to the improvement of the design and evaluation of mitigation measures in similar contexts.


2019 ◽  
Vol 30 (1) ◽  
pp. 81-99
Author(s):  
Azlan Long Abdullah ◽  
Zawiyah Mohammad Yusof ◽  
Umi Asma Mokhtar

Purpose The purpose of this paper is to explore, identify and gain insight into factors related to electronic records and information management (e-RIM) issues and their influence on the implementation of e-RIM initiative in military service in Malaysia. This exploration was conducted via a literature review and case study. Design/methodology/approach This study adopted a qualitative approach and used a case study involving two army departments in Malaysia. Interviews triangulated by document content analysis and observations were used for data collection. The data were analysed using a directional content analysis approach. Findings This study reveals that people, organizations, technology and processes are the interrelated contexts underlying e-RIM issues which inevitably influence the implementation of e-RIM initiatives. Competency and leadership, governance structure, culture and strategic planning, technology development and record-keeping process are the main factors impacting such efforts, in turn forming potential obstacles for organizations implementing such initiatives. Research limitations/implications The research approach and design adopted and the sample size were insufficient for generalization of the findings. Practical implications This study shows that e-RIM initiatives pose greater challenges related to various issues that cause difficulties in improving and implementing the initiative. Thus, it is crucial for organizations to ascertain and comprehend the factors that influence e-RIM initiatives prior to formulating strategies and approaches in addressing those factors, which would in turn affect the implementation of e-RIM initiatives. Originality/value This study provides insights into the fundamental factors embracing the e-RIM issues which influence the initiatives, and thereby fosters further discussion and research in the subject matter in Malaysia.