Dismantling of a Nuclear Fuel Fabric - Release of Building Rubble and Site: An Overview
2001 ◽
Keyword(s):
Abstract Uranium fuel rods were produced in the nuclear fuel site. The buildings should be dismantled after decontamination and the site should be released for industrial use. The individual dose to the critical group is limited to an annual value of about 10 μSv. The determined specific activity for remediation of the site was a mean value of 60 mBq/g total activity. For the building rubble and soil primarily two pathways, disposal at a landfill and refill of a disused salt mine, were considered. As a result of the investigations the total activity for the disposal at a landfill had to be limited to about 6,6 GBq. For the refill of the salt mine the estimated individual dose fell below the dose limit in the range of 10 μSv/y.