CO2 Tracer Application to Supplement Gas Lift Optimisation Effort in Offshore Field Sarawak

Author(s):  
Azfar Israa Abu Bakar ◽  
M Zul Afiq Ali Jabris ◽  
Hazrina Abd Rahman ◽  
Bakhtiyor Abdullaev ◽  
Khairul Nizam Idris ◽  
...  
2021 ◽  
Author(s):  
Fadzlan Suhaimin ◽  
Nasir Oritola ◽  
Bo Jun Fang ◽  
Hing Kheong Cheong ◽  
Yung Khiong Chan

Abstract The Offshore Field X Project comprises of greenfield scope to expand the Waterflood scheme towards delivering the peak production levels similar to those achieved in the 1990s. Although various artificial lift systems have been successfully deployed in Brunei Shell Petroleum, offshore ESP installation, especially on this scale, is a first and a new journey for the company and its Offshore Assets in which gas lift was predominantly the artificial lift method. The first offshore ESP well was only installed and kicked off in 2017 as part of the Field X Project. As wells are located offshore, cost, resources and logistics remain a challenge for well interventions. With a high workover cost associated with conventional ESP change out, a technology trial was embarked upon to install wireline retrievable ESP systems. A total of 4 out of the 22 ESP wells were approved to be installed and completed with wireline retrievable ESP system on a pilot basis. The business goal was to prove the production deferment reduction and cost advantage for a failed ESP replacement. A critical selection process was followed as well as FAT/industry benchmarking in order to land on WRESP decision for the pilot. System installation and commissioning of the wells was completed by June 2019, however a series of start-up problems were encountered, leading to an intervention requirement to rectify 1 well. Job planning for this intervention was not straight forward and was classified as a high-risk job requiring regulator's approval. Rigorous logistics planning, integration of various vendors, detailed workflow analysis, intervention equipment stack up and modifications were among the planning scope conducted. This paper captures details of the deployment value proposition, case success definition and challenges faced in ensuring all the installed WRESPs are up and running to enable the pilot performance proper evaluation. As no full workover has been executed yet due to the limited operating period, a lifecycle comparison between WL retrievable and conventional ESPs has not been done yet. Once sufficient performance data is available, a detailed study will be conducted to assess the performance of the WRESP system. This analysis will then conclude the technology trial and may change the future of ESP wells in BSP and Shell global.


2020 ◽  
Author(s):  
Abdullah M. Al-Dhafeeri ◽  
Bader M. Al-Enezi ◽  
Elessawy A. Atwa ◽  
Sultan A. Al-Aklabi ◽  
Shebl Fouad Abo Zkery ◽  
...  
Keyword(s):  

2021 ◽  
Author(s):  
Farasdaq Sajjad ◽  
Steven Chandra ◽  
Alvin Wirawan ◽  
Silvya Dewi Rahmawati ◽  
Michelle Santoso ◽  
...  

Abstract In the implementation of gas lift, understanding flow behavior in highly-deviated well is critical in avoiding production loss due to liquid fallback and blockage, even in highly-productive reservoir. In this work, we utilize Computational Fluid Dynamics (CFD) to optimize gas lift design under various flow behavior in highly-deviated well. The analysis is directly implemented into Arjuna offshore field case. Arjuna offshore field has gas-lifted wells, producing from a high-permeability reservoir. However, several wells suffer from huge production loss due to the effect of well's deviation. In deviated well, there exists frequent liquid fallback causes blockage, therefore, reducing the production. Motivated by this issue, we use CFD framework to perform gas lift optimization. We firstly adopt the geometry of gas-lifted wells as the computational domains for our simulation. An image-based meshing technique is deployed to capture the well's trajectory and internal geometry. We secondly utilize compressible Navier-Stokes equation and Finite Volume Method to evaluate the flow behavior. We capture the location of liquid fallback and liquid accumulation at elbows to estimate production loss. We consider the variation of viscosity, density, gas lift valve placement, injected gas rate, and reservoir pressure. We finally perform gradient-based optimization utilizing production loss as the objective function to obtain optimum design. The final result is then used to optimize the current design. The simulation results show that productivity index, pipe diameter, and deviation heavily influence the amount of production loss. At big pipe diameter and high deviation, the gravitational force governs the fluid flow. Therefore, slugs are developed and accumulated at elbows. This accumulation blocks gas flow and reduces production. Changing the gas injection rate affects the lifted density. High injection rate triggers segregation between the liquid and gas, while low injection rate does not reduce the liquid density. Shifting the gas lift valve placement influence the mixing between the liquid and gas. It also determines the cost of gas injection. Hence, we need to optimize both parameters at once. Six of thirty wells in Arjuna field experience severe liquid fallback, therefore, the production significantly decreases. The simulation shows up to 40% coverage of the pipe internal diameter, which blocks the gas flow. We perform the optimization by shifting the gas lift valve placement and adjusting the gas injection rate. By implementing the study result into the field case, we manage to improve the production by 20%. We provide an effective way to connect high-resolution simulation to the field design and revise the current concept in designing gas lift well completion. The simulation allows engineers to provide more insight on flow assurance in highly deviated wells.


2021 ◽  

Bekapai field was discovered in 1972, production commenced in July 1974 and the peak production was achieved in June 1978. This paper presents a challenging and comprehensive artificial lift selection process in mature offshore field, after produced by natural flow for more than 40 years. The screening process is a very important step for the long term profitability of the field. During the initial screening process, several aspects of subsurface characteristic and surface limitation have been studied to find the feasible artificial lift method. It shows that electric submersible pump (ESP) has several critical limitations to be implemented in this field. A long term evaluation then performed to evaluate the impact of any subsurface and surface variations on the performance of artificial lift. Integrated production model was used to predict the long term performance and ultimate recovery, either naturally or using gas lift and ESP. This model is a numerical simulation to describe the reservoir behavior, production system and find the optimum production strategy by integrating the reservoir models, well models and the surface network model. Impact of any variations in reservoir, well condition and surface parameters are evaluated until end of life or economical limit of this field. Based on this evaluation, gas lift and ESP have higher recovery factor than natural flow condition. The production cumulative is expected increase by more than 40% for the next 10 years. In this simulation also observed that gas oil ratio (GOR) is increasing by time, it’s a critical limitation for ESP. By performing long term evaluation and economical evaluation, it’s confirmed that gas lift is the most feasible artificial lift method for Bekapai field. This comprehensive selection process also ensures the long term profitability of the field.


2020 ◽  
Author(s):  
Simona Grifantini ◽  
Talha Saqib ◽  
Abdel Mouez M. Sabri ◽  
Osama M. Keshtta ◽  
Bader S. Albadi ◽  
...  
Keyword(s):  

Sign in / Sign up

Export Citation Format

Share Document