Enhance the Plant Operating Capacity - Maximize the Revenue/Asset Utilization

2021 ◽  
Author(s):  
Atif Javed

Abstract To explore the opportunity for maximum utilization for a Sales Gas Compression Facility (SGCF) in line with ADNOC strategy to enhance profitability and asset utilization. A technical study was conducted to increase the processing capacity up to 133% of its design limit by utilizing the available design margins. This was to identify the potential bottlenecks in the facility and suggest debottlenecking options (if bottlenecks are there). The Technical study covered the following activities: Simulation: Process simulation was performed and H&MB (Heat and Material Balance) was generatd. Engineering: Compressor adequacy checks on increased plant throughputs. Static Equipment rating and adequacy checks performed with the concurrence of original equipment menufacturerers. Line sizing adequacy checks and detailed evaluation of the piping. Adequacy check for In-line instruments like control valves, flow elements/transmitters (Note 1) Relief, blowdown and flare system adequacy check. Utilities adequacy checks. Risk assessment workshop was conducted before the capacity test run. Preparation of Test Run procedure before the actual test run. Actual plant capacity test run to verify the study findings. Note 1: Adequacy check of thermowells had been peformed separately prior to the study. It had already been established that the thermowells were adequate for the increased plant throughputs. The study has concluded the following observations for processing 133% of the design capacity Theoratically, the Sales Gas Compression Plant is adequate to handle the sales gas throughput up to 600 MMSCFD (2 running machines) considering the facts that Sales Gas Compressor suction pressure must always be kept at 32 barg through close monitoring by the operaters.If compressor suction pressure starts dropping below 32 barg, the study outcome would no more valid and the plant throughput would be reduced back to the original design capacity of 450 MMSCFD. Moreover, it was recommended to perform a field test run to validate the study outcome by following the Manageement of Change Procedure as applicable. Based on the successful 48 hours test run, it was established that the facility could handle the increased plant throughput of 600 MMSCFD by following the instructions given in the adequacy study.

Author(s):  
N.L. Velikanov ◽  
V.A. Naumov

Physical and mathematical modeling of characteristics of water-ring vacuum pumps has a number of specific features. Isothermal efficiency, i.e. the ratio of the isothermal gas compression power to the pump power consumed is used as an efficiency indicator. The article describes the existing methods of hydraulic calculation of pumping units. An analysis of physical models, numerical values of empirical coefficients is carried out. An improved algorithm for calculating water-ring vacuum pumps of different manufacturers in the framework of previously developed models is presented. The calculations of compressors manufactured by ZAO Beskom (VVN-3, VVN1-6, VVN1-12) and ERSTVAK (ELRS-45, ELRS-57) are considered as examples. The results of tests of vacuum pumps published by the manufacturers in the open press are used as the initial data for the calculations. The experimental dependences of the performance, power expended, isothermal efficiency of water-ring vacuum pumps on the suction pressure are presented. The results obtained make it possible to improve the accuracy and reliability of predicting the amount of displaced liquid or steam during the operation of the pumping unit.


2021 ◽  
Author(s):  
M. Arief Salman Alfarizi ◽  
Marja Dinata ◽  
Rizki Ananda Parulian ◽  
Kamal Hamzah ◽  
Tejo Sukotrihadiyono ◽  
...  

Abstract XJN field has implemented water injection as pressure maintenance since 1987, only one year after initial production. XJN is carbonate reservoir with weak aquifer underlying the oil zone. Initial reservoir pressure was 2,700 psi and peak production was 27,000 BOPD. Reservoir pressure was drop to 1,800 psi within 5 years of production. During 1991-2007, better injection management was performed to provide negative voidage. This action has managed to bring reservoir pressure back to its initial pressure, eventually enabling all wells to be converted from gaslift to naturalflow. In 2013, watercut has increased to 97% and several naturally flowing wells began to ceased-to-flow, then production mode was changed gradually from naturalflow to artificial lift using Electric Submersible Pump (ESP). In 2017-2020, there was rapid reservoir pressure decline around 300 psi/year while XJN water injection performance considered flawless. Voidage Replacement Ratio (VRR) was 1.3, but reservoir pressure was kept declining. This situation will cause ESP pump off on producer wells which in turn means big production loss. This paper will elaborate about the simple-uncommon-yet effective methods for problem detection and its solution to revive pressure and production. Analysis was began with observing the deviation of VRR and reservoir pressure, this was to estimate "leak" time of water injection. Next analysis was evaluation of injection rate leak off using material balance with reverse history matching. Reverse here means making reservoir pressure as main constraint rather than history matching goal. After that, it was continued with water injection flow path analysis. This was done by plotting production-injection-pressure data then make several small groups of injector-producer based on visible relationships. The purposes were to find key injector wells and to shut-in all inefficient ones. Furthermore, injection re-distribution was also performed based on VRR calculation on groups from previous step, water distribution priority was focused on key injector wells. These analysis have also paved the way for searching channeling possibility on injector wells. The results, XJN reservoir pressure showed an increasing trend of 100 psi/year after optimization was performed, with current pressure around 2000 psi. The increase in reservoir pressure has also made it possible to optimize ESP, field lifting has increased for 5000 BLPD. This project has also successfully secured XJN remaining oil. This project was racing with rapid pressure decline that will lead to early ESP pump off and production loss. The integrated subsurface analytical methods and actions being taken were simple but effective. Close monitoring on reservoir pressure, water injection and ESP parameters will be needed as field surveillance. Integrated analysis with surface facility engineering should also be carried out in the future in regards to surface network, injection rate and reservoir pressure.


2021 ◽  
Author(s):  
Dheeraj Nagwani ◽  
Sara Al Katheeri

Abstract ADNOC Gas Processing Ruwais NGL Fractionation plant receives and fractionates the NGL produced in upstream gas processing plants. After operation of newly designed upstream NGL plants, composition of NGL feedstock has become richer in Ethane and Propane. Consequently, nameplate capacity were reduced by~25%. In view of future increased NGL production, nameplate capacity of fractionation trains needs to be re-instated. Alternatively, a new fractionation train needs to be installed to accommodate additional NGL. To explore the opportunity for maximum utilization for existing trains, in line with the ADNOC strategy of enhancing profitability and asset utilization, a technical study was conducted to increase the processing capacity back to original nameplate capacity with lighter NGL composition. This was to identify the potential bottlenecks in the facility and suggest debottlenecking options with a reasonable investment. The Technical study covers the following activities: Simulation: Rigorous process simulation including the licensor units of DEO/Propane amine units Adequacy checks and identification of bottlenecks: Line sizing adequacy check and detailed hydraulic evaluation of the major piping Equipment adequacy check Relief & blowdown and flare system adequacy check Proprietary equipment/design evaluation of licensed units Adequacy check for In-line instruments like control valves, flow elements/transmitters, thermowells Rotating equipment adequacy checks performed with the concurrence from OEMs. Licensor Endorsement: Obtained the endorsement of AGRU licensor (Shell) for the increased flow rate with revised contaminant levels with recommendations of removing identified bottlenecks. Bottlenecks mitigation: Various options for bottleneck mitigation was studied and most optimum solution was selected to remove the identified bottleneck. The study has concluded that current capacity limitation was mainly due to bottlenecks in Ethane loop. Therefore, by mitigating the identified bottlenecks (i.e. replacing lines with bigger size, providing high performance trays, high performance internals, replacing few equipment's with new one etc.), the original nameplate capacity can be re-instated. The study concludes that increased NGL forecasted flow with lighter composition could be processed in existing Ruwais fractionation trains by doing minor modifications (as compared to new train). A capacity increase of ~25% was achieved with minimum investment and requirement of new fractionation train could avoided. If extensive adequacy studies are carried out to identify the bottlenecks, the capacity enhancement in existing facilities can be achieved with minimum investment and major cost for new plants/trains can be avoided.


2006 ◽  
Vol 39 (12) ◽  
pp. 1-19
Author(s):  
MICHELE G. SULLIVAN
Keyword(s):  

1975 ◽  
Vol 34 (01) ◽  
pp. 236-245 ◽  
Author(s):  
I. D Walker ◽  
J. F Davidson ◽  
P Young ◽  
J. A Conkie

SummarySix anabolic steroids were assessed for their ability to enhance plasma fibrinolytic activity in males with ischaemic heart disease. Five 17α-alkylated steroids (Ethyloestrenol, Norethandrolone, Methandienone, Methylandrostenediol and Oxymetholone) were examined and all produced a significant increase in plasma plasminogen activator as measured by the euglobulin lysis time. The only non-17α-alkylated steroid studied (Methenolone acetate) failed to enhance fibrinolysis. The 17α-alkylated steroids studied all deserve more detailed evaluation of their long term effects on plasma fibrinolytic activity.


TAPPI Journal ◽  
2014 ◽  
Vol 13 (1) ◽  
pp. 9-19 ◽  
Author(s):  
RICARDO B. SANTOS ◽  
PETER W. HART

Brownstock washing is a complex, dynamic process in which dirty wash water or weak black liquor (dissolved organic and inorganic material obtained from the pulp cooking process) is separated from pulp fibers. The use of material balance techniques is of great importance to identify potential problems and determine how well the system is operating. The kraft pulping industry was the first known to combine pulp washing with the recovery of materials used and produced in the wood cooking process. The motivation behind materials recovery is economic, and more recently, environmentally driven. The chemicals used in the kraft process are expensive as compared to those used in the sulfite process. For the kraft process to be economically viable, it is imperative that a very high percentage of the cooking chemicals be recovered. To reach such high efficiency, a variety of washing systems and monitoring parameters have been developed. Antifoam additives and processing aids have also played an important role in increasing washing effectiveness. Antifoam materials help attain washing effectiveness by preventing entrapped air from forming in the system, which allows for an easier, unimpeded flow of filtrate through the screens and washers.


Sign in / Sign up

Export Citation Format

Share Document