scholarly journals ESTIMATION OF COST AND TIME OVERRUN USING NAVFAC P-405

Author(s):  
Nikita Sadashiv Patil ◽  
Amol Thorbole

— In construction industry delays and cost overrun are significant problems so it requires investigation at planning stage. This paper gives introduction to the NAVFAC P-405, US Naval handbook for planning and estimation. This is used for site independent duration calculation and also involves steps on using NAVFAC P-405 in calculating delays. Further a method to calculate cost and time overrun for single activity using NAVFAC P-405 is explained in detail with case study.

2015 ◽  
Vol 77 (16) ◽  
Author(s):  
Nasiru Zakari Muhammad ◽  
Ali Keyvanfar ◽  
Muhd Zaimi Abd Majid ◽  
Arezou Shafaghat ◽  
Aliyu Muhammad Magana ◽  
...  

Variation does not only affect labour productivity but also leads to the dispute, time and cost overrun. Consequently, it affects projects performance. It is, therefore, imperative for construction professionals to eliminate unnecessary additional cost from a project so as to optimize the client’s benefit against input resources. This paper identifies and examines the most significant causes that contribute to the variation orders. Also, Nigerian construction industry is used as a case study. Variation orders causing factors were assessed. Questionnaires were administered to clients, consultants and contractors to elicit information regarding variation causing factors. These factors were analyzed using frequency aggregation, mean score method and subsequently ranked according to their severity. The result revealed three most significant causes of variation which are: ‘Change of plan’’ with the highest frequency of 58% then followed by ‘‘Conflicting contract documents (50%). The next most frequent causing factors were the “substitution of materials” and “change in design” each with frequency of 43%. The least causing factor of variation was the “error and omission in design” with the frequency of 10%. Also differing site condition, new government regulation, weather condition were identified as other cause of variation with the frequency of 27%, 29% and 10% respectively.  It has also shown that most critical source of variation order is the client due to change of plan then followed by consultant due to conflicting contract document.


2016 ◽  
Vol 23 (1) ◽  
pp. 125-136 ◽  
Author(s):  
Roya DERAKHSHANALAVIJEH ◽  
Jose Manuel Cardoso TEIXEIRA

Cost overrun in construction projects is a common issue affecting project performance, and Gas-Oil con­struction projects in Iran are no exception. This paper presents the results of a questionnaire conducted to identify and evaluate the relative importance of the significant factors contributing to the Gas-Oil construction industry of Iran as a case study for developing countries. The survey respondents included project owners, contractors and consultants in­volved in Iranian Gas-Oil construction projects. The results of the survey revealed that the main causes of cost overrun in this industry include inaccurate cost estimations, improper planning, frequent design changes, inadequate labour/skill availability, inflation of costs of machinery, labour, raw material and transportation prices. The first three factors are the project consultants’ responsibility and the appointment of qualified consultants and personnel training are strongly recommended to alleviate cost overrun. The paper also reviews and compares findings of a set of similar researches in a number of developing countries.


2020 ◽  
Vol 11 (4) ◽  
pp. 122
Author(s):  
Yaser Gamil ◽  
Abdulsalam Alhagar

Since the World Health Organization (WHO) announced the coronavirus 2019 (COVID-19) outbreak as a pandemic, many countries have declared a complete national lockdown after a remarkable spike in COVID 19 cases. These decisions have restricted the movement of people and resulted in a complete shutdown of many businesses across many sectors. The construction industry, as a significant growth driver of the economy with no exception, has also been completely shut down. All the developments and projects were postponed until further notice. It is, therefore, a prudent to address the impact of the pandemic at the outset and end of the crisis to prepare for any future possibility and gain lessons for plans. This study aims to investigate the effect of COVID 19 on the construction industry's survival. The impacts and fallout have been determined and evaluated through the recruitment of construction experts and practitioners. The impacts have been classified into different groups which include economic, human resources. The study implied two methods include exploratory interviews and questionnaire surveys. The study found the most prominent impacts of COVID 19 are the suspension of projects, labour impact and job loss, time overrun, cost overrun, and financial implications. The findings of this study shed light on the consequences of the sudden occurrence of pandemic and raise awareness of the most critical impacts which can’t be overlooked. The findings also help project stakeholders to realise the sequences of the sudden epidemic and prepare for the worst-case scenario during the planning stage of the construction projects.


Author(s):  
Ahmed Salem Ahmed Marey Alhammadi ◽  
◽  
Aftab Hameed Memon ◽  

UAE construction industry frequently faces poor cost performance which commonly known as cost overrun problem. This problem is resulted from several factors and it is important to identify these cost overrun factors in order to avoid and minimize it. Hence, this paper focused on determined the relevancy of factors affecting cost performance in construction projects of UAE. Through a review of past research works conducted globally, 27 factors of cost overrun were listed and used for developing a structured questionnaire. A survey was conducted with 33 practitioners from client, consultant and contractors organizations involved in handling construction projects in UAE. The respondents were requested to state their perception regarding the relevancy of each of the factors that was perceived in context with cost overrun issue using 5-points Likert scale. The responses were analysed using average index method and the results found that all the 27 factors are relevant with construction industry of UAE in causing cost overrun. These factors can be used for further investigation to uncover critical problems of cost overrun.


Buildings ◽  
2021 ◽  
Vol 11 (6) ◽  
pp. 260
Author(s):  
James Ellis ◽  
David John Edwards ◽  
Wellington Didibhuku Thwala ◽  
Obuks Ejohwomu ◽  
Ernest Effah Ameyaw ◽  
...  

This research explores the failure of competitively tendered projects in the UK construction industry to procure the most suited contractor(s) to conduct the works. Such work may have equal relevance for other developed nations globally. This research seeks to teach clients and their representatives that “lowest price” does not mean “best value”, by presenting a case study of a successfully negotiated tender undertaken by a small-to-medium enterprise (SME) contractor; SME studies are relatively scant in academic literature. By applying the “lessons learnt” principle, this study seeks to improve future practice through the development of a novel alternative procurement option (i.e., negotiation). A mixed philosophical stance combining interpretivism and pragmatism was used—interpretivism to critically review literature in order to form the basis of inductive research to discuss negotiation as a viable procurement route, and pragmatism to analyse perceptions of tendering and procurement. The methods used follow a three-stage waterfall process including: (1) literature review and pilot study; (2) quantitative analysis of case study data; and (3) qualitative data collection via a focus group. Our research underscores the need to advise clients and their representatives of the importance of understanding the scope of works allowed within a tender submission before discounting it based solely on price. In addition, we highlight the failings of competitive tendering, which results in increased costs and project duration once the works commence on site. These findings provide new contemporary insight into procurement and tendering in the construction industry, with emphasis on SME contractors, existing relationships, and open-book negotiation. This research illustrates the adverse effects of early cost estimates produced without first securing a true understanding of project buildability and programming. Our work concludes with a novel insight into an alternative procurement option that involves early SME contractor involvement in an open-book environment, without the need for a third-party cost control.


2021 ◽  
Vol 13 (15) ◽  
pp. 8238
Author(s):  
Noemi Bakos ◽  
Rosa Schiano-Phan

To transform the negative impacts of buildings on the environment into a positive footprint, a radical shift from the current, linear ‘make-use-dispose’ practice to a closed-loop ‘make-use-return’ system, associated with a circular economy, is necessary. This research aims to demonstrate the possible shift to a circular construction industry by developing the first practical framework with tangible benchmarks for a ‘Circular University Campus’ based on an exemplary case study project, which is a real project development in India. As a first step, a thorough literature review was undertaken to demonstrate the social, environmental and economic benefits of a circular construction industry. As next step, the guideline for a ‘Circular University Campus’ was developed, and its applicability tested on the case study. As final step, the evolved principles were used to establish ‘Project Specific Circular Building Indicators’ for a student residential block and enhance the proposed design through bioclimatic and regenerative design strategies. The building’s performance was evaluated through computational simulations, whole-life carbon analysis and a circular building assessment tool. The results demonstrated the benefits and feasibility of bioclimatic, regenerative building and neighbourhood design and provided practical prototypical case study and guidelines which can be adapted by architects, planners and governmental institutions to other projects, thereby enabling the shift to a restorative, circular construction industry.


Author(s):  
Soumith Kumar Oduru ◽  
Pasi Lautala

Transportation industry at large is a major consumer of fossil fuels and contributes heavily to the global greenhouse gas emissions. A significant portion of these emissions come from freight transportation and decisions on mode/route may affect the overall scale of emissions from a specific movement. It is common to consider several alternatives for a new freight activity and compare the alternatives from economic perspective. However, there is a growing emphasis for adding emissions to this evaluation process. One of the approaches to do this is through Life Cycle Assessment (LCA); a method for estimating the emissions, energy consumption and environmental impacts of the project throughout its life cycle. Since modal/route selections are often investigated early in the planning stage of the project, availability of data and resources for analysis may become a challenge for completing a detailed LCA on alternatives. This research builds on such detailed LCA comparison performed on a previous case study by Kalluri et al. (2016), but it also investigates whether a simplified LCA process that only includes emissions from operations phase could be used as a less resource intensive option for the analysis while still providing relevant outcomes. The detailed LCA is performed using SimaPro software and simplified LCA is performed using GREET 2016 model. The results are obtained in terms of Kg CO2 equivalents of GHG emissions. This paper introduces both detailed and simplified methodologies and applies them to a case study of a nickel and copper mine in the Upper Peninsula of Michigan. The analysis’ are done for three modal alternatives (two truck routes and one rail route) and for multiple mine lives.


Sign in / Sign up

Export Citation Format

Share Document