Journal of Civil Engineering and Management
Latest Publications


TOTAL DOCUMENTS

1774
(FIVE YEARS 179)

H-INDEX

39
(FIVE YEARS 8)

Published By Vilnius Gediminas Technical University

1822-3605, 1392-3730

2022 ◽  
Vol 28 (2) ◽  
pp. 93-105
Author(s):  
Muhammad Khalid Hafiz ◽  
Qaiser-uz-Zaman Khan ◽  
Sohaib Ahmad

Different researchers have performed seismic hazard assessment studies for Pakistan using faults sources which differ from Building Code of Pakistan (BCP 2007) with diverse standard deviations. The results of seismic hazard studies indicate that BCP requires gross revision considering micro and macro level investigations. The recent earthquakes in Pakistan also damaged bridge structures and some studies have been conducted by different researchers to investigate capacity of existing bridges. The most of bridge stock in Pakistan has been designed assuming seismic loads as 2%, 4% and 6% of dead loads following West Pakistan Code of Practice for Highway Bridges. The capacity of eight selected real bridges, two from each seismic zone 2A, 2B, 3 & 4 is checked against BCP demands. Static and dynamic analyses were performed and the piers were checked for elastic limits. It is established that piers are on lower side in capacity and the bridges in zone 2A are generally less vulnerable. Whereas the bridges in zone 2B, 3 and 4 are vulnerable from medium to very high level. Hence, an in-depth analytical vulnerability study of bridge stock particularly in high-risk zone needs to be conducted on priority and appropriate seismic retrofitting schemes need to be proposed.


2022 ◽  
Vol 28 (2) ◽  
pp. 81-92
Author(s):  
Chihcheng Chen ◽  
Ban-Jwu Shih ◽  
Ching-Jiang Jeng

The main structure of the Baishihu suspension bridge was connected to the anchor foundations by three main steel cables. The wooden pedestrian deck was fixed to the main steel cables using steel beams and was stabilized by two stabilizing cables. The stabilizing cables and bridge body were joined by 44 steel connecting rods. Therefore, the slope stability at the anchorage foundations of the main steel cables, as well as the performance monitoring and analysis of the main steel cables and stabilizing cables, are critical to the overall performance of the suspension bridge. This paper discusses the performance monitoring and analysis of the steel cable deflection and cable strength for this bridge, as well as the main considerations and results of the stability analysis of the bridge abutments and side slopes of the two banks. Water-level observation wells, inclinometers, and tiltmeters monitoring were used to record reference data for the analysis of the slope stability performance. Additionally, the three-dimensional dynamic analysis program VFIFE was used to analyze the deformation and motion of the bridge. The final steady-state results were used to compare the static design value and monitoring data. The dynamic response before the final steady state was also observed.


2022 ◽  
Vol 28 (2) ◽  
pp. 120-133
Author(s):  
Jeffrey Boon Hui Yap ◽  
Canwin Guan Ying Lam ◽  
Martin Skitmore ◽  
Nima Talebian

The adoption rate of new technologies is still relatively low in the construction industry, particularly for mitigating occupational safety and health (OSH) risks, which is traditionally a largely labor-intensive activity in developing countries, occupying ill-afforded non-productive management resources. However, understanding why this is the case is a relatively unresearched area in developing countries such as Malaysia. In aiming to help redress this situation, this study explored the major barriers involved, firstly by a detailed literature review to identify the main barriers hampering the adoption of new technologies for safety science and management in construction. Then, a questionnaire survey of Malaysian construction practitioners was used to prioritize these barriers. A factor analysis further identified six major dimensions underlying the barriers, relating to the lack of OSH regulations and legislation, technological limitations, lack of genuine organizational commitment, prohibitive costs, poor safety culture within the construction industry, and privacy and data security concerns. Taken together, the findings provide a valuable reference to assist industry practitioners and researchers regarding the critical barriers to the adoption of new technologies for construction safety management in Malaysia and other similar developing countries, and bridge the identified knowledge gap concerning the dimensionality of the barriers.


2022 ◽  
Vol 28 (2) ◽  
pp. 106-119
Author(s):  
Weiwei Zuo ◽  
Qiankun Wang ◽  
Peng Li

The performance of a construction project can be severely harmed by its participants’ rent-seeking. In order to prevent such attempt, this research integrates the evolutionary game theory with system dynamics method to simulate the impact of the change of some factors that may cause/reduce rent-seeking. Based on the analysis of the behavioral characteristics and interactive relationships of the main participants (the owner, supervisor, and contractor), an evolutionary game model is constructed and simulated with the method of system dynamics based on the replication dynamic equation of the mixed strategy solution of the three-party static game model. By assigning the parameters of project scale, supervision likelihood, supervision success rate, supervision cost, and penalty intensity, the interaction mechanism of the participants on each factor is revealed through a case-based simulation. The results show that the impacts of these factors on participants’ rent-seeking decisions are significantly different. Furthermore, some management suggestions are provided to prevent rent-seeking for project owner according to the research conclusions. This research can help the project owners take proper measures to prevent rent-seeking of the supervisors and the contractors to improve the performances of the projects.


2022 ◽  
Vol 28 (1) ◽  
pp. 1-5
Author(s):  
Artūras Kaklauskas ◽  
Edmundas Kazimieras Zavadskas ◽  
Ieva Ubartė
Keyword(s):  

Celebrating the 55th anniversary of the Journal of Civil Engineering and Management: editor’s introduction. Journal of Civil Engineering and Management, 28(1), 1–5.


2021 ◽  
Vol 0 (0) ◽  
pp. 1-19
Author(s):  
Lelin Lv ◽  
Huimin Li Li ◽  
Zhuofu Wang ◽  
Chengyi Zhang ◽  
Ran Qiao

Major infrastructure projects (MIPs) possess significant strategic positions in the national economy and social development. However, recently, the rent-seeking behavior between supervision units and project contractors has intensified in project construction. This paper aims to study the behavior decision-making of stakeholders in rent-seeking behavior supervision system of MIPs. In the complex and uncertain environment of MIPs, game players have cognitive bias and value perception preference. Therefore, this study introduced prospect theory and constructed the perceived return matrix and evolutionary game model of MIP rent-seeking behavior supervision among project owners, supervision units, and project contractors. From the perspective of risk perception theory, the reasons for the behavioral tendencies of game participants and the conditions for the steady state of strategy selection were explored through system dynamics simulations. The results showed that the stable state of the optimal strategy in the rent-seeking behavior supervision system of MIPs is related to the cognitive bias of the game players and is influenced by the level of regulation cost, the intensity of punishment and the size of accident losses. The contribution of this study lies in providing theoretical basis and decision support for constructing a long-term preventive mechanism for rent-seeking activities in MIPs.


2021 ◽  
Vol 0 (0) ◽  
pp. 1-13
Author(s):  
Shuwen Guo ◽  
Junwu Wang

Integrated Project Delivery (IPD) is regarded as an effective project delivery method that can deal with the challenge of the rapid development of the architecture, engineering, and construction (AEC) industry. In the IPD team, the alliance profit is not distributed fairly and effectively due to uncertainty, preventing the achievement of the IPD project goals. This study focuses on optimizing the profit distribution among stakeholders in IPD projects and uses quadratic programming models to solve fuzzy cooperative games in the IPD. A payoff function is used in the fuzzy alliance to determine the characteristics of the interval-valued fuzzy numbers, and different weights of the alliance and the efficiency of the player’s participation in the IPD are considered in the profit distribution. A case study is conducted, and the results of the proposed method are compared with those of crisp cooperative games. The results show that the fuzzy cooperative game increases the profit of participants in IPD projects. It is more practical to use weight fuzzy cooperative games than crisp games to express imputation. Moreover, the quadratic programming models and methods result in a fair and efficient profit distribution scheme in IPD projects.


2021 ◽  
Vol 0 (0) ◽  
pp. 1-12
Author(s):  
Junho Choi ◽  
Jaepil Choi

Residential buildings are being renovated around the world, especially apartments, their solutions are becoming increasingly important. The number of apartments in Korea that are more than 20 years old has reached 4.3 million, and the problem of aged apartments now needs to be addressed. Consequently, the government is promoting the improvement of the residential environment through renovation. In a renovation project, a feasibility study is conducted at the outset, but many apartments fail to complete the renovation process during the project. One reason is that feasibility studies focus on economics without sufficiently considering the technical aspects of the redesign. This study developed a feasibility study model that can pre-evaluate apartment renovation in terms of technology. We selected 27 criteria that affect technical feasibility, and the analytic hierarchy process (AHP) was performed with experts to derive the relative importance of the criteria. Based on the weight of the criteria, we developed an apartment renovation technology feasibility study model. As a result of the study, unit and complex conditions were found to have a significant influence on renovation. Moreover, it was found that the technical feasibility study model can quantitatively evaluate the technical aspects of an apartment to be renovated.


2021 ◽  
Vol 0 (0) ◽  
pp. 1-14
Author(s):  
Meijing Hao ◽  
Wenzhong Zheng ◽  
Wei Chang

The objective of this study is to evaluate the axial load-bearing capacity of section-enlargement concrete columns. To reach the objection, a new strengthened method in which columns are jacketed with a large welded octagonal stirrup at the center and four spiral stirrups at the corners of column is developed. The new section-enlargement method avoids interrupting existing columns and improves the reliability of strengthened part, besides, the confining stress generated by octagonal stirrup and spiral stirrups enhances the compressive strength and deformability of strengthened columns. In addition, sixteen large-scale concrete columns strengthened by the new strengthened method were tested under axial compressive loads. The experimental results show that the axial compression ratio of existing column generates stressstrain lag in strengthened part and decreases the load-bearing capacity of specimens; the stirrups in strengthened part significantly enhance the axial load-bearing capacity of specimens. According to confinement conditions, the cross-section of specimens is divided into five parts and the confinement factor for each part is calculated to establish the prediction models for the load-bearing capacity of specimens. Furthermore, by comparing the results between the developed model and existing models, the developed model has high accuracy in evaluating the load-bearing capacity of strengthened columns.


2021 ◽  
Vol 0 (0) ◽  
pp. 1-17
Author(s):  
Yi-Kai Juan ◽  
Ling-Er Liou

The Ministry of Education (MOE) of Taiwan invests about NTD 30 billion a year in Public School Building Projects (PSBPs). However, 95% of the PSBPs have been extended and have incurred increased costs. A PSBP performance evaluation and prediction system was established by using the Fuzzy Delphi Method (FDM), association rules and an Artificial Neural Network (ANN). Sixty-two Taiwanese PSBPs were used as the samples, while eleven high correlation factors that influence the project performance of PSBPs were defined, and the reasons leading to the poor project performance were discussed in this study. Moreover, the results of the test cases operated by ANN showed that the accuracy rate for schedule and cost variability predictions can reach 84%. The high accuracy rate indicated the reliability of priority control for high-risk projects in the future. The proposed approach can be provided to clients, design and construction firms, and project managers to understand the project performance in real time and to establish a dynamic tracking review and response measures for improving the overall project satisfaction.


Sign in / Sign up

Export Citation Format

Share Document