scholarly journals Computational Fluid Dynamic Modelling and Optimisation of Wastewater Treatment Plant Bioreactor Mixer

Author(s):  
Andrew Elshaw ◽  
N. M. S. Hassan ◽  
M. M. K. Khan

This study aims to determine the optimal configuration (position and operation duration) for wall mounted mechanical mixers based on the comparison of three-dimensional computational fluid dynamics (CFD) modelling results and physical data collected from the treatment plant. A three-dimensional model of anoxic zone 1, 2 and 3 of Northern Wastewater Treatment Plant (WWTP) located at Cairns Regional Council, Cairns, Queensland, Australia was developed and validated. The model was used to simulate the flow pattern of the WWTP and the simulation results are in good agreement with the physical data varying between 0% to 15% in key locations. The anoxic zones were subject to velocities less than the desired 0.3 metres per second however results for suspended solids concentration indicate that good mixing is being achieved. Results for suspended solids concentrations suggest that the anoxic zones are towards the upper limits recommended by literature for specific power dissipation. The duration for operation of mechanical mixers was investigated and identified that the duration could be reduced from 900 seconds down to 150 seconds. Alternative mixer positioning was also investigated and identified positioning which would increase the average flow velocity with decreased duration (150 seconds). The study identified that Council may achieve savings of $24,000 per year through optimisation of the mechanical mixers.

Energies ◽  
2018 ◽  
Vol 11 (12) ◽  
pp. 3530 ◽  
Author(s):  
Andrew Elshaw ◽  
Nur M. S. Hassan ◽  
M. Masud K. Khan

This study aims to determine the optimal configuration (position and operation duration) for wall mounted mechanical mixers based on the comparison of three-dimensional computational fluid dynamics (CFD) modelling results and physical data collected from the treatment plant. A three dimensional model of anoxic zone in 1, 2 and 3 of Northern Wastewater Treatment Plant (NWWTP) located at Cairns Regional Council, Cairns, Queensland, Australia was developed and validated. The model was used to simulate the flow pattern of the WWTP and the simulation results are in good agreement with the physical data varying between 0% to 15% in key locations. The anoxic zones were subject to velocities less than the desired 0.3 m per second however results for mixed liquor suspended solids (MLSS) concentration indicate that good mixing is being achieved. Results for suspended solids concentrations suggest that the anoxic zones are towards the upper limits recommended by literature for specific power dissipation. The duration for operation of mechanical mixers was investigated and identified that the duration could be reduced from 900 s down to 150 s. Alternative mixer positioning was also investigated and identified positioning which would increase the average flow velocity with decreased duration (150 s). The study identified that Council may achieve savings of $28,500 per year through optimisation of the mechanical mixers and would be expected to extend the operational life of the mixers.


1995 ◽  
Vol 31 (12) ◽  
pp. 171-183 ◽  
Author(s):  
M. M. Saqqar ◽  
M. B. Pescod

The performance of the primary anaerobic pond at the Alsamra Wastewater Treatment Plant in Jordan was monitored over 48 months. Overall averages for the removal efficiencies of BOD5, COD and suspended solids were 53%, 53% and 74%, respectively. An improvement in removal efficiency with increase in pond water temperature was demonstrated. A model, which takes into account the variability of raw wastewater at different locations, has been developed to describe the performance of a primary anaerobic pond in terms of a settleability ratio for the raw wastewater. The model has been verified by illustrating the high correlation between actual and predicted pond performance.


2012 ◽  
Vol 7 (1) ◽  
Author(s):  
S. S. Fatima ◽  
S. Jamal Khan

In this study, the performance of wastewater treatment plant located at sector I-9 Islamabad, Pakistan, was evaluated. This full scale domestic wastewater treatment plant is based on conventional activated sludge process. The parameters which were monitored regularly included total suspended solids (TSS), mixed liquor suspended solids (MLSS), mixed liquor volatile suspended solids (MLVSS), biological oxygen demand (BOD), and chemical oxygen demand (COD). It was found that the biological degradation efficiency of the plant was below the desired levels in terms of COD and BOD. Also the plant operators were not maintaining consistent sludge retention time (SRT). Abrupt discharge of MLSS through the Surplus Activated sludge (SAS) pump was the main reason for the low MLSS in the aeration tank and consequently low treatment performance. In this study the SRT was optimized based on desired MLSS concentration between 3,000–3,500 mg/L and required performance in terms of BOD, COD and TSS. This study revealed that SRT is a very important operational parameter and its knowledge and correct implementation by the plant operators should be mandatory.


Author(s):  
Tomáš Vítěz ◽  
Jana Ševčíková ◽  
Petra Oppeltová

This paper is focused on primary, secondary, and total efficiency evaluation of the wastewater treatment process for chosen small wastewater treatment plant (WWTP) located near the Moravian Karst. Eight wastewater samples were taken during one year in three sampling profiles of WWTP: biochemical oxygen demand (BOD), chemical oxygen demand (COD), suspended solids (SS), pH, ammonia nitrogen (N-NH4), nitrite nitrogen (N-NO2), nitrate nitrogen (N-NO3), inorganic nitrogen (Ninorg), total phosphorus (Ptotal). Treatment efficiency by reduction was calculated for all laboratory analyzed indicators and average values were determined for the whole period. Calculated treatment efficiency of indicators BOD, COD and suspended solids was compared with the permissible minimum treatment efficiency of discharged waste water by Government Regulation No. 61/2003 Coll., for the WWTP from 500 to 2 000 PE. Permissible minimum treatment efficiency is not legislatively determined for the primary and secondary level. The results of the work will be used especially to compare results with other similar works.Analyzed values ​​of parameters BOD, COD, suspended solids, N-NH4 at the outflow from wastewater treatment plant were compared with the permissible maximum values at the outflow of the WWTP which the municipality has an obligation to respect according to the decision issued by the District Environment Authority.


2011 ◽  
Vol 22 (6) ◽  
pp. 1150-1155 ◽  
Author(s):  
Nathália C. Viecelli ◽  
Eduardo R. Lovatel ◽  
Eduardo M. Cardoso ◽  
Irajá Nascimento Filho

2005 ◽  
Vol 51 (11) ◽  
pp. 159-166
Author(s):  
E. Ubay-Cokgor ◽  
C.W. Randall ◽  
D. Orhon

In this paper, the performance of the Tyson Foods wastewater treatment plant with an average flow rate of 6500 m3/d was evaluated before and after upgrading of the treatment system for nitrogen removal. This study was also covered with an additional recommendation of BIOWINTM BNR program simulation after the modification period to achieve an additional nutrient removal. The results clearly show that the upgrading was very successful for improved nitrogen removal, with a 57% decrease on the total nitrogen discharge. There also were slight reductions in the discharged loads of biological oxygen demand, total suspended solids, ammonium and total phosphorus with denitrification, even though the effluent flow was higher during operation of the nitrogen removal configuration.


1994 ◽  
Vol 29 (12) ◽  
pp. 237-245
Author(s):  
Arno Grau ◽  
Michael Haeusler ◽  
Wälti Schmitt

Micro-straining as an advance treatment of wastewater has been evaluated in a half as well as full technical unit. Mesh dimensions of 10, 20 and 40 μ have been used, straining velocities between 10 to 35 m/h have been measured and suspended solids retention of 75 – 85 % could be achieved. The investment and operational costs are lower than those of other systems, e.g. sand filtration.


2020 ◽  
Vol 81 (9) ◽  
pp. 1863-1869
Author(s):  
A. Bawiec ◽  
K. Pawęska

Abstract Wastewater treatment in semi-natural systems, such as a hydroponic lagoon operating as the third stage of purification, is becoming more and more popular because of the efficiency of nutrient removal. Very often treatment processes in hydroponic ditches are supported by algal growth, which can cause an increase in the concentration of total suspended solids in the outflow from the wastewater treatment plant. The aim of this study was to analyse changes in the granulometric composition of particles in the hydroponic lagoon operating as the third stage of wastewater purification in a municipal wastewater treatment plant (WWTP) in Poland. Measurements of the particle sizes were made with the use of the laser diffraction method. The results showed that the size of the particles in the hydroponic lagoon varied from 0.01 to 1000 μm. Analyses of the average diameters D(3.2) and D(4.3) showed that particles have low reactivity but good sedimentation properties and their fractal dimensions are usually higher than 2.0, which indicated that they had well-developed surfaces. Most of the particles flowing out of the WWTP were probably algae or particles that could adsorb other pollutants onto their surfaces. The use of laser granulometry for particle identification might be useful in characterizing the total suspended solids as well as helping to develop cheaper and more efficient methods for its removal.


Sign in / Sign up

Export Citation Format

Share Document