Sour Gas Well Completion Practices in the Foothills, Western Canada

1982 ◽  
Vol 34 (09) ◽  
pp. 2113-2124 ◽  
Author(s):  
M.R. Millian
2021 ◽  
Author(s):  
Ming-Lei Yeow

Abstract A large gas field with carbonate formations was discovered about 200 km (kilometers) offshore, in water depths of 108 m (meters) below mean sea level. Flow analysis and reservoir depletion studies by the Operator show 7" tubing is required to provide high production rates of about 80 to 120 million Standard Cubic Feet per day (mmscfd) per well as the optimum production and depletion strategy for the field. The field presents significant challenges to well construction and completion. These challenges were considered in the design stage to optimise well completion design and operations. This paper describes the approach and methods used to overcome the challenges in the design and execution stage to optimise the completion design and to manage challenges during construction of the well including: –Due to loss of circulation in the fractured gas carbonate reservoirs, the well will be drilled with Pressurised Mud Cap Drilling (PMCD), a form of Managed Pressure Drilling (MPD). Thus, the design needs to provide for installing the well completion in this condition–The wells required heavy mud weight for drilling and thus, heavy brine weights for well completion. Challenges to avoid or minimise the loss of high cost heavy brine were considered–High reservoir temperatures of about 325 deg. F (degrees Fahrenheit) which lead to challenges of ensuring equipment will continue to work in high temperature environments, high loads / stresses on completion & casing during production, and Wellhead & Christmas Tree & Flowline movement / growth.–Presence of sour gas and CO2 (Carbon Dioxide) which require optimising metallurgy of tubulars and downhole equipment, considering corrosion and cost requirements–Understanding loads / stresses on the tubing and casings with high flowrates and high flowing temperatures–Concerns with formation collapse during production–Corrosion studies to optimise material selection and ensuring well integrity for at least twenty (20) years’ field life–Manage hydrates and scaling while carrying out well completion, well clean and well test operations and during the field life–Acceptable seals, barriers and completion equipment to manage high pressure gas–Wellhead and Christmas Tree that can take the high temperature and sour gas content–Well clean-up and testing after completion in conjunction with drilling operations–Cost and time optimisation to maximize returns on investment for the project. Well completion engineering studies were carried out for each challenge or consideration. Experiences and lessons from similar gas fields were also considered. Corrosion laboratory analysis was carried out to optimise the corrosion resistant alloy for the completion tubular and completion equipment. For each solution to the challenge, cost and time considerations were reviewed and studied to optimise the design, cost, integrity and safety of the wells and operations. This paper describes the approaches and methods taken by the Operator to optimise the Big Bore Gas Well Completion Design including some lessons for improvement after successfully drilling, completing, clean-up and testing of the first well with this completion design.


1983 ◽  
Vol 35 (01) ◽  
pp. 40-46 ◽  
Author(s):  
Kevin J. Kilstrom
Keyword(s):  
Gas Well ◽  

2011 ◽  
Author(s):  
Mohammed Jasem Al-Saeedi ◽  
Fayez Abdulrahman Al Fayez ◽  
Dakhil Rasheed Al Enezi ◽  
mahesh sounderrajan ◽  
Mishary Najeeb Al-Mudhaf ◽  
...  
Keyword(s):  
Gas Well ◽  

2015 ◽  
Author(s):  
A. Ebrahimi ◽  
P. J. Schermer ◽  
W. Jelinek ◽  
D. Pommier ◽  
S. Pfeil ◽  
...  

2021 ◽  
Author(s):  
Ying Wang ◽  
Xin Zheng ◽  
Li Li ◽  
Jianbo Yuan ◽  
Minh Vo ◽  
...  

Abstract This paper describes the successful resin squeeze operation to seal off a micro-annulus between the 7" and 9-5/8" casings on a sour gas well located in Sichuan Basin, China. Integrated plug and abandonment were also essential to eliminate the risk of potential H2S exposure presented to the residents around this area. Resin, as a new alternative sealing technology, was technically evaluated, laboratory tested, and then chosen for squeezing into a micro-annulus to stop gas migration for its solids-free and low-viscosity properties compared to a conventional cement. The squeeze job was designed by taking the casing yield strength as the pressure limit (Confirmed by caliper log the casing was in good condition) and determining the resin pumping volume based on estimated resin squeeze volume and the remaining resin plug length. A "Braden-head" squeeze method was selected considering the low injection rate observed during the water injection test. Both stage-up and stage down squeezing techniques (hesitation squeeze of increasing and decreasing wellhead pressure stage by stage) were performed to maximize the injected volume of the resin sealant. A total of 800 L of 9.16 lb/gal resin was placed into a 4 ft milled interval, and 50 L were successfully squeezed into the 7" × 9-5/8" casing annulus. An operational learning was that resin injection is greatly improved during the stage-down process while keeping the casing annulus open. Evidence that the micro-annulus leak path had been sealed was an observation of 0 psi on the 7" × 9-5/8" casing annulus after resin fully set. The method of locating the optimal spot to squeeze resin involved noise logging to analyze for a potential gas source in the annulus. The post job results confirmed that resin acts effectively as an annular barrier in the repair of gas leaks in the small volume situations where micro-annulus exists in the cement sheath. For large voids such as inside 7" casing, a combination of cement plug plus mechanical barrier is recommended to be placed directly above resin plugs to complete permanent plug and abandonment of the wellbore.


2018 ◽  
Author(s):  
Jiandong Wang ◽  
Huali Zhang ◽  
Yufei Li ◽  
Dajiang Zhu ◽  
Chuanlei Wang

2020 ◽  
Author(s):  
Ardian Nengkoda ◽  
Abdallah Qahtani ◽  
Sami Logan ◽  
Mostafa Youssef ◽  
Alastair Sinker

2013 ◽  
Vol 712-715 ◽  
pp. 1096-1099
Author(s):  
Ling Feng Li

For natural gas well in sour gas reservoirs, very serious corrosion in the completed well system is an important factor of gas production system life. In order to ensure the long-term development of gas wells, this paper mainly introduces material corrosion prevention technology in the completed well system, such as corrosion-resistant alloy steel corrosion control technology, bimetallic combination tubing, corrosion inhibitor technology and so on. By taking LJ Gas Field as an example, this paper introduces the material corrosion prevention technology in the completed well system in LJ Gas Field. For application in the completed well system in LJ Gas Field, the technology above have good performance of corrosion resistance.


2013 ◽  
Vol 690-693 ◽  
pp. 1516-1519
Author(s):  
Ling Feng Li

For natural gas well in sour gas reservoirs, very serious corrosion in the gas well string is an important factor of gas production system life. In order to ensure the long-term development of gas wells, this paper mainly introduces the tubing and casing corrosion in sour gas reservoirs, corrosion-resistant material selection of tubing and casing in sour gas reservoirs and proposes the optimization idea and technique of tubing material selection.. By taking W 63 well as an example, this paper optimizes the material selection of production casing for W 63 well. For application, the optimal materials of gas well string in W 63 well have good performance of corrosion resistance.


Sign in / Sign up

Export Citation Format

Share Document