Optimising Big Bore Gas Well Completion Design in a Carbonate Field

2021 ◽  
Author(s):  
Ming-Lei Yeow

Abstract A large gas field with carbonate formations was discovered about 200 km (kilometers) offshore, in water depths of 108 m (meters) below mean sea level. Flow analysis and reservoir depletion studies by the Operator show 7" tubing is required to provide high production rates of about 80 to 120 million Standard Cubic Feet per day (mmscfd) per well as the optimum production and depletion strategy for the field. The field presents significant challenges to well construction and completion. These challenges were considered in the design stage to optimise well completion design and operations. This paper describes the approach and methods used to overcome the challenges in the design and execution stage to optimise the completion design and to manage challenges during construction of the well including: –Due to loss of circulation in the fractured gas carbonate reservoirs, the well will be drilled with Pressurised Mud Cap Drilling (PMCD), a form of Managed Pressure Drilling (MPD). Thus, the design needs to provide for installing the well completion in this condition–The wells required heavy mud weight for drilling and thus, heavy brine weights for well completion. Challenges to avoid or minimise the loss of high cost heavy brine were considered–High reservoir temperatures of about 325 deg. F (degrees Fahrenheit) which lead to challenges of ensuring equipment will continue to work in high temperature environments, high loads / stresses on completion & casing during production, and Wellhead & Christmas Tree & Flowline movement / growth.–Presence of sour gas and CO2 (Carbon Dioxide) which require optimising metallurgy of tubulars and downhole equipment, considering corrosion and cost requirements–Understanding loads / stresses on the tubing and casings with high flowrates and high flowing temperatures–Concerns with formation collapse during production–Corrosion studies to optimise material selection and ensuring well integrity for at least twenty (20) years’ field life–Manage hydrates and scaling while carrying out well completion, well clean and well test operations and during the field life–Acceptable seals, barriers and completion equipment to manage high pressure gas–Wellhead and Christmas Tree that can take the high temperature and sour gas content–Well clean-up and testing after completion in conjunction with drilling operations–Cost and time optimisation to maximize returns on investment for the project. Well completion engineering studies were carried out for each challenge or consideration. Experiences and lessons from similar gas fields were also considered. Corrosion laboratory analysis was carried out to optimise the corrosion resistant alloy for the completion tubular and completion equipment. For each solution to the challenge, cost and time considerations were reviewed and studied to optimise the design, cost, integrity and safety of the wells and operations. This paper describes the approaches and methods taken by the Operator to optimise the Big Bore Gas Well Completion Design including some lessons for improvement after successfully drilling, completing, clean-up and testing of the first well with this completion design.

2012 ◽  
Vol 485 ◽  
pp. 429-432
Author(s):  
Ling Feng Li ◽  
Xiao Ming Liu ◽  
Zhi Qiang Huang

For natural gas well with high content of CO2 and H2S, very serious corrosion in the gas well string is an important factor of gas production system life. In order to ensure the long-term development of gas wells, this paper mainly study the corrosion-resistant material selection of tubing and casing in sour gas reservoirs under coexistence of H2S and CO2 and proposes the optimization idea and technique of tubing and casing material selection. By taking Puguang gas field as an example, this paper optimizes the material selection of production casing for Puguang gas field. By testing, the optimal materials of gas well string in Puguang gas field have good performance of erosion resistance


2013 ◽  
Vol 712-715 ◽  
pp. 1096-1099
Author(s):  
Ling Feng Li

For natural gas well in sour gas reservoirs, very serious corrosion in the completed well system is an important factor of gas production system life. In order to ensure the long-term development of gas wells, this paper mainly introduces material corrosion prevention technology in the completed well system, such as corrosion-resistant alloy steel corrosion control technology, bimetallic combination tubing, corrosion inhibitor technology and so on. By taking LJ Gas Field as an example, this paper introduces the material corrosion prevention technology in the completed well system in LJ Gas Field. For application in the completed well system in LJ Gas Field, the technology above have good performance of corrosion resistance.


2013 ◽  
Vol 690-693 ◽  
pp. 1516-1519
Author(s):  
Ling Feng Li

For natural gas well in sour gas reservoirs, very serious corrosion in the gas well string is an important factor of gas production system life. In order to ensure the long-term development of gas wells, this paper mainly introduces the tubing and casing corrosion in sour gas reservoirs, corrosion-resistant material selection of tubing and casing in sour gas reservoirs and proposes the optimization idea and technique of tubing material selection.. By taking W 63 well as an example, this paper optimizes the material selection of production casing for W 63 well. For application, the optimal materials of gas well string in W 63 well have good performance of corrosion resistance.


2021 ◽  
Vol 9 ◽  
Author(s):  
Liu Er-hu ◽  
Liu Yang-yang ◽  
Gao Li-jun ◽  
Zhou De-sheng ◽  
Liu Xiong ◽  
...  

The productivity equation of a gas well is, in the final analysis, an expression that describes the relationship between the production of a gas well and its bottom-hole flowing pressure. There are two kinds of productivity equations in common use at present: binomial productivity equation and exponential productivity equation. Combined with the modified isochronal well test, the test data are interpreted, and it is found that the open flow rates calculated by the two productivity equations are basically the same when the pressure difference at the test point is large, and the deviation of the exponential productivity equation is large when the pressure difference at the test point is small. Using binomial productivity equation and modifying isochronous well test, we established the single-point deliverability formula for the Jingbian sector of the Yan’an gas field. The field experience formula and production data are used to verify it. Their average errors are 2.59% and 7.12%, respectively; and the coincidence rate of productivity evaluation is 90%. The one-point productivity formula established has high precision and is suitable for productivity analysis of gas wells in paleozoic reservoirs in the Jingbian sector of the Yan’an gas field. This paper provides insights into the one-point productivity evaluation and its future application in the gas field.


2011 ◽  
Vol 201-203 ◽  
pp. 982-985
Author(s):  
Xiang Zhen Yan ◽  
Bing Shao ◽  
Xiu Juan Yang ◽  
Tong Tao Wang

Based on analysis of different guidelines and standards for material selection of casing which belong to six companies in four countries, the main factors that influence the material selection of casing have been generalized. Through comparing the safety and corrosion resistance properties of materials recommended by different guidelines in specific conditions, a synthetic guideline has been developed, which can provide a more appropriate suggestion. The environmental conditions and materials adopted in East Sichuan region have been taken for example. By comparing the proposed results with adopted materials of field well completion, it demonstrates that the result provided by the synthetic guideline is accurate and reliable.


2013 ◽  
Vol 700 ◽  
pp. 213-216
Author(s):  
Ling Feng Li

In natural gas production engineering for high-temperature gas well, material selection and sizes optimization of casing material are one of the important phases. This paper presents the effect of high temperature on material strength of casing, performance matching requirements of high-strength material, sizes optimization of casing material for high-temperature gas well and examples for application.By testing, the study above is good and easy for on-the-spot application.


1983 ◽  
Vol 35 (01) ◽  
pp. 40-46 ◽  
Author(s):  
Kevin J. Kilstrom
Keyword(s):  
Gas Well ◽  

2011 ◽  
Author(s):  
Mohammed Jasem Al-Saeedi ◽  
Fayez Abdulrahman Al Fayez ◽  
Dakhil Rasheed Al Enezi ◽  
mahesh sounderrajan ◽  
Mishary Najeeb Al-Mudhaf ◽  
...  
Keyword(s):  
Gas Well ◽  

Sign in / Sign up

Export Citation Format

Share Document