scholarly journals Use of Best Value Process for Inspection and Preventive Maintenance of Pumping Stations

Author(s):  
Jannie Koster-Robaard

The water board Velt en Vecht is a Best Value (BV) client who used the Performance Information Procurement System (PIPS) process to select professional services in 2012. The client had a procurement mission of integrity, transparency, objectivity, and non-discrimination that aligned them with the BV PIPS system. With a strategic plan of leadership instead of management and control, the water board is an example of a visionary owner that can be successful with BV PIPS. Lessons learned from the water board implementation of PIPS are that BV PIPS is a change of paradigm, even for a visionary owner. Both the owner who selects and the contractors who compete for the award must learn the new paradigm of minimized decision making, proactive planning, and risk management.

Author(s):  
Dean Kashiwagi

Best Value Procurement/Performance Information Procurement System (BVP/PIPS) has been developed by Dean Kashiwagi and the Performance Based Studies Research Group (PBSRG) from 1991 - 2010. BVP/PIPS is a licensed technology from Arizona State University that includes a deductive logic called Information Measurement Theory (IMT), an industry structure model which shapes the PIPS functions, and a process and structure that transfers risk and control to expert vendors. The BVP/PIPS has gone through numerous stages: the performance information centered PIPS (1994-2001); the PIPS testing phase (2001-2005); and the implementation stage (2005-2009); and the theoretical refinement and standardization of BVP/PIPS technology (2010). BVP/PIPS was introduced into the Netherlands in 2005 by a large general contractor Heijmans, the Rijkeswaterstaat, and aggressively proliferated by Scenter and others. BVP/PIPS usage in the Netherlands is modified to fit within the European procurement law. However, the main advantage of PIPS is the IMT based philosophy of minimized management, direction, and control of expert vendors.


Author(s):  
Jeroen Van de Rijt ◽  
Sicco Santema

More than 15 years ago Dean Kashiwagi created a process called BVP/PIPS (Best Value Procurement/Performance Information Procurement System) at Arizona State University. PIPS is a procurement method that aims to select the most suitable vendor for the job, to spur this vendor on to highest performance, and to reduce the client’s management and control tasks (Kashiwagi, 2009b). Kashiwagi developed the method for several years with the objective of improving the procurement and management of construction projects by reducing risk in selecting the top performer. The method (herein BV approach) has a number of steps, each built around a specific "filter”, which focuses on a different element to separate high and low performers. The early phase of the adoption of the process in the Netherlands has been described by Van de Rijt and Witteveen (2011) in the special issue of the Journal for the Advancement of Performance Information and Value. In this paper an update is given and future developments are described. The paper covers the BV approach, a brief history of PIPS in the Netherlands, technology adoption theory, adoption and adaptation of the technology and future developments.


Author(s):  
Bas Plehn

Best value PIPS has been introduced in the Netherlands in the procurement of construction systems. The Water Board De Dommel utilized best value PIPS to select engineering consultant services. The test differed from other Dutch tests in that the PIPS process used the pre-award phase before the award phase. The best value selection of engineers also proposes that design firms can compete on value (price and performance). The engineering selection process was much closer to the original BVP/PIPS than the construction phases. The major lesson learned is the BVP/PIPS is a paradigm shift. The success of the test led to the recommendation of more professional services using BVP/PIPS.


Author(s):  
Elske Bosma ◽  
Marcus Van der Ven ◽  
Oscar Kerkhoven ◽  
Dean Kashiwagi ◽  
Isaac Kashiwagi

The Best Value (BV) environment was introduced into the Netherlands in 2006. By 2008 testing was being done by a partnership of Arizona State University and Scenter (Sicco Santema, professor from Delft University). In 2010, the first significant test of the BV approach was done by the Rijkswaterstaat to deliver the $1B fast track infrastructure projects, and by 2015, the BV approach had become the “buzzword” of procurement and the professional procurement organization NEVI. However, in the delivery of professional engineering services, larger, more traditional services which were built on a system of relationships between clients and vendors, clients controlling the expert, and the importance of “billable man-hours”. The transition from a traditional approach to a BV approach is very challenging. Large traditional professional organizations naturally will have more difficulty adapting to the new approach. The BV approach utilized the expertise of experts to replace the need for relationships and owner management, direction and control (MDC). It also places less value on traditional practices that have been used by professional services to get business (relationships and working together with the client in a trust based relationship). The study captures the efforts of a very successful engineering firm (the second largest in the Netherlands) as they attempt to become successful in this new approach. The Best Value team that they have put together has had outstanding results in using the BV approach to changing their paradigm.


Author(s):  
Antoinette Bos ◽  
Dean Kashiwagi ◽  
Isaac Kashiwagi

The BV environment was introduced into the Netherlands in 2004. By 2008 testing was being done by a partnership between Arizona State University and Scenter (private entity led by Sicco Santema). In 2010, the $1B fast track projects were procured by the Rijkswaterstaat, using the Best Value Procurement. By 2015, instead of the BV approach being treated as just another option, NEVI, the Dutch professional procurement group (third largest procurement group in the world) designated the Best Value Procurement as one of the main stream procurement approaches, and hired a full time Director to guide their Best Value Procurement training programs. However, in three major areas: IT delivery, professional services and the medical arena, buyers and larger-traditional vendors were having difficulty adapting to the approach. The BV approach utilizes the expertise of experts to replace the need for owner management, direction and control (MDC). However, a stumbling block occurred, when a “Best Value” vendor was selected, but did not have their detailed plan as a baseline from which they could identify risk that was outside of their control, their risk mitigation plan, and a simple way to create transparency to help the client/user. This is a case study that shows how the Best Value Approach was requiring a paradigm shift with both the user and the vendor, which neither party was well-prepared for.


Author(s):  
Syed Nihas ◽  
Jacob Kashiwagi ◽  
Dean Kashiwagi

In September of 2013 the Performance Based Studies Research Group (PBSRG) made its first entry into India to introduce the Best Value approach. The purpose of the entry was to identify if the Best Value (BV) approach and technology could optimize the performance of the Indian Construction industry. This paper documents the results of the exploratory effort. In 2014, industry visionaries in coordination with the SJCE university group, will commence testing of the implementation of the licensed Best Value technology in India. The technology includes the Information Measurement Theory (IMT), the Performance Information Procurement System (PIPS) and the Construction Industry Structure (CIS).


Author(s):  
Ramona Apostol

This paper discusses the legal implications of using the elements of the Performance Information Procurement System (PIPS) procedure in the Netherlands. The article proposes the pros and cons of the potential compliance of these elements, in the form adopted in a test case with the municipality of ‘s-Hertogenbosch who attempted to meet the requirements of Aanbestedingsreglement Werken1 (hereafter: ARW) 2005. The author proposes that the national restricted procurement with pre-selection prescribed by the ARW 2005 may raise potential issues of interpretation and may therefore be too strict for the efficient application of the elements of the American methodology. Based on the legal discussion of the test case, the author is proposing to choose a more flexible policy for the public works contracts, which can benefit from the application of the American methodology.


Author(s):  
John Savicky ◽  
Dean Kashiwagi ◽  
Kristen Barlish ◽  
Kenneth Sullivan

A large government agency, seeking to become more efficient, implemented the Performance Information Procurement System (PIPS) Best Value (BV) process on various construction projects to determine if the program could increase the performance of outsourced services. The impact of this model for increasing the performance of procured projects is presented. The environment of the projects and testing of the process were unique, as they allowed concurrent testing and validation of multiple projects, similar in scope, and uniform application of key performance metrics. A case study is also used to illustrate the overall performance of the BV process. The findings in this paper show that the process resulted in approximately a 60% increase in performance with regards to customer satisfaction, project delays, and cost increases. In an industry with delays in excess of 20-50%, a model that results in an increase of performance for outsourced services is significant.


Author(s):  
Gumgaro Simon-Peter Buba ◽  
Razali Adul Hamid ◽  
Zuhaili Mohamad Ramly ◽  
Tchad Sharon Jatau ◽  
James David Jatau

The construction industry is vital to the economic development of any country. It has a major role in providing built infrastructures in an innovative and cost-effective way using an effective procurement approach. In contrast, the most widely used procurement method in Nigeria is the traditional procurement approach which is known for plaguing the industry with the poor working condition and poor performances thus, reducing the sustainability and quality of products and services. For this reason, there is a need for a procurement approach which utilises expertise to minimise the risk of non-performance and create a win-win environment for both client and contractors, while increasing transparency and add value to the project such like, the Best Value Procurement. Against the background, this paper aims to establish the perception of the Nigerian construction professionals on the unique factors of the Best Value Procurement. The paper outlines the following objectives: To identify the unique factors of the Best Value Procurement and, to establish the perception of the Nigerian construction professionals on the Best Value Procurement unique factors. Using a questionnaire survey, data was collected form 314 construction professionals involving Quantity Surveyors, Architects, Builders and Civil Engineers. Kruskal Wallis Test and mean score ranking was used for data analysis. The findings show that the professionals generally agree that the Best Value Procurement unique factors can bring about transparency, accountability, increase project performance and the contractor is the best to control risk and adds value to the project. This paper derives its significance from the need to stabilise the procurement system in Nigeria by transferring the risk and control to contractors who must act in the best interest of the client. 


Author(s):  
Marianne Van Leeuwen

Best Value Procurement Performance Information Procurement System (hereinafter: BVP-PIPS) is a methodology developed in the United States and is now being used by private and public contractors in the Netherlands. For public contractors in Europe, application of BVP-PIPS is not straightforward because of the constraints of the European legislation on procurement. This paper describes how BVP-PiPS can be used in a European legal context. First, some basic aspects of European procurement law are explained. Next, the original BVP-PiPS method is described in short. Subsequently the method is tested against the European legal constraints. Implications from European procurement law to all phases from the BVP-PiPS method will be described. The paper ends with conclusions on how BVP-PiPS can be used within the European legal framework.