Pilot testing and preliminary design of moving bed biofilm reactors for nitrogen removal at the FREVAR wastewater treatment plant

2000 ◽  
Vol 41 (4-5) ◽  
pp. 13-20 ◽  
Author(s):  
B. Rusten ◽  
B.G. Hellström ◽  
F. Hellström ◽  
O. Sehested ◽  
E. Skjelfoss ◽  
...  

A moving bed biofilm reactor (MBBR) pilot plant, using Kaldnes type K1 biofilm carriers, was tested for nitrogen removal at the FREVAR wastewater treatment plant. The pilot plant was fed primary treated municipal wastewater, at temperatures from 4.8 to about 20°C. The results showed that a reasonable design nitrification rate will be 190 g TKN/m3d, at 10°C and a reactor pH≥7.0. Pre-denitrification was very dependent on the concentration of readily biodegradable organic matter and the amount of oxygen in the influent to the first anoxic MBBR. It was found that a MBBR process for nitrogen removal at FREVAR will require a total reactor volume corresponding to an empty bed hydraulic retention time of 4–5 hours at average design influent flow. This was based on an influent concentration of 25 mg total N/l, 70% annual average removal of total N and a treatment process consisting of primary treatment, MBBRs with combined pre- and post-denitrification, and followed by coagulation/flocculation and a final solids separation stage.

2001 ◽  
Vol 44 (1) ◽  
pp. 113-120 ◽  
Author(s):  
G. Esposito ◽  
C. Bastianutti ◽  
G. Bortone ◽  
F. Pirozzi ◽  
S. Sgroi

The effects of suppressing primary sedimentation on nitrogen removal efficiency of a pre-denitrification system have been evaluated for a large municipal wastewater treatment plant. Simulations have been carried out using the STOAT model. For both the process schemes with and without primary sedimentation, nitrification efficiencies are calculated for increasing influent loads of COD, total N and suspended solids. The sensitivity analysis shows that for the usual carbon to nitrogen ratios in the raw influent both the process schemes allow the requested removal efficiencies, whereas for significantly high C/N ratios the scheme with primary sedimentation is preferable.


2000 ◽  
Vol 41 (1) ◽  
pp. 177-185 ◽  
Author(s):  
G. Andreottola ◽  
P. Foladori ◽  
M. Ragazzi

The aim of this study was to evaluate the performance of a full-scale upgrading of an existing RBC wastewater treatment plant with a MBBR (Moving Bed Biofilm Reactor) system, installed in a tank previously used for sludge aerobic digestion. The full-scale plant is located in a mountain resort in the North-East of Italy. Due to the fact that the people varied during the year's seasons (2000 resident people and 2000 tourists) the RBC system was insufficient to meet the effluent standards. The MBBR applied system consists of the FLOCOR-RMP®plastic media with a specific surface area of about 160 m2/m3 (internal surface only). Nitrogen and carbon removal from wastewater was investigated over a 1-year period, with two different plant lay-outs: one-stage (only MBBR) and two stage system (MBBR and rotating biological contactors in series). The systems have been operated at low temperature (5–15°C). 50% of the MBBR volume (V=79 m3) was filled. The organic and ammonium loads were in the average 7.9 gCOD m−2 d−1 and 0.9 g NH4−N m−2 d−1. Typical carbon and nitrogen removals in MBBR at temperature lower than 8°C were respectively 73% and 72%.


2010 ◽  
Vol 61 (9) ◽  
pp. 2259-2266 ◽  
Author(s):  
Styliani Kantartzi ◽  
Paraschos Melidis ◽  
Alexander Aivasidis

In the present study, a laboratory scale system, consisting of a primary settling tank, a continuous stirred tank reactor and a clarifier were constructed and operated, using wastewater from the municipal wastewater treatment plant in Xanthi, Greece. The system operated under intermittent aeration in aerobic/anoxic conditions and feeding of the wastewater once in every cycle. The unit was inoculated with sludge, which originated from the recirculation stream of the local wastewater treatment plant. The wastewater was processed with hydraulic retention time (HRT) of 12 h, in which various experimental states were studied regarding the combination of aerobic and anoxic intervals. The wastewater was fed in limited time once in every cycle of aerobic/anoxic conditions at the beginning of the anoxic period. The two states that exhibited highest performance in nitrification and total nitrogen removal were, then, repeated with HRT of 10 h. The results show that, regarding the nitrification stage and the organic load removal, the intermittent system achieved optimum efficiency, with an overall removal of biological oxygen demand (BOD5) and ammonium nitrogen in the range of 93–96% and 91–95% respectively. As far as the total nitrogen removal is concerned, and if the stage of the denitrification is taken into account, the performance of the intermittent system surpassed other methods, as it is shown by the total Kjeldahl nitrogen (TKN) removal efficiency of 85–87%. These operating conditions suppressed the growth of filamentous organisms, a fact reflected at the SVI values, which were lower than 150 ml/g.


2000 ◽  
Vol 41 (4-5) ◽  
pp. 5-12 ◽  
Author(s):  
E.v. Münch ◽  
K. Barr ◽  
S. Watts ◽  
J. Keller

The Oxley Creek wastewater treatment plant is a conventional 185,000 EP BOD removal activated sludge plant that is to be upgraded for nitrogen removal to protect its receiving water bodies, the Brisbane River and Moreton Bay. Suspended carrier technology is one possible way of upgrading this activated sludge wastewater treatment plant for nitrogen removal. Freely moving plastic media is added to the aeration zone, providing a growth platform for nitrifying bacteria and increasing the effective solids residence time (SRT). This paper presents the results from operating a pilot plant for 7 months at the Oxley Creek WWTP in Brisbane, Australia. Natrix Major 12/12 plastic media, developed by ANOX (Lund, Sweden), was trialed in the pilot plant. The pilot plant was operated with a mixed liquor suspended solids concentration of 1220 mg/L and a total hydraulic residence time of 5.4 hours, similar to the operating conditions in the full-scale Stage 1&2 works at the Oxley Creek WWTP. The plastic carriers were suspended in the last third of the bioreactor volume, which was aerated to a DO setpoint of 4.0 mg/L. The first third of the bioreactor volume was made anoxic and the second third served for carbon removal, being aerated to a DO setpoint of 0.5 mg/L. The results from the pilot plant indicate that an average effluent total inorganic nitrogen concentration (ammonia-N plus NOx−N) of less than 12 mg/L is possible. However, the effluent ammonia concentrations from the pilot plant showed large weekly fluctuations due to the intermittent operation of the sludge dewatering centrifuge returning significant ammonia loads to the plant on three days of the week. Optimising denitrification was carried out by lowering the DO concentration in the influent and in the carbon removal reactor. The results from the pilot plant study show that the Oxley Creek WWTP could be upgraded for nitrogen removal without additional tankage, using suspended carrier technology.


2014 ◽  
Vol 2 (3) ◽  
pp. 33-42
Author(s):  
Mehdi Ahmadi ◽  
Aliakbar Mehr alian ◽  
Hoda Amiri ◽  
Bahman Ramavandi ◽  
Hassan Izanloo ◽  
...  

2014 ◽  
Vol 9 (2) ◽  
pp. 235-242 ◽  
Author(s):  
S. Morling ◽  
A. Franquiz ◽  
J. Måhlgren ◽  
Å. Westlund

A biological wastewater treatment plant, Nynäshamn treating municipal wastewater and septic sludge operated with a combination of sequencing batch reactor (SBR) units and constructed wetland is presented in this paper. The plant has to treat low temperature wastewater in winter time, still with demands for a biological nitrogen removal. Treatment results from a 13 year operation period are presented. Special attention was given to the nutrient removal during low temperature conditions. The combination of a SBR system along with classical chemical precipitation and a polishing step based on ‘natural’ extensive treatment has been a sustainable way to keep the discharge levels low. The combined treatment with SBR and the wetland at the Nynäshamn plant has resulted in improved discharge levels typically as follows (annual mean values); BOD7 3 mg/l, to be compared with the formal consent value of <15 mg/l, total P < 0.1 mg/l, to be compared with the formal consent value of <0.5 mg/l and total N 7 mg/l, to be compared with the formal consent value of <15 mg/l. It is also important to underline that the change of process train has resulted in a substantial saving of the precipitant agent for phosphorus removal. The needed dosage is now 50% of the previous dose, before the implementation of the SBR-units.


1996 ◽  
Vol 33 (12) ◽  
pp. 255-258 ◽  
Author(s):  
Olga Burica ◽  
Marjeta Strazar ◽  
Ivan Mahne

The recirculation activated sludge process with preanoxic treatment was applied for biological reduction of the nitrogen content in municipal wastewater at pilot plant level. The pilot plant of total volume 3 300 1 with an initial anoxic to aerobic volume ratio of 40 : 60 was fed with wastewater from the first heavily loaded aerobic stage of a local wastewater treatment plant. Experiments were run over the summer and winter periods, the influent wastewater temperature being approx 24°C and approx 10°C, respectively. Special attention was paid to the hydraulic retention time, the total as well as mineral nitrogen loading, the aerobic to anaerobic volume ratio, and to the energy demand for denitrification of oxidised mineral nitrogen forms. Under optimal operating conditions the effluent quality that could be achieved was about 10 mg/l of total nitrogen (74% removal) and less than 2 mg N/l mineral nitrogen (87% removal), while simultaneously 205 mg BOD5/l in the influent was reduced to less than 7mg O2/l in the effluent. It was found feasible from the pilot plant experiments to upgrade an existing two stage aerobic-anaerobic wastewater treatment plant to reduce nitrogen from the liquid fraction of municipal wastewater so as to meet effluent quality standards without much additional volume and without amending the energy source for bioconversion of oxidised mineral nitrogen to gaseous forms.


2002 ◽  
Vol 46 (4-5) ◽  
pp. 325-332 ◽  
Author(s):  
N. Hvala ◽  
D. Vrečko ◽  
O. Burica ◽  
M. Strazžar ◽  
M. Levstek

The paper presents a study where upgrading of an existing wastewater treatment plant was supported by simulation. The aim of the work was to decide between two technologies to improve nitrogen removal: a conventional activated sludge process (ASP) and a moving bed biofilm reactor (MBBR). To perform simulations, the mathematical models of both processes were designed. The models were calibrated based on data from ASP and MBBR pilot plants operating in parallel on the existing plant. Only two kinetic parameters needed to be adjusted to represent the real plant behaviour. Steady-state analyses have shown a similar efficiency of both processes in relation to carbon removal, but improved performance of MBBR in relation to nitrogen removal. Better performance of MBBR can be expected especially at low temperatures. Simulations have not confirmed the expected less volume required for the MBBR process. Finally, the MBBR was chosen for plant upgrading. The developed process model will be further used to evaluate the final plant configuration and to optimise the plant operating parameters.


2004 ◽  
Vol 50 (6) ◽  
pp. 163-171 ◽  
Author(s):  
K.J. Chae ◽  
S.K. Yim ◽  
K.H. Choi

For the upgrade and expansion of an existing caprolactam wastewater treatment plant, a freely floating sponge media (BioCube) process was selected based on extensive pilot-plant tests, due to extreme space constraints. In order to protect nitrifier inhibition caused by high strength organics in caprolactam wastewater, the pilot plant consisted of an organics removal reactor, which functioned as a pretreatment for nitrification, and followed the nitrogen removal reactor. The suspended MLSS was 1,800-4,000 and the media attached MLSS was maintained at 22,000-26,000 mg/L. The final effluent COD was noticeably low, around 20.4-37 mg/L, even with fairly large fluctuations in the feed levels, between 1,400-6,770 mg/L. The removal of total nitrogen with the system, when denitrification was close to completion, was approximately 97.6%. For the entire run, complete nitrification of 99.6% was achieved, which might have been due to well-acclimatized nitrifiers attached in the BioCube media. Specifically, after adaptation, the nitrification continuously increased in the organics removal reactor, even under high residual organics conditions. From the numerous experimental results, the BioCube process seemed to be an effective method for the upgrading and expansion of the existing wastewater treatment plant, with minimum reactor enlargement.


Sign in / Sign up

Export Citation Format

Share Document