subsea pipeline
Recently Published Documents


TOTAL DOCUMENTS

278
(FIVE YEARS 75)

H-INDEX

15
(FIVE YEARS 3)

2021 ◽  
Vol 169 ◽  
pp. 108350
Author(s):  
Yang Yu ◽  
Zhenmian Li ◽  
Jianxing Yu ◽  
Lixin Xu ◽  
Siyuan Cheng ◽  
...  

2021 ◽  
Author(s):  
Song Wang ◽  
Lawrence Khin Leong Lau ◽  
Wu Jun Tong ◽  
Kun An ◽  
Jiang Nan Duan ◽  
...  

Abstract This paper elucidates the importance of flow assurance transient multiphase modelling to ensure uninterrupted late life productions. This is discussed in details through the case study of shut-in and restart scenarios of a subsea gas well (namely Well A) located in South China Sea region. There were two wells (Well A and Well B) producing steadily prior to asset shut-in, as a requirement for subsea pipeline maintenance works. However, it was found that Well A failed to restart while Well B successfully resumed production after the pipeline maintenance works. Flow assurance team is called in order to understand the root cause of the failed re-start of Well A to avoid similar failure for Well B and other wells in this region. Through failure analysis of Well A, key root cause is identified and associated operating strategy is proposed for use for Well B, which is producing through the same subsea infrastructure. Transient multiphase flow assurance model including subsea Well A, subsea Well B, associated spools, subsea pipeline and subsea riser is developed and fully benchmarked against field data to ensure realistic thermohydraulics representations of the actual asset. Simulation result shows failed restart of Well A and successful restart of Well B, which fully matched with field observations. Further analysis reveals that liquid column accumulated within the wellbore of Well A associates with extra hydrostatic head which caused failed well restart. Through a series of sensitivity analysis, the possibility of successful Well A restart is investigated by manipulating topsides back pressure settings and production flowrates prior to shut-in. These serve as a methodology to systematically analyze such transient scenario and to provide basis for field operating strategy. The analysis and strategy proposed through detailed modelling and simulation serves as valuable guidance for Well B, should shut-in and restart operation is required. This study shows the importance of modelling prior to late life field operations, in order to avoid similar failed well restart, which causes significant production and financial impacts.


2021 ◽  
Author(s):  
Winanto Winanto ◽  
Mukhtarus Bahroinuddin ◽  
Endro Cahyono ◽  
Margaretha Thaliharjanti

Abstract KLB is an offshore platform that consists of production wells and two train gas lift compressors. During well intervention, the KLB operation team must turn off the flaring system due to potential flare radiation of more than 500 BTU/hr-ft2at the working area and gas dispersion more than 50 %-LEL at the flare tip. The relocation of the KLB flaring system to the nearest platform keeps the KLB gas lift compressor operating during this activity. The relocation scenario can maintain the KLB platform production of 700 BOPD. KLA Flowstation is the nearest platform to the KLB. It is separated one kilometer, connected by an idle subsea oil pipeline, but there are no pigging facilities due to limited space at the KLB platform. Therefore, the comprehensive assessment to relocate the KLB flaring system is a) Flare system study using Flare Network software to simulate backpressure and Mach Number at tailpipe in the KLA and KLB flaring system; b). Dynamic transient simulation using Flow Assurance Software to calculate backpressure, liquid hold up, and slugging condition in the flare KO drum; and c). Flare radiation and dispersion study. The initial condition of the idle subsea oil pipeline was full of liquid as the preservation for a pipeline to prevent a further oil spill in case of a leak during the idle condition. The dewatering process for the idle subsea pipeline has been conducted by purging the pipeline utilizes 0.7 MMscfd gas lift with a pressure of 100 psig to displace liquid content to 20 bbl. The transient simulation for gas swapping was conducted at a gas rate of 4.1 MMscfd as the train compressor's flaring condition. The calculated backpressure at the KLB safety valve is 12.3 psig below the required maximum of 30 psig. The calculated liquid surge volume in the Flare KO drum during flaring is 17 bbl and can be handled by surge volume inside the KO drum. The predicted condensation inside the subsea pipeline shows that the maximum operation of the flaring system is limited to 30 days. The radiation and gas dispersion to the nearest facility is within a safe limit. The KLB teams successfully conducted the relocation of the flaring system from the KLB platform to the KLA platform. The result was no interruption of production, no risk of radiation, and no potential explosion during a well intervention. Experience in the last two activities has confirmed that this method can prevent revenue loss of 19 billion rupiahs. This study has initiated a new engineering standard and best practice for flaring systems as opposed to the current practice which states that the flare location shall be at the same location as the production facilities with no pocket piping in between. This study and field experience have proved that the flaring system can be located on a different platform by conducting engineering assessments to ensure process and process safety criteria are within Company and International Standard.


2021 ◽  
Author(s):  
Ferry Firmansyah ◽  
Adit Satriawirawan ◽  
Aryo Wisnudarto

Abstract Offshore terminal usually performs crude oil lifting process regularly every 7-8 days. However, three repetitive leaks in crude oil subsea pipeline 36" MOL SPM-1 to SPM-2 occurred in the offshore terminal area had stopped the natural oil lifting process. Due to complex conditions, leak repair needs a longer duration and some future crude oil lifting schedules facing cancelation possibilities. By simulating the leak parameter, more than 60 bbl. of crude oil would release from the leaking pipeline in 48 hours crude oil lifting operation. An innovative approach is built by designing a new tool to contain oil spills from the source using a pyramid shape tank and safely transport to the temporary storage tank on the diving vessel to keep crude oil lifting process execution still possible to hold while the subsea pipeline repair by installing subsea clamp is undergo. New tools have successfully eliminated oil spill spreading during crude oil lifting takes place schedule. Six crude lifting schedules have been safely delivered with nearly 30,000 liters of crude oil spill have been evacuated and transferred back to processing facilities. Further implementation would possibly be held in pipeline preservation program and diver less application, which can increase leak response time.


2021 ◽  
Author(s):  
Abhinav Gupta ◽  
Tribhuwan Tyagi

Abstract Pipelines have proven to be the most reliable and efficient means of transportation of hydrocarbons. Different fluids from numerous sources have different physical, chemical and operational properties, thereby separate pipelines were laid for most of the fluids. However, laying of new pipelines is becoming more and more challenging with vast and complex network of existing pipelines and topographies being faced in both onshore as well as offshore. Moreover considering the huge laying costs and risks of damaging the delicate balance of flora and fauna by entering the unchartered territories, a point does arise to optimally utilize already existing massive pipeline infrastructure. In this technical paper a method has been formulated to achieve such a cause. A case study from an existing subsea pipeline project of M/s ADOC (Japan) has been presented. Existing 8 inch subsea pipeline of M/s ADOC (Japan) from Hail Site Terminal (HST) to Mubarraz Island in UAE was originally designed for gas service. However, the client intended to use the same for treated sea water service. A thorough design adequacy check was performed to convert the existing subsea gas pipeline into a liquid pipeline. In such a case it is mandatory to check the adequacy of the pipeline for the intended service and design parameters which includes checking for suitability of already selected pipe wall thickness, on-bottom stability and free spans under the action of hydrostatic and hydrodynamic forces. The methodology adopted for this project can be generalized in order to create a framework to establish a basis to use an existing pipeline for different services.


2021 ◽  
Author(s):  
Craig Macdonald ◽  
Javad Safari ◽  
Stuart Anderson

Abstract Known as HFW-MLP, Mechanically Lined Pipe (MLP) with High Frequency Welded (HFW) host pipes are potentially the most cost-effective bi-metallic pipes for subsea pipelines when corrosion resistant alloys (CRA) are required. However, HFW-MLP has a very limited track record for subsea applications. This paper details a recent programme to qualify MLP with HFW host pipes. The qualification programme has been performed in accordance with DNVGL-ST-F101 (2017) and internal supplementary requirements for reelability and weldability. It considers material testing of HFW-MLP at each manufacturing stage and product qualification including full-scale reeling simulation, anti-corrosion coating simulation and girth welding. Qualification is supplemented with a detailed evaluation of the manufacturing process HFW-MLP is compared to traditional MLP which is supplied with seamless carbon steel as the host pipe or backing steel. This novel product lowers the supply cost, reducing the Capital Expenditure (CAPEX) for subsea pipeline projects. Detailed evaluation of mechanical test results and dimensional inspections using laser profiling assess the impact of the HFW host pipe longitudinal seam weld and conclude that there is no detrimental effect on the performance of the completed MLP. A comprehensive review of full-scale reeling simulations, coating simulations and welding trials is completed, with the conclusion that an HFW host pipe does not adversely affect the ability of the MLP product to be girth welded and to withstand the plastic deformation exerted upon the product during reel-lay installation. It is concluded that HFW-MLP is qualified for subsea pipeline static applications via the reel-lay, S-Lay or J-lay installation methods. The qualification of HFW-MLP provides a more cost-effective solution for the development of corrosive subsea fields by reducing overall product supply and installation costs.


2021 ◽  
Vol 2021 ◽  
pp. 1-15
Author(s):  
Lunliang Duan ◽  
Meiling Fan ◽  
Duoyin Wang ◽  
Caixia Meng ◽  
Lei Xing

To investigate the wave- and current-induced seabed response near a fully buried subsea pipeline, a two-dimensional coupled model for fluid-seabed-pipeline interaction (FSPI-2D) is developed within the framework of COMSOL multiphysics. Different from previous studies, both the wave-current interaction and the nonlinear pipeline-soil contacts are considered in the present model. In this paper, Biot’s consolidation mode is used to govern the fluid-induced seabed response, and combined Reynolds averaged Navier–Stokes (RANS) equation with the k-ε turbulence model is employed to simulate the fluid propagation. Meanwhile, the pipeline is treated as a linear elasticity. Firstly, the effectiveness of the new model is verified by laboratory experiments from previous reports. Then, the numerical model is employed to examine the effects of nonlinear pipeline-seabed contacts and fluid characteristics on the seabed response around the structure. Finally, the momentary liquefaction near the fully buried pipeline is studied based on the 2D coupled model.


Sign in / Sign up

Export Citation Format

Share Document