scholarly journals Study on the Oil Pipeline Design of R Oil Field

2020 ◽  
Vol 3 (3) ◽  
pp. 40
Author(s):  
Qing Liu

It’s a compressive article consists of three parts, an overview of pipeline development in China, oil pipeline design for R oilfield and pipeline management suggestions. First, this article introduces the current status of pipeline construction, oil pipeline technology and gas pipeline technology in China in recent years. The current status of China’s pipeline construction is divided into three stages. In terms of construction, pipeline construction is developing in the direction of intelligence and modernization. Long-distance oil pipelines require technical breakthroughs in two aspects. One is the sequential oil product delivery technology to improve the type of oil that can be delivered sequentially; the second is the viscosity reduction delivery technology for heavy oil. Gas transmission pipelines are developing in the direction of high pressure, large diameter and high steel grade. Secondly, based on all the pipeline development above, in order to meet the development of R oil field, an oil-water two-phase pipeline transportation design and a pipeline crossing river design were carried out. Under the condition of the design pressure of the pipeline of 5.5MPa, it is preferable to produce a pipeline of φ219×6.5mm, and the steel grade of the pipeline is L360. A heating station and pumping station are needed in the transportation process, and the heating station and pumping station are combined for one construction. Considering that the strata of the river crossing section are mainly gravel sand layer, clay layer and non-lithological stratum, horizontal directional drilling (HDD) is adopted for river crossing, and suggestions are made for the construction process. Finally, after the pipeline was put into production, the corresponding auxiliary production system and supporting engineering suggestions were put forward.

Author(s):  
Matthew Y-H. Kuo ◽  
Malcolm D. Bolton

In recent years, the presence of crusts within near surface sediments found in deep water locations off the west coast of Angola has been of interest to hot-oil pipeline designers. The origin for these crusts is considered to be of biological origin, based on the observation of thousands of faecal pellets in natural crust core samples. This paper presents the results of laboratory tests undertaken on natural and faecal pellet-only samples. These tests investigate the role faecal pellets play in modifying the gemechanical behaviour of clayey sediments. It is found that faecal pellets are able to significantly alter both the strength and the average grain-size of natural sediments, and therefore, influence the permeability and stiffness. Hot-oil pipelines self-embed into and subsequent shear on crusts containing faecal pellets. Being able to predict the time required for installed pipelines to consolidate the underlying sediment and thus, how soon after pipe-laying, the interface strength will develop is of great interest to pipeline designers. It is concluded from wet-sieving samples before and after oedometer tests, that the process of pipe laying is unlikely to destroy pellets. They will therefore, be a major constituent of the sediment subject to soil-pipeline shearing behaviour during axial pipe-walking and lateral buckling. Based on the presented results, a discussion highlighting the key implications for pipeline design is therefore provided.


2012 ◽  
Vol 268-270 ◽  
pp. 547-550
Author(s):  
Qing Wang Liu ◽  
Xin Wang ◽  
Zhen Zhong Fan ◽  
Jiao Wang ◽  
Rui Gao ◽  
...  

Liaohe oil field block 58 for Huancai, the efficiency of production of thickened oil is low, and the efficiency of displacement is worse, likely to cause other issues. Researching and developing an type of Heavy Oil Viscosity Reducer for exploiting. The high viscosity of W/O emulsion changed into low viscosity O/W emulsion to facilitate recovery, enhanced oil recovery. Through the experiment determine the viscosity properties of Heavy Oil Viscosity Reducer. The oil/water interfacial tension is lower than 0.0031mN•m-1, salt-resisting is good. The efficiency of viscosity reduction is higher than 90%, and also good at 180°C.


2008 ◽  
Vol 11 (04) ◽  
pp. 778-791 ◽  
Author(s):  
Secaeddin Sahin ◽  
Ulker Kalfa ◽  
Demet Celebioglu

Summary The Bati Raman field is the largest oil field in Turkey and contains approximately 1.85 billion bbl of oil initially in place. The oil is heavy (12°API), with high viscosity and low solution-gas content. Primary recovery was less than 2% of oil originally in place (OOIP). Over the period of primary recovery (1961-86), the reservoir underwent extensive pressure depletion from 1,800 psig to as low as 400 psig in some regions, resulting in a production decline from 9,000 to 1,600 STB/D. In March 1986, a carbon-dioxide (CO2) -injection pilot in a 1,200-acre area containing 33 wells was initiated in the western portion of the field. The gas-injection was initially cyclic. In 1988, the gas injection scheme was converted to a CO2-flood process. Later, the process was extended to cover the whole field. A peak daily production rate of 13,000 STB/D was achieved, whereas rate would have been less than 1,600 STB/D without CO2 application. However, the field has undergone a progressive production decline since 1995to recent levels of approximately 5,500 STB/D. Polymer-gel treatments were carried out to increase the CO2 sweep efficiency. Multilateral- and horizontal-well technology also was applied on a pilot scale to reach the bypassed oil. A water-alternating-gas (WAG) application has been applied extensively in the western part of the field. Current production is 7,000 STB/D. This paper documents more than 25 years of experience of the Turkish Petroleum Corporation (TPAO) on the design and operation of this full-field immiscible CO2-injection project conducted in the Bati Raman oil field in Turkey. The objective is to update the current status report, update the reservoir/field problems that TPAO has encountered (unpredictable problems and results), and provide a critical evaluation of the success of the project. Introduction The Bati Raman field is the biggest oil accumulation in Turkey and is operated by TPAO. It contains very viscous and low-API-gravity oil in a very challenging geological environment. Because of the fact that the recovery factor by primary recovery was limited, several enhanced-oil-recovery (EOR) techniques had been proposed and tested at the pilot level in the 1970s and 1980s. On the basis of the success of the laboratory tests and the vast amount of CO2 available in a neighboring field, which is only 55 miles away from the Bati Raman field, huff ‘n’ puff injection was started in the early 1980s. Because of the early breakthrough of CO2 in offset wells in a short period of time, the project was converted to field-scale random-pattern continuous injection. During more than 20 years of injection, the recovery peaked at approximately 13,000 STB/D and began to decline, reaching today's value of approximately 7,000 STB/D. In the case of Bati Raman, in its mature, the injected agent is bypassing the remaining oil and production is curtailed by excessively high gas/oil ratios (GORs). The naturally fractured character of the reservoir rock has been a challenge for establishing successful 3D conformance from the beginning, and its impact is even more pronounced in the later stages of the process. Therefore, the field requires modifications in the reservoir-management scheme to improve the recovery factor and to improve productivity of the current wells.


2012 ◽  
Vol 614-615 ◽  
pp. 550-554
Author(s):  
Rong Ge Xiao ◽  
Dong Rui Yi ◽  
Pei Fen Yao ◽  
Jia Quan Zhou

Because the most of crude oil has the nature of "three-high" in China and the natural aging of crude oil in the part of oil field, the transmission of crude-oil has reduced, and the oil refining has increased in oil field, Thus the majority of pipelines laid in china are running at a low-flowrate. Analysis of the problems in the running of low-flowrate pipeline: with the temperature drops up, the viscosity increases; the accident of condensate tubes very easily occurs; the turnover point increases; the pressure load of pipeline increases; the supply of heat is shortage, the reliability of equipment is reduced; costs increases and so on. There is proposing the main operation mode to solve the pipeline in low-flowrate, including intermittent transportation, the transportation of mixing light oil, oil and gas batch transportation, the transportation with adding pour point depressant and so on, and has discussed the instability of the running of hot pipeline in the low-flowrate.


Author(s):  
N. E. Udosoh ◽  
Clement Idiapho ◽  
Sani Awwal

This research work on material selection for subsea pipeline construction was carried out to analyze and recommend suitable material option that satisfies DNV-OS-F101 standard for subsea pipeline constructions which will not succumb to extreme conditions and performs well in unpredictable conditions in the Niger Delta Region of Nigeria. Crude oil is mainly transported through pipelines, structural failure of the pipelines will severely affect oil production processes and will cause huge economic loss. Data on oil pipeline failures in the Niger Delta region of Nigeria were gathered and the major causes were; corrosion, operational error, third party activities and mechanical failures which were associated with the construction materials and structures of the pipelines. Hence, material selection for subsea pipelines is of vital importance. This paper makes use of Technique for Order Preference by Similarity to the Ideal Solution (TOPSIS) Theory to make fuzzy evaluation of different material options for pipeline construction. Statistical data and experts’ knowledge were integrated in addressing data limitation. This paper utilizes related weights and normalized scores based on experts’ judgements and with the aid of value engineering (VE) method, material criteria based on DNV-OS-F101 standard and TOPSIS Theory to achieve the best material option. The analysis has demonstrated that the estimation of TOPSIS is reliable. The outcome obtained can be used to assist the decision maker in the selection of the best material option suitable for the construction of subsea pipeline in Niger Delta region.


Sign in / Sign up

Export Citation Format

Share Document