scholarly journals Delays in construction works in Polish construction industry from the contractors’ point of view

2018 ◽  
Vol 222 ◽  
pp. 01008 ◽  
Author(s):  
Anna Kowalczyk ◽  
Wiesław Meszek ◽  
Mariusz Rejment ◽  
Agnieszka Dziadosz

The construction industry is sensitive to changing random conditions that determine the occurrence of various disturbances during the construction investment process. These disturbances are the source of numerous delays during realization of the construction project. The identification of the reasons for delays and their impact on the progress of construction works allows for the efficient management of the construction project and planning of protective measures, which reduce the risk of their occurrence. The purpose of this article is to identify and then to assess, on the basis of the conducted questionnaire survey, the impact of disturbances on delays in construction works. In addition, the factors were ranked in terms of the degree of impact on the construction project by calculating the rank of the factor.

2015 ◽  
Vol 735 ◽  
pp. 154-158
Author(s):  
Siti Hafiza Mat Yahya ◽  
Syuhaida Ismail

Contractors are one of the important parties in completing a construction project as they directly involved in the construction works execution. Therefore, contractors’ performance should be monitored and assessed on a regular basis to ensure the success of the project, particularly by identifying the failures and shortfalls, as well as any delays and losses that might occur due to the poor productivity of the contractors. A systematic performance appraisal is one of the endeavours in ensuring that the contractors’ performance is as per the expectation of the stakeholders, particularly the client. Hence, this paper provides a review on the contractors’ performance appraisal practices in construction industry in Malaysia. Questionnaire survey on 214 respondents from construction industries, ranging from contractors to project managers, was undertaken where the results showed that contractors’ performance appraisal in a particular construction project is very essential as it drives the project towards better improvement and ultimate success.


2018 ◽  
Vol 11 (3) ◽  
pp. 761-782 ◽  
Author(s):  
Shamil George Naoum ◽  
Carlos Herrero ◽  
Charles Egbu ◽  
Daniel Fong

Purpose It is axiomatic that construction is a fast-paced and competitive industry, which goes hand in hand with many construction professionals suffering from stress including construction project managers (C-PMs). The role of C-PMs is crucial to achieving project success as they are responsible for planning the project, organising human resources, controlling operations and the budget, and forecasting probable difficulties. The purpose of this paper is to investigate the causal relationships between stressors, stresses, stress-coping behaviours and their impact on the performance of C-PMs. Design/methodology/approach To investigate the relationships between stress and performance among C-PMs, a questionnaire was designed based on the extensive literature, and was sent to 150 C-PMs who had amassed at least five years’ direct working experience in the construction industry. A total of 44 completed questionnaires were returned. Correlation analysis and structural equation modelling were employed to understand the integrated relationships between these factors. Based on the data collected and analysis of the results, an integrated structural equation model of the stresses and performances of C-PMs was developed using AMOS version 22.0. Findings The results of structural equation modelling reveal the following: burnout is the type of stress that has the highest impact on the performance of C-PMs, being detrimental to their interpersonal performance (IPP) and positive for their organisational performance (OP), whereas physiological stress worsens the task performance of C-PMs and objective stress improves their IPP. The most active stressor towards the performance of C-PMs is “workgroup cooperation”, which has an impact on the IPP in a positive way but is detrimental to the OP. Career-developing environment, poor organisational structure and role conflict affect both stress and performance together. Originality/value This study provides a comprehensive investigation into the impact of various types of stress on the performances of C-PMs. The result constitutes a significant step towards the stress management of C-PMs in the dynamic and stressful construction industry.


Author(s):  
S. Kıvrak ◽  
G. Arslan

Augmented reality is one of the innovative technologies that will provide significant benefits to construction project applications in the future. In this study, an augmented reality system is developed for improving construction project activities. By using this system, construction workers, equipment operators, engineers and managers can follow each step of the construction activities that they are responsible for. Users can access necessary information about training materials and construction methods related to the construction works. Thus, construction engineers and workers can learn the correct methods of project activities and prevent themselves to make wrong productions. The system is tested in ceramic tile installation. It has been proposed that the system can improve the quality and productivity of construction activities and therefore provide significant contributions to the construction industry.


2020 ◽  
Vol 10 (1) ◽  
pp. 70-85
Author(s):  
Abdarahim Salem ◽  
Eric Simpeh ◽  
Julius Fapohunda

The construction industry is extremely complex, with dynamic project environments creating an atmosphere of high uncertainty and risk. For that reason, risks in construction project have become an inevitable feature and the industry is susceptible to numerous business, socio-political and technical risks that negatively influence project delivery. This study therefore investigates the causes of external risks factors in construction project delivery and the effect on project and organisational performance so that efficient control measures can be designed to minimise its occurrence. A quantitative research design was adopted, and the sample comprised of randomly selected construction professionals in the Western Cape Province. The data was statistically analysed using descriptive and inferential analyses. The salient findings revealed that socio-political-related risk factors were the major causes of risks during construction project delivery, these factors include labour strikes and disputes due to union issues, excessive influence by government on court proceedings regarding construction project disputes, and constraints on the availability and employment of expatriate staff. In addition, the study revealed the impact of external related risks on projects and organisational performance, and it was found that cost overrun was ranked the most significant on project performance and disputes between parties to the contract was ranked the most significant on organisational performance. In the context of the South African construction industry, previous studies tended to focus more on internal risks as opposed to external risks. Therefore, this study makes a contribution to the body of knowledge on the subject within a previously unexplored context. The study provides insights with regard to the sources of external related risks associated with construction project within the context of the South African construction industry.


Most civil engineering construction works, and the site investigations and planning decisions that precede them, are intimately concerned with the nature of the first few metres of the Earth's surface. The materials that constitute this zone were either deposited by the processes that took place in the Quarternary or have been significantly altered by them.This volume contains a collection of papers which examine in detail those processes, the properties of the materials that are produced by them and their implications for construction. The subject is considered from an international point of view with authors from 14 countries describing events in glacial, periglacial, temperate and tropical environments.The scene is set by P. G. Fookes whose keynote address describes from an engineer's perspective the events of the Quaternary and how they affected the surface of the Earth. Each environmental theme is introduced by a report on the papers by an eminent worker in that field and there are 'state of the art' reviews of the major themes by J. N. Hutchinson and G. E. Blight.This book is an important contribution to the engineering geological literature, especially relevant to today's international construction industry, combining clear overviews with detailed case studies which demonstrate the implications of Quaternary processes and materials in civil engineering operations.


2018 ◽  
Vol 27 (1) ◽  
pp. 71-81 ◽  
Author(s):  
Agnieszka Leśniak ◽  
Daniela Mačková ◽  
Grzegorz Piskorz ◽  
Marcela Spišáková

Any construction project, even one that is excellently planned and organized, is prone to the risk of unforeseen events and problems, which in effect can cause late completion of works. The paper presents the results of the research conducted among Polish and Slovakian building contractors. One attempt was to identify and assess the potential causes of delays in the construction works resulting from the provisions of the contract. The knowledge of these factors can help contractors to take protective measures, reducing the risk of delays during the implementation of construction works.


2013 ◽  
Vol 4 (2) ◽  
pp. 34-39
Author(s):  
Ting Sim Nee ◽  
Chin Lin Wei

Construction contract refers to an agreement which in enforced by law; standard form is printed form of contract to define responsibilities to various parties involved to complete the construction works. Malaysian construction industry relies essentially on a number of standard forms namely the JKR Sarawak Form of Contract, PWD 203A, PAM, IEM and CIDB forms to execute its construction projects. However, with the number of choices available and without a clear selection guide, selection of an appropriate standard form for the particular projects has hinged on the familiarity of the form users with the particular form. This study aims to identify the selection criteria that can be used for standard form selection. The study form looks into the current practice and how decisions are made to select the appropriate standard form. Selection criteria are identified and this research carried out verification works with local construction industry players via questionnaire survey method. Results from questionnaire survey also indicated that standard forms are usually predetermined by the client in tender stage. It is also shown that some of the respondents have limited exposure to certain standard forms of contract. With the selection criteria identified, it is hopeful that a selection guideline can be developed.


Webology ◽  
2021 ◽  
Vol 18 (Special Issue 04) ◽  
pp. 641-652
Author(s):  
Irina Gladilina ◽  
Svetlana Sergeeva ◽  
Nelli Kozhevnikova ◽  
Elizaveta Tokareva

The information eco-environment of the city, aimed at attracting investment, is designed to solve the problems of forming investment attractiveness, protection from unscrupulous investors, obtaining reliable information when justifying the implementation of investment projects, participation in them. Considering the dynamism of modern investment processes, the creation of an effective information eco-environment is an important component of the development of the investment process, especially from the point of view of ensuring effective interaction of its participants and attracting a wide range of investors to the investment activity process. Therefore, it is necessary to assess the impact of the information eco-environment on the processes of investment in the urban environment and increase the investment attractiveness of the city. However, the features of information support of the investment market specifically at the municipal level remain insufficiently studied. Based on the analysis of literary sources and an expert survey, this article examines the forms of information disclosure that are most effective from the point of view of investors; factors of investment attractiveness that should be paid attention to when forming an information eco-environment. Finally, this article suggests the identification of key areas of development of the urban information eco-environment, which can be transformed into the investment attractiveness of the city. The results showed that the systematic use of the information eco-environment of the city should create conditions for users to receive the necessary information promptly, which contributes to the activation of investment activity, increasing its efficiency.


2021 ◽  
Vol 33 (2) ◽  
Author(s):  
Mohd Ashraf Mohd Fateh ◽  
Tan Hee Yee

Every activity in a construction project is related to time and cost. Delay is considered common and often occurred in a construction project. A slight delay can be very costly. It will impact all of the related stakeholders. This paper seeks to identify the financial issues in the construction industry and the impact of the financial issues towards the projects in Malaysia. Literature reviews and questionnaire surveys were used to carry out the study. The data collected were analysed via Microsoft Excel and SPSS software. The paper reveals that the withholding of payment by the approval parties is the critical financial issues in Malaysia’s construction industry, while the main impact when the financial issues occurs is where the project is delayed/postponed/terminated. The findings of this research will give a good insight to the industry and help to improve the local players’ competitive capabilities as highlighted by the Construction Industry Development Board (CIDB) in the Construction Transformation Programme (CITP) 2016-2020 and in line with the Sustainable Development Goals (SDGs) that was introduced by the United Nations (UN).


Most construction projects are suffering from claims due to many reasons. Claim emergencies have risen for ten years due to the critical political situation. These claims have a bad impact on all groups who were work in the construction field. The impact of claim could be followed to cost overrun, loss of efforts and suspension of work, contract termination. This investigation means to recognize the real reason for causes of claim in construction and demonstrate their difference between respondent concerning individual, company and organization traits. It also aims found the important factors in developing for the management of construction project claim to predict claim occurrence and to mitigate the negative impact of a claim. The objective of the study achieved through a valid questionnaire obtained from several construction companies. The questionnaire survey was conducted involving the contractor, consultant, client point of view. The result of the questionnaire encountered in the SPSS software for finding the major factor that affects the construction. The finding demonstrates the absence of site attention to detect claims, detachment or inaccessible of related documents proactively, and conflicts which develop during owner/contractor negotiation are all critical issue related with the system of claim management. My work aims to distinguish the various claims through review paper and to recognize the most impacted causes of claim in our region.