Geotechnical Lessons Learned From Nineteen Railway Trenchless Crossings During Construction of a Transmission Pipeline

Author(s):  
Jack Park ◽  
Lisa Wheeler ◽  
Katherine Johnston ◽  
Mike Statters

Abstract When new pipelines are constructed, they often cross existing major infrastructure, such as railways. To reduce potential service disruption, it is a common practice to complete these crossings using trenchless technologies. Without proper methods and oversight in planning and construction, there may be serious safety and financial implications to the operators of the railways and the public due to unacceptable settlement or heave. If movement tolerances are exceeded, the schedule and financial loss to the railway operators could be in the millions of dollars per day. Recent construction of a new pipeline across the Canadian prairies implemented ground movement monitoring plans at 19 trenchless railway crossings in order to reduce the potential for impact to the track and railway operations. The specifics of the plan varied for each site and were based on the expected ground conditions, as well as permit requirements from the various railway operators, but typically included ground movement monitoring surveys, observation of the cuttings, recommendations for a soil plug at the leading edge of the bore casing, and frequent communication with both the railway operators and the contractors. For all crossings, the expected soil and groundwater conditions were obtained from pre-construction boreholes and confirmed during excavation of the bore bays. Based on the expected ground conditions, appropriate soil plug lengths, if required, were recommended. In general, fine-grained clay/silt-dominated soils needed minimal to no soil plug in order to minimize the potential for ground heave, while coarser-grained sand-dominated soils needed a longer soil plug in order to reduce the potential for “flowing soil” which would cause over excavation along the bore path. Prior to boring, surface monitoring points were established along the tracks to monitor for changes in the ground surface elevation. Additional subsurface points were installed for crossings where the potential for over excavation was higher. These monitoring points were surveyed before, throughout, and following completion of construction, and the frequency of the surveys was increased when the movement was nearing or exceeding specified tolerances. The effort to monitor and reduce the potential for ground movement was a coordinated effort between the geotechnical engineers, railway operators, and construction contractors. The purpose of this paper is to present the lessons learned from the 19 trenchless railway crossings, including the challenges and successes. Recommendations for ground movement monitoring are also provided to help guide railway operators, design and geotechnical engineers, and contractors during the construction of future trenchless pipeline crossings of railway infrastructure.

Author(s):  
Michael Porter ◽  
Clint Logue ◽  
K. Wayne Savigny ◽  
Fiona Esford ◽  
Iain Bruce

Natural hazards (also known as ground movement or geohazards) can cause pipeline failures, with consequences ranging from injury/death, environmental impact, and property damage, to lengthy service disruption and a failure to achieve delivery targets. In North America and western Europe, pipeline failure resulting from natural hazards are typically rare (but costly) events. However, where difficult ground conditions have not been properly accounted for in pipeline design, construction, and operation, natural hazards may have an overriding influence on pipeline risk and reliability. These issues are discussed, and a framework for estimating the influence of natural hazards on pipeline risk and system reliability is introduced.


2017 ◽  
Vol 63 (No. 8) ◽  
pp. 363-369
Author(s):  
Mikleš Milan ◽  
Helexa Milan ◽  
Mikleš Juraj

The issue of terrain conditions is very complex and its description is approached from different perspectives and with different objectives. Because it consists of the gathering of basic information for a mobile object, a wheeled forestry tractor, the terrain-vehicle approach was taken as the basis. Ground conditions are part of the operating conditions of wheeled forestry tractors. Uneven ground can be regarded as a source of vibration in the vehicle – towing truck. In this respect, given the random shape of the surface roughness, the solution to vibrations leads to a terrain correlation analysis in order to obtain a correlation function and power spectral density of the ground surface. Scanning of the ground micro-profile was performed using a device for quick terrain scanning, which from the mechanical aspect consists of a towing vehicle and a measuring carriage. Correlation function and power spectral density are the evaluation based on ground micro-profile measurements and the results of calculations. Measurements of forest terrain (road) micro-profile were done in the area of Little Fatra and Little Carpathians in Slovakia. In geological terms, the measurements were done in an area with the occurrence of gneiss, granite, limestone and flysch. No measurements were performed in a sandy area.


2020 ◽  
Vol 29 (1) ◽  
pp. 291-309 ◽  
Author(s):  
Laurance Donnelly

AbstractOne of the geohazards associated with coal mining is subsidence. Coal was originally extracted where it outcropped, then mining became progressively deeper via shallow workings including bell pits, which later developed into room-and-pillar workings. By the middle of the 1900s, coal was mined in larger open pits and underground by longwall mining methods. The mining of coal can often result in the subsidence of the ground surface. Generally, there are two main types of subsidence associated with coal mining. The first is the generation of crown holes caused by the collapse of mine entries and mine roadway intersections and the consolidation of shallow voids. The second is where longwall mining encourages the roof to fail to relieve the strains on the working face and this generates a subsidence trough. The ground movement migrates upwards and outwards from the seam being mined and ultimately causes the subsidence and deformation of the ground surface. Methods are available to predict mining subsidence so that existing or proposed structures and land developments may be safeguarded. Ground investigative methods and geotechnical engineering options are also available for sites that have been or may be adversely affected by coal mining subsidence.


1993 ◽  
Vol 18 ◽  
pp. 142-148 ◽  
Author(s):  
Masayuki Maki ◽  
Sento Nakai ◽  
Tsuruhei Yagi ◽  
Hideomi Nakamura

The mechanisms of strong winds associated with snow clouds, and the relationship between strong winds and blowing/drifting snow, were investigated. A snowstorm occurred with a typical L-mode snow band which was generated and organized longitudinally during a continental cold-air outbreak over the Sea of Japan. Doppler radar observations revealed that the snow band consisted of small echo cells arranged along the direction of the snow band. When one of the echo cells passed, blowing/drifting snow was generated and intensified by a snow cloud-induced gust, and the horizontal visibility near the ground surface was significantly decreased. Doppler radar and radiosonde data showed that the gust was due to the cold air outflow (CAO) from the snow clouds. The leading edge of the CAO was about 9 km ahead of the center of the snow cloud and the depth of the CAO was about 600 m near the forward flank of the snow cloud. The CAO was caused by a downdraft at the center of the snow cloud, which was initiated at a height of about 1.3 km and with a velocity in excess of 1 ms−1. The observed CAO speed was explained by the theory of the gravity current.


2017 ◽  
pp. 18-22 ◽  
Author(s):  
S. V. Usanov ◽  
◽  
A. V. Usanova ◽  

Author(s):  
R. Todd Swinderman ◽  
Greg Bierie ◽  
Andrew D. Marti ◽  
Barbara A. Wheatall

To address issues associated with the recently updated OSHA Instruction on combustible dust hazards, this presentation will explore an innovative concept of conveyor design. The author will also examine two “leading edge” conveyor technologies and review recent projects that employed these two technologies. This presentation will first address concerns associated with the OSHA Instruction on combustible dust hazards by exploring the architecture concept for conveyor design and the new dust accumulation resistant conveyor structure. This pioneering approach to conveyor design focuses on prevention of fugitive dust accumulation and ease of maintenance. The next of these advanced technologies is “engineered-flow” chutes. Designed from material testing and flow studies, these transfer chute systems provide better material control, continuous flow at higher capacities, and dramatic reductions in material spillage and the release of airborne dust. By regulating the path of material movement, these engineered chutes improve the load placement on the belt, eliminate chute blockages, reduce safety hazards, and minimize maintenance costs. A third leading edge conveying system is air-supported belt conveyors. Rather than using rollers, these leading edge systems use a film of air rising from a troughed pan to support the belt and cargo. These totally enclosed conveyors offer a number of benefits, including improved tracking, improved control of dust and spillage, and reduced friction and power consumption. In this presentation, the author will present “project profiles” of recent installations of these systems. The author will look at the reasons these systems were selected and report on the lessons learned from system engineering, installation, and operation. These projects will include systems handling Powder River Basin (PRB) coal in mines and power plants.


2006 ◽  
Vol 17 (7) ◽  
pp. 1733-1740 ◽  
Author(s):  
Yen-Te Ho ◽  
An-Bin Huang ◽  
Jui-Ting Lee

1979 ◽  
Vol 22 (88) ◽  
pp. 503-511 ◽  
Author(s):  
K. L. Dawson ◽  
T. E. Lang

AbstractNumerical hydrodynamic simulation of the jet-roof geometry for control of snow deposition to prevent cornice formation at mountain ridges is reported. Different jet-roof geometries are evaluated based upon the extent and size of the ground-surface stagnation region and the recirculation region to the lee of the roof. Results show that jet-roof length should be of the same order as nominal height of the roof from the ground surface. Efficient placement of the roof is shown to be that with the leading edge directly above the mountain ridge, and roof angle approximately equal to lee slope angle. In numerical simulation of flow-field start-up, near steady-state flow is approached in less than 1.0 s real time, indicating short transient-flow duration.


2014 ◽  
Vol 30 (1) ◽  
pp. 183-204 ◽  
Author(s):  
Thomas D. O'Rourke ◽  
Sang-Soo Jeon ◽  
Selcuk Toprak ◽  
Misko Cubrinovski ◽  
Matthew Hughes ◽  
...  

This paper explores key aspects of underground pipeline network response to the Canterbury earthquake sequence in Christchurch, New Zealand, including the response of the water and wastewater distribution systems to the MW6.2 22 February 2011 and MW6.0 13 June 2011 earthquakes, and the response of the gas distribution system to the MW7.1 4 September 2010 earthquake, as well as the 22 February and 13 June events. Repair rates, expressed as repairs/km, for different types of pipelines are evaluated relative to (1) the spatial distribution of peak ground velocity outside liquefaction areas and (2) the differential ground surface settlement and lateral ground strain within areas affected by liquefaction, calculated from high-resolution LiDAR survey data acquired before and after each main seismic event. The excellent performance of the gas distribution network is the result of highly ductile polyethylene pipelines. Lessons learned regarding the earthquake performance of underground lifeline systems are summarized.


2017 ◽  
Author(s):  
Ki-Young Eum ◽  
Young-Kon Park ◽  
Sang-Soo Jeon

Abstract. In recent years, leakages in aged pipelines for water and sewage in urban areas have frequently induced ground loss resulting in cavities. One third of the pipelines buried in Seoul city in South Korea are more than fifty years old. Train loadings and change in groundwater levels in the undiscerned development of urban areas induce roadbed settlements. Train derailment may occur as the roadbed exceeds the allowable settlements associated with location and size of the cavity adjacent to the roadbed. In this study, FLAC3D, which is a three-dimensional finite-difference numerical modeling software, is used to do stability and risk level assessment for the roadbed in adjacent to urban railways with respect to various groundwater levels and the geometric characteristics of cavities. Numerical results show that the roadbed settlements in simulated ground conditions in South Korea, that satisfy the allowable values for a cavity of diameter of 10 m exists adjacent to the roadbed. The distance between the center of the roadbed and the center of the cavity should be greater than 25 m and the groundwater level should be greater than 22 m below the ground surface.


Sign in / Sign up

Export Citation Format

Share Document