scholarly journals A Study on the Seismic Response Characteristics of an Oblique Pile Group-Soil-Structure with Different Pile Caps

2019 ◽  
Vol 2019 ◽  
pp. 1-12 ◽  
Author(s):  
Desen Kong ◽  
Yifei Bai ◽  
Yongpo Chen ◽  
Meixu Deng

For the study of interaction between piles-soil-structure with different caps, the FLAC3D finite difference software was used as the research tool, and dynamic load was El Centro seismic wave. The numerical model of obliquely pile groups of the pile-soil-structure with low cap and high cap was established, respectively. The variation of pore pressure, the moment, the displacement of piles, and the displacement of pier was analyzed. The results indicate that under the action of earthquake, the distribution of pore water pressure in the soil layer increases gradually from top to bottom. The instantaneous negative value of partial soil due to shear dilation occurs at the peak of vibration acceleration. The middle area of the pile foundation in sandy soil is prone to liquefaction. In the same model, the maximum bending moment of inclined piles is greater than that of vertical piles. The vertical displacement of the vertical piles is a constant value along the depth, while the vertical displacement of the inclined piles is changed along the depth of the buried piles. In the high cap model, the horizontal displacement of the inclined piles is no longer monotonous along the burying depth, and the maximum value occurs in the sand soil layer. The vertical and horizontal displacements of the inclined piles and vertical piles in the high cap model are obviously greater than those of the low cap model. The maximum horizontal displacement of the pier of the two models occurs at the same time.

2020 ◽  
Vol 2020 ◽  
pp. 1-15
Author(s):  
Shaofu Gu ◽  
Weizheng Liu ◽  
Mengyuan Ge

The south extension line was constructed as a new part of the Xintai Expressway in Guangdong Province, China. The project required the construction of an embankment over soft soil with a thickness of up to approximately 14.0 m, and prestressed pipe pile was selected for reinforcing the soft soil foundation to increase bearing capacity and reduce settlement. Embankment sliding with a length of approximately 110 m and cracking with a length that exceeded 300 m occurred before the construction of the pavement structure. Field investigation and theoretical analysis results indicate that the safety factor of the overall stability calculated by the existing code methods is overly large, thereby resulting in large design pile spacing, low design bearing capacity provided by single pile, and excessive load shared by subsoil between piles. These results all cause the flow sliding of soft soil between the piles and the bending fracture of some piles. The revised density method can be used to check the stability of flow sliding, and the bending moment of piles should also be checked during the embankment design stage. In addition, perpendicularity deviation and poor joint quality of pile construction also contributed to the reduction of the bearing capacity of the pipe piles and the overall stability of embankment. Reconstruction of additional rigid piles and add pile after drilling holes are adopted in the sliding and cracking sections to reinforce the failed embankment, respectively. The remediation effect was validated by the measured excess pore water pressure, subgrade settlement, and horizontal displacement.


2015 ◽  
Vol 764-765 ◽  
pp. 1041-1045
Author(s):  
Meng Hsiu Hsieh ◽  
Wen Yi Hung ◽  
Chung Jung Lee

A series of grouped-model piles (2×2) centrifuge shaking table tests at an acceleration of 80 g was conducted to simulate seismic responses of a grouped-piles embedded in liquefiable sandy soil subjected to different magnitudes of earthquake loading. The tested grouped-piles connected with a pile cap are used to support 4 sets of model dry storage tank.Different test conditions including elevations of pile cap, elevations of ground water table, and dry and saturated sand beds all are reported in the study. Sensors (i.e., strain gauges along the depths of pile for measuring the bending moments, accelerometers for measuring the accelerations at different depths, LVDTs and pore water pressure transducers) densely instrumented in the piles and the surrounding soils provide valuable information for examining their evolution at various degrees of liquefaction. The magnitudes of bending moment along pile depths would increase with the increases of base shaking. The lowest bending moments were measured for the grouped–piles with the pile cap embedded in the dry sand bed while the largest lowest bending moments for the grouped–piles with the pile cap embedded in the saturated sand bed with the water table at the surface. The test results can be used to validate the results derived from the numerical simulation.


Author(s):  
Milad Souri

The results of five centrifuge models were used to evaluate the response of pile-supported wharves subjected to inertial and liquefaction-induced lateral spreading loads. The centrifuge models contained pile groups that were embedded in rockfill dikes over layers of loose to dense sand and were shaken by a series of ground motions. The p-y curves were back-calculated for both dynamic and static loading from centrifuge data and were compared against commonly used American Petroleum Institute p-y relationships. It was found that liquefaction in loose sand resulted in a significant reduction in ultimate soil resistance. It was also found that incorporating p-multipliers that are proportional to the pore water pressure ratio in granular materials is adequate for estimating pile demands in pseudo-static analysis. The unique contribution of this study is that the piles in these tests were subjected to combined effects of inertial loads from the superstructure and kinematic loads from liquefaction-induced lateral spreading.


2013 ◽  
Vol 438-439 ◽  
pp. 1171-1175
Author(s):  
Zhi Li Sui ◽  
Zhao Guang Li ◽  
Xu Peng Wang ◽  
Wen Li Li ◽  
Tie Jun Xu

Dynamic consolidation method has been widely used in improving soft land, but always inefficient to saturated soft clay land, which is hard to improve, and even leads to rubber soil. Dynamic and drain consolidation method will deal with it well, with drainage system, pore-water can be expelled instantly from saturated soft clay as impacting. The pore-water pressure and earth pressure test in construction, the standard penetration test, plate loading test, geotechnical test after construction, which are all effective methods for effect testing. There is a comprehensive detection through different depth of soil layer with different detecting means on construction site. The results show that improving saturated soft clay land with dynamic and drain consolidation method has obtained good effect, and the fruit can be guidance for such construction in the future.


Author(s):  
Dingwen Zhang ◽  
Anhui Wang ◽  
Xuanming Ding

A series of shaking table model tests were performed to examine the effects of deep cement mixing (DCM) columns with different reinforcement depths on the seismic behavior of a pile group in liquefiable sand. Due to the DCM column reinforcement, the fundamental natural frequency of the model ground increases noticeably. The excess pore pressure of soils reduces with the increase of reinforcement depths of the DCM columns. Before liquefaction, the acceleration response of soils in the improved cases is obviously lower than that in the unimproved case, but the acceleration attenuation is greater after liquefaction in the unimproved case. Moreover, the lateral displacement of the superstructure, the settlement of the raft, and the bending moment of the piles in the improved cases are significantly reduced compared to those in the unimproved case, and the reduction ratios rise with the increase of reinforcement depth of the DCM columns. However, reinforcement by the DCM columns may result in the variation of the location of the maximum moment that occurs in the pile.


2018 ◽  
Vol 203 ◽  
pp. 04011
Author(s):  
Ong Yin Hoe ◽  
Hisham Mohamad

There is a trend in Malaysia and Singapore, engineers tend to model the effect of TBM tunneling or deep excavation to the adjacent piles in 2D model. In the 2D model, the pile is modelled using embedded row pile element which is a 1-D element. The user is allowed to input the pile spacing in out-of-plane direction. This gives an impression to engineers the embedded pile row element is able to model the pile which virtually is a 3D problem. It is reported by Sluis (2014) that the application of embedded pile row element is limited to 8D of pile length. It is also reported that the 2D model overestimates the axial load in pile and the shear force and bending moment at pile top and it is not realistic in comparison to 3D model. In this paper, the centrifuge results of single pile and 6-pile group - tunneling problem carried out in NUS (National University of Singapore) are back-analysed with Midas GTS 3D and a 2D program. In a separate case study, pile groups adjacent to a deep excavation is modelled by 3D and 2D program. This paper compares the deflection and forces in piles in 2D and 3D models.


Author(s):  
Chao-Lung Yeh ◽  
Wei-Cheng Lo ◽  
Cheng-Wei Lin ◽  
Chung-Feng Ding

Abstract. There are many factors causing land subsidence, and groundwater extraction is one of the most important causes of subsidence. A set of coupled partial differential equations are derived in this study by using the poro-elasticity theory and linear stress-strain constitutive relation to describe the one-dimensional consolidation in a saturated porous medium subjected to pore water pressure change due to groundwater table depression. Simultaneously, the closed-form analytical solutions for excess pore water pressure and total settlement are obtained. To illustrate the consolidation behavior of the poroelastic medium, the saturated layer of clay sandwiched between two sand layers is simulated, and the dimensionless pore water pressure changes with depths and the dimensionless total settlement as function of time in the clay layer are examined. The results show that the greater the water level change in the upper and lower sand layers, the greater the pore water pressure change and the total settlement of the clay layer, and the more time it takes to reach the steady state. If the amount of groundwater replenishment is increased, the soil layer will rebound.


2014 ◽  
Vol 1030-1032 ◽  
pp. 1037-1040
Author(s):  
Jin Fang Hou ◽  
Ju Chen ◽  
Jian Yu

The artificial island ground on an open sea is covered by thick soft soil. It must be improved before using. In accordance with a designing scheme, the ground treatment method is inserting drain boards on land and jointed dewatering surcharge preloading, the residual settlement is not more than 30cm after improvement and the average consolidation degree is more than 85%. In order to estimate ground improvement effect and construction safety, instruments are buried to monitor the whole ground improving processes. By monitoring settlement and pore water pressure, it is shown that the total ground settlement in construction is 2234mm, its final settlement is 2464mm, and consolidation degree and residual settlement respectively satisfy requirements. In ground improvement, horizontal displacement is small and construction is safe. Meanwhile, the results of soil properties and vane shear strength detection tests show the soft soil ground is greatly reduced in water content and porosity ratio, and improved in strength. It is named that the ground improvement method is reasonable and reaches expected effect.


Geosciences ◽  
2019 ◽  
Vol 9 (3) ◽  
pp. 138 ◽  
Author(s):  
Yasutaka Tanaka ◽  
Taro Uchida ◽  
Hitoshi Nagai ◽  
Hikaru Todate

Soil pipes are commonly found in landslide scarps, and it has been suggested that build-up of pore water pressure due to clogged soil pipes influences landslide initiation. Several researchers have also suggested that entrapped air in the soil layer increases the pore water pressure. We carried out bench-scale model experiments to investigate the influence of soil pipes and entrapped air on the build-up of pore water pressure. We installed a water supply system consisting of an artificial rainfall simulator, and used a water supply tank to supply water to the model slope and artificial pipe. We used two types of artificial pipe: A straight pipe, and a confluence of three pipes. Furthermore, we placed a layer of silica sand on top of the model slope to investigate the effect of entrapped air in the soil layer on the build-up of pore water pressure. Silica sand is finer than the sand that we used for the bulk of the model slope. Our results indicate that, although artificial pipes decrease the pore water pressure when the amount of water supplied was smaller than the pipe drainage capacity, the pore water pressure increased when the water supply was too large for the artificial pipe to drain. In particular, the confluence of pipes increased the pore water pressure because the water supply exceeded the drainage capacity. The results also indicate that entrapped air increases the pore water pressure in the area with relatively low drainage capacity, too. Based on these results, we found that although soil pipes can drain a certain amount of water from a soil layer, they can also increase the pore water pressure, and destabilize slopes. Furthermore, entrapped air enhances the trend that the pore water pressure can increase in the area with relatively low drainage capacity, as pore water pressure increases when too much water is supplied, and the artificial pipe cannot drain all of it.


2018 ◽  
Vol 38 ◽  
pp. 03027
Author(s):  
Bin Bin Xu

Usually the natural sedimentary soils possess structure more or less, which makes their mechanical response much different from the fully remolded soils. In this paper, the influence of soil structure on the mechanical response such as compressibility, shear, permeability is literately reviewed. It is found that the compressibility and consolidation behavior of structured and remolded soils can be divided clearly before or after the structural yield stress. The stress-strain relationship can be divided into two segments before and after the structural yield stress. Before the yield stress, the curve is elevating and after the yield stress the curve is decreasing. The increasing rate of pore water pressure increases after the soil reached yield stress.


Sign in / Sign up

Export Citation Format

Share Document