Incorporating Uncertainties in Well-Count Optimization With Experimental Design for the Deepwater Agbami Field

2005 ◽  
Vol 8 (06) ◽  
pp. 548-560 ◽  
Author(s):  
Gene M. Narahara ◽  
John J. Spokes ◽  
David D. Brennan ◽  
Gregor Maxwell ◽  
Michael S. Bast

Summary This paper describes a methodology for incorporating uncertainties in the optimization of well count for the deepwater Agbami field development. The lack of substantial reservoir-description data is common in many deepwater discoveries. Therefore, the development plan must be optimized and proven to berobust for a wide range of uncertainties. In the Agbami project, the design of experiments, or experimental design (ED) technique, was incorporated to optimize the well count across a wide range of subsurface uncertainties. The lack of substantial reservoir-description data is common for many deepwater discoveries. In the Agbami project, the uncertainty in oil in place was significant (greater than a factor of 2). This uncertainty was captured in a range of earth (geologic) models. Additional uncertainty variables, including permeability, fault seals, and injection conformance, were studied concurrently. Multiple well-count development plans (high, mid, and low) were developed and used as a variable in ED. The ED technique allowed multiple well counts to be tested quickly against multiple geologic models. With the net present value (NPV) calculated for each case, not only was the well count for the overall highest NPV determined, but discrete testing of each geologic model determined the optimum well count for each model. The process allowed for testing the robustness of any well count vs. any uncertainty (or set of uncertainties). A method was demonstrated quantifying the difference between perfect and imperfect knowledge of the reservoir description (geologic model) as it pertains to well locations. Introduction The Agbami structure is a northwest/southeast-trending four-way closure anticline and is located on the Niger delta front approximately 65 miles offshore Nigeria in the Gulf of Guinea (see the map in Fig. 1). The structure spans an area of 45,000 acres at spill point and is located in 4,800 ft of water. The Agbami No. 1 discovery well was drilled in late 1998. The appraisal program was completed in 2001 and included five wells and one sidetrack drilled on the structure, with each encountering oil pay. These five wells and a sidetrack penetrated an average of approximately 350 ft of oil. In this phase (Phase 3) of the development process, the key objectives are to construct a field-development plan and to obtain sanctioning. With drilling depths of up to 10,000 ft below mudline in 4,800 ft of water, well costs at Agbami will be at the high end of typical deepwater costs. Therefore, an important optimization parameter in the field development is the total well count. Agbami is typical of many deepwater developments in that the seismic is less than perfect and the appraisal well data are sparse relative to the area coverage. Therefore, subsurface uncertainty is high. In fact, the 5% probable oil in place is more than two times the oil in place at the 95% probability. As a result, the development process is challenged with determining the optimum well count for the field development across the wide range of subsurface uncertainty. Several key development decisions were determined in the previous phase(Phase 2) of the development process. These decisions were taken as givens in this study and are listed as follows:• The recommended pressure-maintenance scheme and gas-disposition strategy for the 17 million-year (MY) units is a combination of crestal gas injection with peripheral water injection.• The recommended pressure-maintenance scheme and gas-disposition strategy for the 14MY/16MY units is crestal gas injection only.• The facility design capacity recommendations are:- 250,000 stock-tank bbl per day (STB/D) oil.- 450,000 thousand cubic ft per day (Mcf/D) gas production.- 250,000 STB/D water production.- 450,000 STB/D liquid production.- 450,000 STB/D water injection.

2021 ◽  
Author(s):  
Jiaxi Gao ◽  
Yuedong Yao ◽  
He Bao ◽  
Jinjiang Shen

Abstract: Yanchang Oilfield conducts systematic research on nitrogen injection to enhance oil recovery. Through the research of this project, the energy supplement method of horizontal wells suitable for the study area is determined, and its injection system and process parameters are optimized and determined. The optimal energy replenishment method selected by the mine field test achieves the following economic and technical indicators: Provide a nitrogen suitability evaluation plan; Complete the nitrogen flooding matching process design of the target well; Complete the design of the injection-production plan for the target well; Compare with other energy supplement methods. Through the analysis of two supplementary energy methods of water injection and gas injection in indoor and similar reservoirs, the following understandings have been obtained: (1) Nitrogen is insoluble in water, slightly soluble in oil, good swelling, large elastic energy, is an inert gas, exists widely in the atmosphere, inexhaustible, inexhaustible, has a wide range of sources. (2) the recovery rate of nitrogen flooding is significantly higher than that of water flooding. (3) The field test results of water injection and nitrogen test in similar reservoirs show that the supplementary formation energy of nitrogen injection is suitable for the later development of Chang 64 and Chang 71 in the Haobasi oil field. (4) Compared with deep ultra-low permeability reservoirs, it is more economical to use nitrogen to supplement formation energy and change oil. The rate is higher. From the above analysis, it can be seen that the supplementary energy of Chang 64 and Chang 71 reservoirs in the Haobasi oil area should be nitrogen injection as the main supplement, and water injection as a supplement. Gas/water alternate injection is used to adjust the gas injection profile to slow down the escape of injected nitrogen. . Although water injection supplements the formation energy with greater uncertainty, it can be used as a technical means of fluidity control in the gas injection process and is relatively economical.


2021 ◽  
Author(s):  
Ankaj Kumar Sinha ◽  
Shlok Jalan ◽  
Rakesh Ranjan ◽  
Rahim Masoudi

Abstract Identification of an optimal field development plan is one of the most critical decisions for oil asset management. In the new norm of low oil prices, this assumes even more relevance for mature oilfields to maximize overall recovery. In greenfield developments and oilfields in early production life, the absence of a clear roadmap detailing their future development strategy can often lead to missed opportunities and sub-optimal recovery. To bridge this gap, Petroliam Nasional Berhad (PETRONAS) began identifying new improved oil recovery (IOR) opportunities in mature fields and started formulating an optimal development plan in greenfields. In 2019, PETRONAS embarked on implementing the Reservoir Performance Benchmarking (RPB) tool to evaluate reservoir recovery potential with waterflood. This paper will detail the Phase-II development of this data-analytics based tool which focuses on delivering a comprehensive roadmap, which includes other recovery mechanisms such as gas injection and reservoir under primary recovery. Phase-I of RPB tool (SPE-196443) had considered water injection as a key secondary recovery process to evaluate the benchmark recovery factor for an oil reservoir. As part of Phase-II development, this has been further enhanced to evaluate field recovery potential and provide the benchmark recovery factor for primary recovery and gas injection processes. For fields under primary recovery, a comparative assessment between volumetric depletion and varying aquifer/gas-cap drive is conducted to ascertain the recovery potential. Assessment for incremental secondary recovery gains considers both gas injection and water injection scenarios in the enhanced benchmarking methodology. In addition, the benchmarking calibration methodology has also focused on incorporating additional reservoir parameters specific to each of the recovery processes for overall estimation of the benchmark value. The benchmarking tool also identifies analogue reservoirs to enable replication of best development practices and optimization of the development strategy. With the deployment of this enhanced RPB tool, a comprehensive 5-year roadmap has been developed to improve Malaysian oilfields recovery. This has enabled PETRONAS to augment its resource funnel inventory, streamline its opportunity ranking and integrate project maturation tracking with existing digital platforms of its entire portfolio. This is a novel benchmarking tool to assess reservoir potential recovery factor for primary and secondary recovery processes (both water and gas injection) along with analogue identification for replication of best development practices


2001 ◽  
Vol 4 (01) ◽  
pp. 26-35
Author(s):  
Richard W. Smith ◽  
Rodolfo Colmenares ◽  
Eulalio Rosas ◽  
Isaura Echeverria

Summary The El Furrial field is one of Venezuela's major field assets and is operated by PDVSA (Petroleos de Venezuela, S.A.), the national oil company. Its current production of more than 450,000 BOPD makes it a giant oil field. Development of the field, which has an average reservoir depth of approximately 15,000 ft, is in its mature stages owing to implementation of high-pressure gas injection. PDVSA has consistently followed a forward planning approach related to reservoir management. Using high-angle deviation drilling techniques allows development wells to be strategically located by penetrating the reservoir at high angles to optimize production rate, extend well life, increase reserves per well, reduce operating expenses, and reduce total field development costs. A reservoir model was constructed and simulated with detailed reservoir stratigraphy to determine realistic potential of high-angle wells (HAW's). Five wells had been drilled as of June 2000, and the first four wells have proved the effectiveness of the design. The philosophy, modeling technique, well design considerations, problems encountered, well results, and economic criteria provide a clear understanding of the risk of this technology not previously used at this depth in Venezuela. The result was the first HAW in the deep, challenging environment of eastern Venezuela. Results show that optimization objectives can be attained with HAW's, mainly increasing per-well production rate, maximizing per-well recovery, and extending the breakthrough time of gas or water from pressure maintenance and enhanced oil recovery projects. Well results indicate that the geological and simulation modeling technique is reliable and accurate. A pilot program shows that HAW technology provides major advantages to increase production rate and reduce the overall number of wells needed to reach production objectives. However, the project also has experienced a number of unexpected drilling problems.1 The costs associated with the total project are significant, but more importantly, this program becomes very attractive because of the long-term benefits of decreased water-cut related to current water injection; decreased gas breakthrough owing to high-pressure gas injection, and fewer wells required to meet production goals. Technical contributions include the following:The modeling technique of applying detailed stratigraphy to a full-scale reservoir model is accurate if performed with the appropriate objectives in mind.The application of state-of-the-art drilling techniques to attain high angles at deep drilling depth is possible; however, drilling problems caused by formation instability require more study and experience.This method can be applied to other fields in the eastern Venezuelan basin currently under, or planned to be under, enhanced recovery programs and development programs. Introduction The El Furrial field is one of several giant fields found northwest of Maturin, Venezuela, in what is described as the El Furrial thrust trend (location shown in Fig. 1). The field was discovered in 1986 with the FUL-1 well, which established production from the Naricual formation. A late 1996 study, using a full-field simulation model of the El Furrial field, showed that problems associated with gas or water breakthrough in producing wells from high-pressure gas injection and water injection can be reduced with this technology. The potential to reduce problems comes from drilling infill wells at a high angle between the advancing gas and water fronts. High-pressure gas injection was started in 1998 and was justified, in part, by this work and other associated studies. The field produces from two formations, the Naricual and Los Jabillos, giving a total gross thickness of more than 1,500 ft. The primary 1,200-ft-thick Naricual formation is divided into three major stratigraphic sequences - the Superior (upper), Medio (middle), and Inferior (lower). Net-to-gross ratio is typically 80%. Philosophy PDVSA has consistently maintained reservoir models through the years to aid in reservoir management.2 To date, eight full-field and numerous sector-simulation models have been built. Optimization of the field began in 1996. During the study, it was noted that predictions of conventional vertical infill wells drilled into the structure had short production lives because of water or gas breakthrough. The review identified the possibility of placing well trajectories between the advancing water and gas fronts. One benefit was that the production rate from new wells could be increased; this indicated that the number of development wells could be reduced, saving investment costs. Thus, the following objectives were determined.Define optimization alternatives of the El Furrial field well-development scheme. The use of nonconventional well completions such as vertical large interval single completions (LISC) and high-angle completion (HAC) wells may present a higher potential for meeting production needs at a lower total development cost.Define the most reasonable completion configuration for new wells in El Furrial field. It is probable that the entire Naricual acts as a single reservoir unit, with at least partial vertical communication existing in the majority of the field caused by fault juxtaposition and limited fractures associated with faults. Therefore, single completions in all of Naricual Superior and Medio, or Naricual Medio and Inferior, may present viable completion alternatives.Provide technical support to the Venezuelan Ministry of Mines and Energy, which approves operation philosophy, development, and completion practices. The HAW program was different from the previous accepted philosophy, so technical support was necessary to permit the FUL-63 pilot test well. High-Angle Wells This work was split into two parts. The first was an evaluation of HAC wells as an alternative to current vertical-well strategies. This includes the possible alternative of LISC completions for all of Naricual Superior and Medio. The second was additional simulation cases to test the potential development plan with only HAC wells in a full-scale reservoir model.


2021 ◽  
Author(s):  
M. Fitri Ramli ◽  
M. Shahrul M. Long ◽  
Amol Nivrutti Pote ◽  
Khairul Azri Ishak

Abstract This paper discusses the workflow and method of selecting optimum number of infill and injection wells based on incremental recovery. Normally, for infill wells study, a ‘creaming curve’ method is used to evaluate the optimum number of wells against incremental recovery from the field. However, in the case of determining number of infill wells together with water injection wells, a more comprehensive approach is needed. One needs to evaluate the pressure depletion rate from existing and infill wells together with the dynamic of the producer-injector pairings as well as the sweeping factor. The paper is based on infill and water injection development plan for a brown field in Sabah basin which located in Malaysia. To maintain operatability of the field in the future, several new infill and water injection wells options are evaluated for optimum field life oil production. Unlike infill or producer-only assessment, the same ‘creaming curve’ approach for combination of infill and water injection wells is less effective as large number of simulation runs are needed to sample the combination of these wells that generate optimum oil recovery. This has proven to be challenging especially when the models are large which is normally the case for brown fields and it requires extensive computational hours. In the first part, a modified approach bringing some pre-analytic assessment of producer-injector pairing is being used. The pairings are first ranked based on streamlines visualization, drainage tables and their respective contributions towards oil recovery. The ‘creaming curve’ is then built based on the highest contribution as well as the sequencing of the pairings. The second method mentioned in this paper is the numerical approach through multi-objective optimization using assisted history matching and uncertainty tool. With the help of optimizer, the number of simulation runs can be drastically reduced when only best combination of infills and injectors for each total number of wells are considered. Both alternative methods will be compared with the full computational runs, sampling every single combination of wells. Finally, the optimum number of wells with the combination of infill and water injection wells are analysed based on cumulative oil recovery against the Net Present Value (NPV). This case study therefore demonstrates how alternative methods can be used to resolve the optimum number of infill and water injection wells to avoid lengthy and very large numbers of simulation runs.


2013 ◽  
Vol 340 ◽  
pp. 27-30
Author(s):  
Quan Hou Li ◽  
Wei Qu ◽  
Hang Chi Li

The well casing damage is common during the oilfield exploitation .Analysis on casing damage in a wide range , especially in the late term of exploitation ,indicates that the major influence factors which lead to wide-range casing damage are water injection pressure , block pressure differential and water soaked area .We conclude several types of abnormal strata pressure distribution which are common existing after water injection .These analysis are good preparation for monitoring and take precaution against casing damage .It has significant benefits for prolonging oil and water well casings serviceable life , as well as sustainable and stable production.


2017 ◽  
Author(s):  
Fazeel Ahmad ◽  
Arlen Sarsekov ◽  
Hiroki Iwama ◽  
Omar Yousaf Saif ◽  
Abdalla Abed ◽  
...  

2021 ◽  
Author(s):  
Basel AL-Otaibi ◽  
Issa Abu Shiekah ◽  
Manish Kumar Jha ◽  
Gerbert de Bruijn ◽  
Peter Male ◽  
...  

Abstract After 40 years of depletion drive, a mature, giant and multi-layer carbonate reservoir is developed through waterflooding. Oil production, sustained through infill drilling and new development patterns, is often associated with increasingly higher water production compared to earlier development phases. A field re-development plan has been established to alleviate the impact of reservoir heterogeneities on oil recovery, driven by the analysis of the historical performance of production and injection of a range of well types. The field is developed through historical opportunistic development concepts utilizing evolving technology trends. Therefore, the field has initially wide spacing vertical waterflooding patterns followed by horizontal wells, subjected to seawater or produced water injection, applying a range of wells placement or completion technologies and different water injection operating strategies. Systematic categorization, grouping and analyzing of a rich data set of wells performance have been complemented and integrated with insights from coarse full field and conceptual sector dynamic modeling activities. This workflow efficiently paved the way to optimize the field development aiming for increased oil recovery and cost saving opportunities. Integrated analysis of evolving historical development decisions revealed and ranked the primary subsurface and operational drivers behind the limited sweep efficiency and increased watercut. This helped mapping the impact of fundamental subsurface attributes from well placement, completion, or water injection strategies. Excellent vertical wells performance during the primary depletion and the early stage of water flooding was slowly outperformed by a more sustainable horizontal well production and injection strategy. This is consistent with a conceptual model in which the reservoir is dominated by extensive high conductive features that contributed in the early life of the field to good oil production before becoming the primary source of premature water breakthrough after a limited fraction of pore volume water was injected. The next level of analysis provided actual field evidence to support informed decisions to optimize the front runner horizontal wells development concept to cover wells length, orientation, vertical placement in the stratigraphy, spacing, pattern strategy and completion design. The findings enabled delivering updated field development plan covering the field life cycle to sustain and increase field oil production through adding ~ 200 additional wells and introducing more structured water flooding patterns in addition to establishing improved wells reservoir management practices. This integrated study manifests the power, efficiency and value from data driven analysis to capture lessons learned from evolving wells and development concepts applied in a complex brown field over six decades. The workflow enabled the delivery of an updated field development plan and production forecasts within a year through utilizing data analytics to compensate for the recognized limitations of subsurface models in addition to providing input to steer the more time-consuming modeling activities.


2021 ◽  
Author(s):  
Mohd Azri Hanifah ◽  
Sai Ravindra Panuganti ◽  
Nur Atiqah Zakaria ◽  
Nur Hazrina Kamarul Zaman ◽  
Raj Deo Tewari

Abstract A deep-water Field X with two major Reservoirs U and L discovered recently offshore Malaysia is on development for early production. The subsurface plan for the Field X includes water injection. But the presence of sulphate rich seawater can provide a favorable environment for souring activity to take place. This study evaluates the reservoir souring potential for the green Field X as a result of seawater flooding. Reservoir souring is the increase of the hydrogen sulfide (H2S) concentration in produced reservoir fluids. As hydrogen sulfide is a highly toxic and corrosive gas, the production of H2S has a huge impact on the safety, infrastructure and facilities of the field. Whether a reservoir is susceptible to souring is dependent on a variety of factors. Some of these include water injection flow rate, temperature of the reservoir, presence of bacterial nutrients and rock minerology. Effective prediction of biogenic reservoir souring using computer models is essential when undertaking major technical and economic decisions regarding field development. For H2S concentration calculation PETRONAS utilized in-house stand-alone modeling tool that considers physicochemical hydrodynamics of multiphase flow, heat transfer, substrate propagation and bacterial activity. The simulator looks at bacterial growth both in planktonic and sessile forms. Monod kinetics is applied for the growth of bacteria, leading to the consumption of sulphate and volatile fatty acids which in-turn is linked to H2S generation. Along with H2S propagation, H2S scavenging by rock and H2S partitioning between the various phases is also accounted for. The model can also deal with the effects of lift gas, reinjection of sour produced water, injection of biocide and nitrite. Since the Field X is a green field and historical production data is unavailable, the model is calibrated against the provided field development plan (FDP) data with sensitivity analysis. The simulation runs show that the H2S breakthrough occurs before the end of production. The amount of H2S produced indicates that the risk of reservoir souring associated with seawater injection in U and L Reservoirs of the Field X is high. It is recommended to evaluate different reservoir souring preventive measures in combination with mitigative options in terms of chance of success, risks, and cost (CAPEX/OPEX) in the context of the Field X development plan.


2016 ◽  
Vol 18 (1) ◽  
pp. 39-53
Author(s):  
Omar Salih ◽  
Mahmoud Tantawy ◽  
Sayed Elayouty ◽  
Atef Abd Hady

Sign in / Sign up

Export Citation Format

Share Document