scholarly journals Usefulness and fields of the application of the Earned Value Management in the implementation of construction projects

2014 ◽  
Vol 13 (4) ◽  
pp. 357-364
Author(s):  
Agnieszka Dziadosz ◽  
Oleg Kapliński ◽  
Mariusz Rejment

The Earned Value Method allows the prediction of future values of the total cost and duration of the construction project realization, and also it allows the early detection of the collisions between the schedule and the construction project budget. It is more often indicated its usefulness for monitoring and controlling the construction work progress in the time and cost formulation. It is used, in the indirect way, to control the risk in terms of the cost overruns of the construction project realization and in case of the failure to meet the deadline for completion of the construction project. The authors’ goal was not only to indicate the advantages of the method (widely discussed in the literature) but also to indicate some inaccuracies in the application of the Earned Value Method, which may affect the costs forecasting and the date of completion of the construction project. The conclusions are based on the analysis of several construction project realizations.

2019 ◽  
Vol 5 (1) ◽  
pp. 13-19
Author(s):  
Fitri Nur Kharina ◽  
Kusno Adi Sambowo

Construction projects in all regions continues to be developed for the creation of facilities that can be utilized by the community. One of them is the construction of apartments which are now being intensively carried out to meet residential needs for the community. Making a construction project plan always refers to estimates that exist at the time development plan is made, therefore problems can arise if there is a discrepancy between the plans that have been made and the actual reality. So the impact that often occurs is the delay in the time of project implementation which can also be accompanied by an increase in the cost of implementing the project. In the construction project of Cinere Terrace Suites Apartemen & Citywalk, Jakarta there was a delay resulting in a late payment of monthly bill progress by the owner. Based on the above reasons, this research was conducted to find out how the project performance was seen from the cost and time period of the review period. how is the estimated cost and time to complete the overall project work. The method used in the analysis of this study is the Earned Value Method. Based on the results of the analysis carried out for 29 weeks the project performance on schedule has been delayed and cost shows a positive value. For the estimated completion time of the project there is an increase in time whose duration increases from the planned 98 weeks or 685 days to 109,624 weeks or 768 days. While the estimated cost of completing the project from the results of the analysis obtained a value of Rp. 270,147,448,569.16 smaller than the planned cost of Rp. 315,272,727,272.73. With the difference VAC of Rp. 45,125,278,703.57 this shows that there are benefits obtained by the contractor.


2019 ◽  
Vol 19 (3) ◽  
pp. 186-200
Author(s):  
Deborah B. Kim ◽  
Edward D. White ◽  
Jonathan D. Ritschel ◽  
Chad A. Millette

Purpose Within earned value management, the cost performance index (CPI) and the critical ratio (CR) are used to generate the estimates at completion (EACs). According to the research in the 1990s, estimating the final contract’s cost at completion (CAC) using EACCR is a quicker predictor of the actual final cost versus using EACCPI. This paper aims to investigate whether this trend stills holds for modern department of defense contracts. Design/methodology/approach Accessing the Cost Assessment Data Enterprise (CADE) database, 451 contracts consisting of 863 contract line item numbers (CLINs) were initially retrieved and analyzed in three stages. The first replicated the work conducted in 1990s. The second stage entailed calculating 95 per cent confidence intervals and hypothesis tests regarding percentage accuracy of EACs for a contract’s final CAC. Lastly, regression analysis was conducted to characterize major, moderate and minor influencers on EAC reliability. Findings For modern contracts, EACCR aligns more with EACCPI and no longer demonstrates early accuracy of a contract’s final CAC. Contract percentage completion strongly reduced the per cent error of estimating CAC, while cost-plus-fixed-fee contracts and those with no work breakdown structure greater than Level 2 negatively affected accuracy. Social implications To militate against optimism of early assessment of a contract's true cost. Originality/value This paper provides empirical evidence that EACCR behaves more like EACCPI with respect to modern contracts, suggesting that today’s contracts have relatively high SPI. Therefore, caution is warranted for program managers when estimating the CAC from contract initiation up to and slightly beyond the mid-point of completion.


Author(s):  
ibraheem Aidan ◽  
Firas Jaber ◽  
Duaa Al-Jeznawi ◽  
Faiq Al-Zwainy

The importance of this study may be defined by using the smart techniques to earned value indicators of residential buildings projects in Republic of Iraq, only one development intelligent forecasting model was presented to predict Schedule Performance Index (SPI), Cost Performance Index (CPI), and To Complete Cost Performance Indicator (TCPI) are defined as the dependent. The approach is principally influenced by the determining numerous factors which effect on the earned value management, that involves Iraqi historical data. In addition, six independent variables (F1: BAC, Budget at Completion., F2: AC, Actual Cost., F3, A%, Actual Percentage., F4: EV, Earned Value. F5: P%, Planning Percentage., and F6: PV, Planning Value) were arbitrarily designated and satisfactorily described for per construction project. It was found that ANN has the capability to envisage the dust storm with a great accuracy. The correlation coefficient (R) has been 90.00%, and typical accuracy percentage has been 89.00%.


Author(s):  
Mega Waty ◽  
Hendrik Sulistio

A Change Order is a written and legal work order that changes the scope of the original contract, with compensation that has been agreed upon by the owner and the contractor. Changes can be in the form of adding or reducing the scope of work, changing materials, or changing schedules. Change Order causes the cost of contract items to swell, planning errors and negligence as well as changes in scope that can be reduced by sharpening planning results. The scope of research on road construction in Indonesia, especially in DKI Jakarta and Banten provinces. This study aims to determine the identification of change orders in road construction projects. Data obtained from real data on road construction projects from 2013-2018 on 16 road construction project packages in the form of road construction project addendum contracts. Based on the addendum contract, added work, less work, addition of new items and removal of work items are determined. The identification of change order risk is seen from three aspects, namely the addition and reduction of work items, the removal of items and the addition of new items and the wishes of the owner, thereby increasing the cost of the change order contract. This study found 732 changes in construction work items. Risk identification is obtained from the frequency of changes above 35% which is an intermediate frequency that tends to increase the occurrence of change orders. The results of risk identification were obtained for 31 construction work items, the highest percentage was for Thermoplastic Road Marking work, followed by 30 other construction work items. Keywords: risk identification; change orders; road construction projects  AbstrakChange Order adalah perintah kerja tertulis dan sah  yang mengubah lingkup kontrak semula, dengan kompensasi  yang sudah disetujui oleh pemilik dan  kontraktor.  Perubahan dapat berupa penambahan atau pengurangan lingkup pekerjaan, perubahan material, atau perubahan jadwal. Change Order menyebabkan biaya  item kontrak membengkak, kesalahan perencanaan dan kelalaian serta perubahan ruang lingkup yang dapat dikurangi dengan mempertajam hasil perencanaan.. Lingkup penelitian pada konstruksi jalan di Indonesia khususnya  provinsi DKI Jakarta dan Banten. Penelitian  bertujuan untuk  mengetahui  identifikasi change order proyek konstruksi jalan. Data didapat dari data riil proyek konstruksi jalan dari tahun 2013- 2018 pada 16 paket proyek konstruksi jalan berupa kontrak addendum proyek konstruksi jalan. Berdasarkan kontrak addendum maka ditentukan pekerjaan tambah, pekerjaan kurang, penambahan item baru dan penghilangan item pekerjaan. Identifikasi risiko change order dilihat dari tiga aspek yakni penambahan dan pengurangan item pekerjaan, penghilangan item dan penambahan item baru dan keinginan dari pihak owner sehingga meningkatkan biaya kontrak change order.  Penelitian ini mendapatkan 732 perubahan  item pekerjaan konstruksi.  Identifikasi risiko didapat dari  frekuensi perubahan diatas 35% yang merupakan frekuensi menengah yang cenderung meningkatkan terjadinya change order. Hasil identifikasi risiko didapat pada  31 item pekerjaan konstruksi, yang tertinggi persentase pada pekerjaan  Marka Jalan Termoplastik, diikuti 30 item pekerjaan konstruksi lainnya.


2015 ◽  
Vol 6 (1) ◽  
pp. 36-42
Author(s):  
Adhi Kusnadi

The success of a project is determined by the success of a software team in estimating the budget plan the cost of the software. The purpose of this paper is the creation, devise ways to estimate project budget software. To be able to compose a Planned Value (PV) project software required several steps. The first step is the preparation of WBS. Division of phase-phase creation of software applications in this paper follow the steps in the development of the software spiral. The second step is a software metric, method is the most straightforward and easiest in its application is a measurement based on metric size oriented. Intentionally taken a sample project that contains the work of hardware, so that can be made analysis unit price for the item that has a high price and need analysis. A summary of which can be taken from this discussion is the preparation method of estimating budget projects have successfully made systematically. How is made as simple as possible so that the team members have no experience whatsoever can make a budget. Keywords: Planned Value (PV) method, spiral, WBS, budget.


Complexity ◽  
2019 ◽  
Vol 2019 ◽  
pp. 1-11 ◽  
Author(s):  
P. Urgilés ◽  
J. Claver ◽  
M. A. Sebastián

All projects take place within a context of uncertainty. That is especially noticeable in complex hydroelectric power generation projects, which are affected by factors such as the large number of multidisciplinary tasks to be performed in parallel, long execution times, or the risks inherent in various fields like geology, hydrology, and structural, electrical, and mechanical engineering, among others. Such factors often lead to cost overruns and delays in projects of this type. This paper analyzes the efficiency of the Earned Value Management technique and its Earned Schedule extension, as means of forecasting costs and deadlines when applied to complex hydroelectric power production projects. It is worth noting that this analysis was based on simulation models applied to real-life projects. The results showed that cost forecasting becomes very accurate over time, whereas duration forecasting is not reliably accurate.


2014 ◽  
Vol 919-921 ◽  
pp. 1437-1440 ◽  
Author(s):  
Jian Wen Huang ◽  
Hui Min Pan ◽  
Yan Li ◽  
Yi Ting Zhu ◽  
Zai Yi Liao

Earned value management (EVM) is one of the most widely used control tools in project management. It is a well-known management system that integrates cost, schedule and performance. Based on the traditional concept of EVM, the cost/schedule monitoring and forecasting model is proposed in this paper. It gives us the analysis steps and provides the methods for monitoring the actual situation and forecasting the final cost and duration. By using this model, the managers are able to know timely the status of a project in terms of budget and schedule and forecast the developing trend and ultimate outcome of the project. So it is a reliable method to improve the capability of project managers for making reasonable decisions.


Forecasting construction project duration for future with accurate efficiency by considering all the delay factors is a big deal. Various examinations have been done to evaluate the reasons for duration delays in a construction site. Most common similarity between many factors are flawed design, inadequate supervision in workplace, shortage of supplies, absence of teamwork and local climatic conditions, causes a myriad of issues. Here, for forecasting, we chose the construction of ROB project at Kurnool, Andhra Pradesh. Though many techniques have been implemented to solve out this problem, predicting completion of an ongoing project is a big deal. Various tools have been used such as earned value management, exponential smoothing technique. After applying these techniques, a comparison with a minimal percentage of error is made and the best tool for prediction is selected. This investigation prescribes Smoothing techniques, the results become better when compared with different procedures.


Sign in / Sign up

Export Citation Format

Share Document