DELAY IN CONSTRUCTION INDUSTRY: CAUSES, EFFECTS AND MITIGATION MEASURES

Author(s):  
Yiannis Vacanas ◽  
Chris Danezis

The main objectives of this paper are to determine the main causes of delays that occur in construction projects in Cyprus and their effects, and suggest measures that can assist in their effective control and reduction. Seeing that no relevant work has been undertaken for the case of Cyprus, a detailed literature review was carried out to identify the most significant causes of delay at the international level. Based on the review, a survey questionnaire was distributed to members of the construction industry of Cyprus. The analysis of the results indicated variations requested by the client, mistakes and missing information from consultants’ drawings, and low productivity and inadequate programming of works from the contractor’s side to be the main causes of delay. By considering the delay causes analysis specific mitigation measures are proposed that are mainly related to the programming of the works, work progress and productivity monitoring, and the appointment process of the parties involved in a construction project.

Author(s):  
Samiullah Sohu ◽  
Abdul Fattah Chandio ◽  
Kaleem ullah

The problem of delay in construction industry is a regular phenomenon worldwide, and construction industry of Pakistan has no exception, particularly in highways projects. Delay can be described as the extension of time to complete the construction project. The aim of this paper is to identify main causes of delays in highway projects of Pakistan, and to determine mitigating measures for the identified causes. The research method of this study is based on literature review, questionnaire survey and semi structured interview. From in-depth literature review, twenty-six common causes of delay were found. A questionnaire survey was carried out among construction professionals of highway projects. The causes of delay in highways projects were ranked referring to their Mean values. A semi structured interview was carried out to determine mitigation measures for the top ten causes of delays. The data gathered from questionnaire survey was analyzed using SPSS (Statistical Package for the Social Sciences) while, data collected through semi structured interviews was analyzed using Nvivo software. The findings of this study are expected to be useful for construction parties, to mitigate the delays in highway construction projects of Pakistan.


2021 ◽  
Vol 9 (3) ◽  
pp. 52-57
Author(s):  
Yasir Mohamed Hassan Amin ◽  
Mohamed Abdulla Nugdalla Ahmedi

Quality management is considered one of the most important obstacles facing the construction industry in Sudan. The application of a quality assessment system contributes to the development of quality in projects as it is possible to measure the quality in projects. This paper aims to introduce one of the quality assessment systems, which is the system followed and applied in the Singapore (CONQUAS). This system assesses quality based on structural, architectural, mechanical and electrical work. The paper also aims to study the factors affecting the application of the quality assessment system in Sudan. The study is carried out in the region of Khartoum. The study is focusing on the construction projects. The study is carried out by questionnaires and other literature review. The respondents are consultants and contractors. The data has been distributed and analyzed by using the Average Index. From the study it was found that CONQUAS standard is assessed the building based on workmanship standards by the assessors from the BCA on site using standard score sheets. The assessment is done throughout the construction process for structural, mechanical and electrical works, and from questionnaire results the main factors affect construction industry in Sudan is lack of standardization in Sudan. The author recommended that more study shall be conducted to identify factors affecting quality in Sudanese construction industry and how to improve the quality.  


2018 ◽  
Vol 25 (4) ◽  
pp. 497-533 ◽  
Author(s):  
Parvaneh Shahsavand ◽  
Akbar Marefat ◽  
Majid Parchamijalal

Purpose The purpose of this paper is to reveal the main causes of delays in the projects are from the client (relative importance index (RII)=0.716), labor and equipment (RII=0.701) and contractor (RII=0.698). Hence determining the contractual responsibility of delay is the most likely source of dispute in construction projects and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule. Therefore, authors try to investigate all process-based techniques of delay claims and evaluated and conformed them with principles by Society of Construction Law (SCL) protocol and Association for the Advancement of Cost Engineering International (AACEI) in order to choose the best techniques based on the specific circumstances of each project. Design/methodology/approach This section is divided into two distinct parts: refers to the methods used to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in construction industry; and refers to advantages and disadvantages of various techniques used to analyze delays and their conform with SCL protocol. A questionnaire was developed to assess the perceptions of clients, consultants, and contractors on the relative importance of causes of delay in Iranian construction industry. The respondents were asked to indicate their response category on 78 well-recognized construction delay factors identified by authors. Findings In total, 78 causes of delay were identified through research. The identified causes are combined into seven groups. The field survey included 58 contractors, 55 consultants, and 62 client. Data collected were analyzed by RII and Statistical Package for Social Sciences (SPSS). The authors identified main causes of delay and ten most important causes, according to Table AII, from the perspective of three major groups of participants (clients, consultants and contractors). The ranking of categories of causes of delay, according to Table I, were: client-related causes (RII=0.716); labor and equipment category causes (RII=0.701); contractor-related causes (RII=0.698); material-related causes (RII=0.690); design-related causes (RII=0.666); external causes (RII=0.662); and consultant-related causes (RII=0.662). But according to the discussions and given that determining the contractual responsibility of delay is the most likely source of dispute in construction industry and many techniques have been used in the courts to demonstrate the criticalities of a delay event on the project schedule. Originality/value All process-based techniques of delay analysis have been present in this paper and categorized in 11 groups. In order to understand the advantages and disadvantages of them by clients, contractor and consultant, a thorough review conducted to reveal the nature of techniques. In the next step, given that selecting the most appropriate technique based on constraints and specific conditions of each project is one of the most important steps to carry out a successful delay analysis. The authors conformed, all process-based techniques of delay analysis, by SCL protocol and AACEI principles. Finally, the result of this match was brought in order to choose the best technique based on the specific circumstances of each project.


Author(s):  
Ramin Asadi ◽  
Suzanne Wilkinson ◽  
James Olabode Bamidele Rotimi

Rework occurs across the life cycle of projects and has significant impacts on construction project performance. A rational approach to managing rework is by identifying the main sources of rework; then mitigation measures can be implemented to enhance performance on projects. Rework has been widely studied within the construction industry, but the link between rework and contract conditions remain unexplored. This study identifies and classifies the root causes of rework at the construction stage of projects. It then examines the relationship between the conditions of contracts with the identified root causes. A comprehensive list of rework root causes was determined through the review of literature, which was categorized into five classified factors. The classified factors include process, human resource, material/equipment, technical, and other related environmental and financial factors. The next step comprises a questionnaire survey designed to determine relationships between rework and contracts. The result of the study is presented descriptively for ease of understanding. The results show that rework could be managed more efficiently through contracting processes, which ultimately benefits construction projects’ performance.


Construction is one of the most important employment sectors in India with very minimal research being done to identify the delay factors and causes that affect the construction Industry. The opinions of the construction professional required for the research was obtained by conduction interviews. A set of questions were circulated between the professionals working on the site to acquire the causes and effects of delays faced by them. To resolve the issues various studies and researches have been done by various researchers. The data analyzed in the research was done by using Relative Important Index (RII) which helpsto categories and rank the causes of delays according to the importance of the causes with respect to its contribution towards time delays, arbitration, litigation, cost overrun and total abandonment. Spearmen’s rank correlation coefficient was used compare the effect of delays between contractors, owners and consultants. In this paper, the research is aimed towards finding the effects of various causes on the various parties on construction sites of coastal parts of Mumbai and methods of minimization of the same.


2020 ◽  
Vol 25 (2) ◽  
pp. 165-181 ◽  
Author(s):  
Amílcar Arantes ◽  
Luís Miguel D.F. Ferreira

Purpose The purpose of this study is to contribute to the theory and practice of project management in the construction industry by identifying the primary causes and extracting the underlying causes of construction delays and providing recommendations on delay mitigation measures. Design/methodology/approach AA survey was used to identify the importance of 47 causes of delays. The relative importance index was used to rank them, factor analysis was applied to extract the underlying causes and focus group interviews were used for discussion and development of mitigation measures. Findings Six of the ten most important causes are in the top ten universal delays in construction projects. Factor analysis revealed six underlying causes: improper planning, poor consultant performance, inefficient site management, owner influence, bureaucracy and sub-standard contracts. Practical implications The owner/sponsor/client must have adequate engineering and project management skills to be able to evaluate proposals and contractors more accurately, economically and technically. The bidding and contract award process should focus on the most economically advantageous proposal and contracts should provide for mechanisms for managing risks while executing projects. Contractors should select reliable, high-quality subcontractors and suppliers and should have competent site managers. Originality/value This work expands and improves the understanding of the causes of delays in construction projects by providing an empirical study of the causes of delays and respective mitigation measures in Portugal.


Energies ◽  
2019 ◽  
Vol 13 (1) ◽  
pp. 17
Author(s):  
Goutom K. Pall ◽  
Adrian J. Bridge ◽  
Jason Gray ◽  
Martin Skitmore

Power transmission (PT) projects are vital for the power sector. However, worldwide PT projects experience delay. There is an urgent need to understand the unique causes of delays in PT projects. This paper presents the first empirical study on causes of delays in PT projects via a comprehensive literature review. Based on this literature review, 63 potential delay factors are identified and divided into ten major groups. These include two new groups of delay attributes, comprising sector-specific factors (SSF) and general factors (GF), where SSF pertains solely to PT projects and GF contributes to minimizing the bias of project participants. A questionnaire survey of 311 PT stakeholders is conducted to determine the overall ranking of the delay factors using the relative importance index. The results indicate that SSF, GF, and external/unavoidable factors are the most critical groups of delay factors, with the top-ranked factors being right of way problems of transmission line (TL), frequent changes in TL routes, and accessibility to the TL tower locations. Finally, recommendations are made to help minimize time overruns in PT projects, as well as in other linear power and non-power construction projects in general.


2013 ◽  
Vol 838-841 ◽  
pp. 3102-3108
Author(s):  
Boon Hoe Goh ◽  
Byung Gyoo Kang ◽  
Chung Lian Liew ◽  
Wee Kang Choong ◽  
Tuck Wai Yeong

Risk management is one of the most important areas in project management particularly in the construction industry. However it is not possible to analyze all of the potential risks as it will require too much time and effort. Therefore in order to identify and analyze the significant risks, the risks should be categorized and ranked. This research applied the concept of risk significance index score to construction projects in Malaysia. A comprehensive list of 40-potential risks has been developed through literature review and an interview survey. A questionnaire survey was conducted to produce project risk significance index score for the risks. The ranks of the risks have been identified and solutions for the significant risks have been produced through interviews. This research proves the practical use of risk significance index score for construction projects in Malaysia.


Author(s):  
Raza Ali Khan ◽  
Muhammad Umer

It is widely believed that construction sector helps developing aggregate economy and reducing unemployment. Currently, Pakistan is experiencing a major transformational phase in the back drop of China-Pakistan Economic Corridor (CPEC). CPEC is valued at US$ 62 Billion. The present study is undertaken to ascertain the impact of time overrun of projects on their cost, the correlation between stakeholders and to predict the effect of delays on cost overruns. Causes of delays are identified by stakeholders of the construction industry of Pakistan. Two models for projects that had delay less and greater than 100 days are developed. Structured questionnaires and personal interviews are carried out to extract primary data for the study. Relative Importance Index (RII) was utilized for ranking of delay causes, and Pearson’s correlation to formulate correlation between causes of delays and cost of construction projects from the perspective of client, contractors and consultants. For predicting the impact of delays on cost of projects Linear Regression technique has been used. The results reveal that the causes of delay related to design, procurement and on-site has significant impact on delays. Pearson’s result indicates strong covenant between client and contractor. Whereas, there is a weak degree of association between consultant and contractor. Results from linear regression concluded that there is a significant effect of delay on cost of the project.


2019 ◽  
Vol 9 (2) ◽  
pp. 3945-3948 ◽  
Author(s):  
M. H. Momade ◽  
M. R. Hainin

Motivation is one of the factors that influence productivity. Project management plays a vital role in the success of projects in Qatar construction industry (QCI). It relies profoundly on the team’s active participation and effective performance. Hence it is important to assess the impact of motivation and demotivation on performance. The main objective of this paper is to identify the key factors that cause motivation and de-motivation in QCI. Literature review, surveys with experts and semi-structured interviews were conducted to identify these factors. Using these factors to conduct specific motivational programs will help improve productivity in QCI. Research on motivational factors impacting productivity has not been conducted in Qatar before, so this work will provide insight on how to deal with productivity issues that QCI faces ahead of a major world event that Qatar will host in 2022.