Urban development often requires the construction of deep excavations. There are some difficulties during design and construction of foundation excavation, such as large engineering quantity, poor geological conditions, as well as challenges to design and construction of retaining and protecting structure. To solve these difficulties, supporting system of steel circle beam, steel pipe support and stiffened support compounding with steel pipe pile cofferdam is designed. Soil resistance calculating method is used for support structure design in all possible conditions and the result is compared with that using the classical method. With reasonable supporting process and construction measures, monitoring results including displacement of steel pipe piles and greatest axial force can meet the norm requirements. It is proved that the retaining and protecting system designed is safe and reliable. With the benefit of small deformation and high integrity, locking steel pipe piles gave full play to its locking function of water. The design method in the paper is feasible and may offer some references for similar deep foundation excavation.

2012 ◽  
Vol 226-228 ◽  
pp. 1531-1534
Author(s):  
Zhen Hong Wu ◽  
Yong Xun ◽  
Ya Nan Gan ◽  
Chun Hua Wang ◽  
Ying Li ◽  
...  

South tower of Taizhou bridge is located in complex hydrogeological conditions,the amount of its excavation engineering is large.Combined with the successful application of locking steel pipe pile cofferdam in the south tower project of Taizhou Yangtze Highway Bridge,from comparison and demonstration, scheme design and construction, process monitoring to introduce locking steel pipe pile cofferdam in detail,using the classical method and the M method to design and calculation for supporting structure.Construction practice shows that the design and calculation of support structure is accurate,locking steel pipe pile fully played its function of sealing,it also has great rigidity, good integrity strong bending resistance and other advantages.The successfully application of this technology,promoting the technological progress of bridge foundation constructionthe in deep water or complex geological conditions,it provides a basis for the construction of similar projects in the future.


CERUCUK ◽  
2019 ◽  
Vol 2 (1) ◽  
Author(s):  
Humaira Afrila ◽  
Markawie Markawie

Long Kali is a sub-district of Paser Tana Paser Regency Prov. East Kalimantan. In this sub-district have two village separate by a river, that is Perkuwen river, there is bridge has a broke. Whereas the village very needed a bridge because it is used as a transportation infrastructure for peoples and also passed by vehicles transporting oil palm yields . Therefore, the design of composite bridges made with spans 25 m and 7 m wide bridge.In this plan the analysis of Standard methods of loading refers to the bridge imposition For RSNI T-02-2005 about composite bridge structure design method, refers to RSNI T-03-2005 about Steel Structural Design For Bridge, SNI 03-1729-2002 about Steel Structures Planning Procedures and SNI 03-2847-2002 about Concrete Structures Calculation for Building.The result is used the main girder profile SH 950 x 400 x 16 x 32 and diaphragm WF 400 x 200 x 8 x 13. Vehicle floor plate thickness 20 cm using quality concrete  30 MPa and quality reinforcing steel reinforcement  360 MPa with subject dividers reinforcement D22- 100 and D12-100 mm. In using concrete pavement  30 MPa D22-100 mm staple reinforcement and shear reinforcement rebars quality D12-100 mm  360 MPa. Concrete abutment in the form  25 MPa at 2 m height and length of 8,5 m. Steel pipe pile foundations quality  25 MPa are 16 pieces with a length of 10 meters and a diameter of 0.4 m.Keyword: Bridge, composite, steel pipe pile.


2012 ◽  
Vol 446-449 ◽  
pp. 1400-1403
Author(s):  
Qi Hu ◽  
Sheng Ming Luo ◽  
Zhu Jin Jiang

By comprehensive consideration of soil conditions, geometric shape of deep foundation pit and many other kinds of factors, enclosure structure design needs to select optimal supporting and enclosure system with safety, economy and construction feasibility. On case study of enclosure structure selection about typical soft soil foundation, this paper researches effects of force- deformation of enclosure structure by brace layout, and of economy and construction feasibility. The research results may offer reference for similar projects.


2011 ◽  
Vol 255-260 ◽  
pp. 747-751
Author(s):  
Jin Sheng Liu ◽  
Shi Mei Liu

As a new type of resist lateral force structure, short-pier shear wall structure has been widely used in high-rise and super-tall residential construction. However, at present, there isn’t a specifically targeted short-leg walls structure design and construction technical regulations both at home and abroad, which led to the architectural engineering design and construction market turmoil. By the prophase research of the short-leg walls structure seismic performance, and a great deal of experiments, combine with the latest research results at home and abroad, adopt the limit state design method based on probability theory, the paper clarifies the definition of short-leg walls, and analyzes the calculation method of section load-carrying capacity for earthquake combination and no-earthquake combination, which has certain directive significance and engineering application for the design and construction of high-rise residential buildings.


2017 ◽  
Vol 23 (4) ◽  
pp. 524-532 ◽  
Author(s):  
Alireza VALIPOUR ◽  
Nordin YAHAYA ◽  
Norhazilan MD NOOR ◽  
Jurgita ANTUCHEVIČIENĖ ◽  
Jolanta TAMOŠAITIENĖ

Existing risks in deep foundation excavation projects is a major issue in developing cities. With the rapid in-crease in the number of various deep foundation and excavation projects in big cities of Iran, many accidents related to deep excavation have been reported every year. These accidents affected delay and increased cost of project implemen-tation. Therefore identification and assessment of risks of these accidents is essential. The aim of the research was to develop a framework to overcome limitations of previous approaches to assess of risks in excavation projects. According to the complexity of a problem and the inherent uncertainty, the framework adopted SWARA (Step-wise Weight As-sessment Ratio Analysis) and COPRAS (COmplex PRoportional ASsessment) methods through introducing new criteria for risk assessment. Data was collected through interview, a literature review and a questionnaire survey distributed to excavation project experts. A case study of deep foundation excavation in Shiraz was presented. The results have shown that the risks involving construction safety, unfavourable geological conditions, shortage of managerial experience, in-complete emergency plan and subsidence of ground are the most significant risks excavation projects in Shiraz. The proposed framework and the obtained results can help stakeholders of excavation projects in developing countries better to manage project risks.


Water ◽  
2021 ◽  
Vol 13 (9) ◽  
pp. 1303
Author(s):  
Chenghua Shi ◽  
Xiaohe Sun ◽  
Shengli Liu ◽  
Chengyong Cao ◽  
Linghui Liu ◽  
...  

At present, jet-grouted horizontal waterproof curtain reinforcement has become an essential method for deep foundation pit groundwater control. However, there is still a lack of an effective theoretical calculation method for horizontal waterproof curtain reinforcement, and there is little research on the seepage laws of foundation pits under different horizontal waterproof curtain conditions. Based on Darcy’s seepage theory, theoretical analysis models of deep foundation pit seepage were established considering the effect of a horizontal curtain in a highly permeable formation. Through the established models, the calculation method of the water inflow and the water pressure under the condition of a horizontal curtain was derived. Then through indoor tests, the reliability of the theoretical calculation method was verified. Furthermore, the established theoretical calculation method is used to analyze the influence of various factors on the water inflow and the water pressure, such as the ratio of hydraulic conductivity of the horizontal curtain to surrounding soil, thickness, and reinforcement position of the horizontal curtain. It is found that the hydraulic conductivity ratio has the most significant influence on the seepage characteristics of the foundation pit. Finally, the design method was applied to an example of the horizontal waterproof curtain of the foundation pit, which is located at Juyuanzhou Station in Fuzhou (China). The water inflow per unit area is 0.36 m3/d in the foundation pit, and this implies that the design method of the horizontal waterproof curtain applied for the excavation case is good and meets the requirements of design and safety.


2021 ◽  
Vol 34 (1) ◽  
Author(s):  
Yingfeng Zhao ◽  
Jianhua Liu ◽  
Jiangtao Ma ◽  
Linlin Wu

AbstractCurrent studies on cable harness layouts have mainly focused on cable harness route planning. However, the topological structure of a cable harness is also extremely complex, and the branch structure of the cable harness can affect the route of the cable harness layout. The topological structure design of the cable harness is a key to such a layout. In this paper, a novel multi-branch cable harness layout design method is presented, which unites the probabilistic roadmap method (PRM) and the genetic algorithm. First, the engineering constraints of the cable harness layout are presented. An obstacle-based PRM used to construct non-interference and near to the surface roadmap is then described. In addition, a new genetic algorithm is proposed, and the algorithm structure of which is redesigned. In addition, the operation probability formula related to fitness is proposed to promote the efficiency of the branch structure design of the cable harness. A prototype system of a cable harness layout design was developed based on the method described in this study, and the method is applied to two scenarios to verify that a quality cable harness layout can be efficiently obtained using the proposed method. In summary, the cable harness layout design method described in this study can be used to quickly design a reasonable topological structure of a cable harness and to search for the corresponding routes of such a harness.


2013 ◽  
Vol 368-370 ◽  
pp. 1043-1047
Author(s):  
Yin Zhang ◽  
You Han ◽  
Shuai Liang

Ecological composite wall as ecological composite wall structure of the main stress components, the seismic performance is ecological composite wall structure seismic performance evaluation system of the main content. Based on the grey system theory, the grey correlation analysis to the key parameters (the mouth of the cave, frame structure, height to width ratio) change ecological composite wall test results are analyzed, the key parameters on the ecological composite wall the influence law of seismic performance, for choosing wall structure design method to provide basis.


2014 ◽  
Vol 711 ◽  
pp. 529-534
Author(s):  
Zi Sheng Yang ◽  
Jun Xia Liu ◽  
Yi Ren Wang

For the past few years, great development has been achieved in deep foundation excavation. However, due to foundation excavation’s locality, individual diversity, complexity and uncertainty, the probability of accidents in foundation pit engineering tends to be greater than that in main works, and the accident rate may even reach about 20%, which makes the study on factors leading to foundation excavation accidents quite necessary and meaningful. By use of Analytic Hierarchy Process (AHP), this paper has figured out the ratio (weight) of the investigation, design, construction and other factors leading to foundation excavation accidents to the whole factor set, which is of great guiding significance to the study on prevention and treatment of foundation excavation accidents in future.


2014 ◽  
Vol 599-601 ◽  
pp. 358-361
Author(s):  
Huan Qiang ◽  
Hu Zhang ◽  
Yan Zhou

A design method of modular joint is proposed according to the complicated structure, line exposed and heavier characteristics of multi-DOF (degree of freedom) mechanical arm. In this paper, the design of modular joint was carried on and a model of six-DOF mechanical arm was built through the research on the structure of mechanical arm. On this basis, dynamics simulation will be carried. The results show that the modular design method simplified the structure of the mechanical arm, the dynamics simulation proved it was feasible for the structure design and drive selection.