Effects of pile extraction and refilling with cement slurry on ground settlements

2013 ◽  
Vol 50 (3) ◽  
pp. 343-349 ◽  
Author(s):  
Y.D. Wu ◽  
J. Liu ◽  
Charles W.W. Ng

Secant pile walls reinforced with steel I-beams are widely used worldwide. Although ground surface settlement caused by the installation of secant pile walls has been investigated, there is minimal data available on ground surface settlement due to extraction of steel I-beams from secant pile walls. This note aims to investigate the effectiveness of cement slurry refilling on reducing ground settlements during extraction of steel I-beams. Measured ground surface settlements during the extraction of steel I-beams from secant pile walls with and without cement slurry refilling are reported, discussed, and explained. Two different influence zones due to steel I-beam extraction can be identified. Ground settlement due to steel I-beam extraction can be minimized with the refilling of cement slurry. By using such a refilling technique, measured maximum surface settlement was reduced by 70%. The average measured settlement rate was reduced by 61%.

2010 ◽  
Vol 168-170 ◽  
pp. 357-364
Author(s):  
Ji Feng Liu ◽  
Bo Liu ◽  
Hui Zhi Zhang

to evaluate the influence of soil-water coupled and shield tunnel construction induced around soil disturbance damage on ground surface settlement, the process of shield tunnel construction induced around soil disturbance is analyzed, the FLAC3D numerical simulation are carried out, and a newly-modified tunnelling-induced ground settlement calculation method based on disturbance degree of around soil and soil-water coupled is presented, and these methods are applied in case of Beijing Metro 10thLine. It is indicated that considering the influence of the shield tunnelling-induced around soil disturbance damage, and soil-water coupled induced soil properties weakening and the excess pore water pressure dissipating induced soil consolidation to the ground surface settlement are necessary, the calculating result of the newly-modified surface settlement prediction method, and the result FLAC3D numerical simulation all agree well with in-site observed data of Beijing Metro 10th Line.


2021 ◽  
Author(s):  
Ali Kazempour Osalou ◽  
sayfoddin moosazadeh ◽  
Ali Nouri Qarahasanlou

Abstract Nowadays, tunnel excavation plays a major role in development of countries. Due to the complex and challenging ground conditions, a comprehensive study and analysis must be done before, during and also after the excavation of tunnels. Hence, the importance of study and evaluation of ground settlement are dramatically increased, since many tunnel projects are performed in the urban areas where there are plenty of constructions, buildings and facilities. For this reason, the control and prediction of ground settlement is one of the complicated topic in the fields of risk engineering. Therefore, in this paper, proportional hazard model (PHM) is used to analyze and study the ground settlement induced by Tabriz Metro Line 2 (TML2) tunneling. The PHM method is a semi-parametric regression method that can enter environmental conditions or factors affecting settlement probability. These influential factors are used as risk factors in the analysis. After establishing a database for a case study and using proportional hazard model for surface settlement analysis, and then, by evaluating the effect of environmental conditions on the ground surface settlement, it has been found that the risk factors of grouting pressure behind the segment, the ratio of tunnel depth to groundwater level, and drained cohesion strength at a significant level of 5% have a direct effect on the probability of settlement. The results also showed that the effect of grout injection pressure on ground subsidence is more than other parameters, and with increasing injection pressure, the probability of exceeding safe subsidence values decreases. In addition, it has been found that increasing the risk factor for the ratio of tunnel depth to groundwater level reduces the probability of exceeding the safe ground settlement. Finally, increasing the number of risk factors for drained cohesion strength increases the probability of exceeding safe settlement.


2018 ◽  
Vol 2018 ◽  
pp. 1-14 ◽  
Author(s):  
Dapeng Li ◽  
Changhong Yan

Building deformations are not only closely related to the distance from the building to metro-station excavation but also related to the relative positions of the building and metro-station excavation. Building deformations can be predicted using ground surface settlement profiles. Based on typical geological parameters of Nanjing metro-station excavation, ground surface settlements were numerically simulated by auxiliary planes perpendicular and parallel to the excavation and by angled auxiliary planes at the excavation corner. Results show that the ground surface settlement profiles in auxiliary planes are closely related to the relative positions of the auxiliary planes and the metro-station excavation. Partitioning of ground surface settlements was proposed according to the three types of ground surface settlement profiles; furthermore, bending deformation and torsional deformation regularities of surrounding buildings were analyzed, and an estimation method for building settlements was developed. Finally, field-monitored settlement data of 21 buildings in different zones were compared with the estimated settlement data, and the application of the settlement estimation method to different types of foundations was analyzed. The results of this study can serve as reference for metro-station deep excavation construction and protection of surrounding buildings.


2011 ◽  
Vol 117-119 ◽  
pp. 721-725 ◽  
Author(s):  
Cheng Ping Zhang ◽  
Li Min Li ◽  
He Li ◽  
Jian Chen Wang

Ground settlement, especially the ground surface settlement induced by subway tunneling is an important issue. However, there is no an agreed standard for controlling ground surface settlement during the subway construction at present. The control standard of ground surface settlement was studied using the methods of statistical analysis and numerical simulation based on the running tunnel in Beijing subway. According to the research results, a conclusion could be obtained that the ground surface settlement can be controlled within 40 mm using the general construction measures in Beijing subway running tunnel construction, and furthermore, the settlement of 40mm will not damage the existing nearby structures and utilities including neighboring buildings, bridges and pipelines, etc. So the control valve of 40 mm is rational, which can be adopted as the control standard of ground surface settlement induced by running tunnel construction in Beijing subway.


2020 ◽  
Vol 10 (14) ◽  
pp. 5002
Author(s):  
Zhongzheng Wang ◽  
Dalong Jin ◽  
Chenghua Shi

This study aims to investigate the effect of the spatial variability of grouting-layer thickness on ground-surface settlement caused by shield tunneling and to provide a rational prediction method. The spatial characteristics of grouting layers were obtained based on statistical analysis. The random finite element method was used to study the effect of spatial variability of different parameters on ground-surface settlement. Simulation results indicate that the spatial variability of the grouting layer has a negative impact on ground settlement. The surface settlement will be underestimated without considering the spatial characteristics of the grouting layer. Thus, a reliable prediction approach of the maximum ground settlement was proposed to control the construction quality.


2013 ◽  
Vol 671-674 ◽  
pp. 1081-1086 ◽  
Author(s):  
Fei Fei Wang ◽  
Hui Ren Bai ◽  
Jing Jing Li

In order to study the Dalian Metro section 202(Cujin Road station-Chunguang Street station, which is shallowly buried and covered with plain fill)’s ground surface settlement, the monitoring measuring station was built during the construction. After 3 months’ measuring by precision level,the data shows that the maximum point is in the center line of the tunnel of the upper part. The settlement is about 25.66-31.82mm. This paper put forward the concept of the distance span ratio β, β effective value range was - 4 <β< 4,Surface subsidence is closely related with β, Severe surface subsidence stage is -2 <β< 2, Occupy whole deformation is 67.5-77.6%,settlement rate about 0.84-0.93mm/d, so should strengthen the monitoring frequency, Suggest increases site tour. Field test results and the ground surface settlement calculation model winkle are identical with each other; the monitoring results have important guiding significance and reference for Dalian subway and the similar shallow depth excavation tunnel construction.


Symmetry ◽  
2021 ◽  
Vol 13 (11) ◽  
pp. 2117
Author(s):  
Keke Li ◽  
Wenyuan Xu ◽  
Liang Yang

The deformation characteristics of a raised and widened old Chinese roadway on a soft soil foundation are investigated in this study via finite element numerical simulation. The rules of ground surface settlement, slope foot lateral displacement, and ground surface settlement evolution of the roadbed under three modes (one-time construction of an eight-lane expressway, widened four-lane expressway, and raised/widened four-lane expressway) are compared. The ground surface settlement process of the eight-lane road foundation, which is formed by first widening and then raising the road, is highly complex. The ground surface settlement curve under the old road foundation increases and then decreases. The lateral displacement of the slope foot also interacts with the widening and raising of the eight-lane roadbed foundation. The range of lateral displacement is 70.05, 42.58, 124.81, 104.54 mm. Fifteen years after construction, the total settlement of the raised and widened roadbed is much larger than that of the one built directly. The total settlement values at the center of the two roadbeds are 297.05 and 234.85 mm, respectively. This manuscript provides data support for the reconstruction and expansion of roads on soft soil foundations, for choosing appropriate construction methods to build roads, and for avoiding major road damage, which is of great significance to the construction of road infrastructure in the future.


2019 ◽  
Vol 9 (7) ◽  
pp. 1399 ◽  
Author(s):  
Wen Zhao ◽  
Peng-jiao Jia ◽  
Lin Zhu ◽  
Cheng Cheng ◽  
Jianyong Han ◽  
...  

Double-O-tube shield tunneling has attracted increasing attention because it offers cost-efficiency in underground construction. Prediction of ground surface settlement and the variety of additional stresses induced by shield construction is crucial to underground construction in metropolises since excessive settlement could trigger potential damage to the surrounding environment. The additional stresses induced by the propulsion of double-O-tube shields are calculated by means of the Mindlin’s equations of elasticity. The characteristics of additional stresses are analyzed with compound Gauss-Legendre integral arithmetic, and the frontal additional thrust, the lateral friction, and the ground loss are taken into account. Subsequently, based on field measurements, the maximum settlement coefficient and width of the settlement trough coefficient of the typical Peck formula are modified. The predictive curve of the Peck formula is closer to the engineering measured data than that of the typical formula. The cut-off functions of ground surface settlement caused by double-O-tube tunnel shield construction are proposed and can predict the shape of ground surface settlement, such as single peak or double peak. The correctness of the proposed functions is verified based on an engineering project.


1998 ◽  
Vol 35 (1) ◽  
pp. 159-168 ◽  
Author(s):  
Chang-Yu Ou ◽  
Richard N Hwang ◽  
Wei-Jung Lai

This paper presents the surface settlement performance induced by the foamed type of earth pressure balance shield in contract CH218 of the Hsintien Line of the Taipei Rapid Transit System. The surface settlement characteristics caused by the single tunnel and by twin tunnels with reference to two sections spaced at 87 m are studied. Field observations indicate that the surface settlement trough due to the single tunnel can be represented by the normal distribution. The distance of the inflection point to the tunnel center and maximum surface settlement value are consistent with those found in the literature. The characteristics of the surface settlement trough are related to the type of the soil, particularly where the crown of the tunnel is located in a layered soil deposit. The ground surface settlement induced by twin tunnels was found to be larger than estimated using the principle of superposition.Key words: shield tunnelling, surface settlement, field observation.