scholarly journals Effects of Water Inrush from Tunnel Excavation Face on the Deformation and Mechanical Performance of Shield Tunnel Segment Joints

2017 ◽  
Vol 2017 ◽  
pp. 1-18 ◽  
Author(s):  
Tingsheng Zhao ◽  
Wen Liu ◽  
Zhi Ye

Water inrush from the excavation face often occurs in the current shield construction of metro tunnels. In this study, the discontinuity of shield tunnel lining and the interaction between the tunnel segments, the grouting layer, and the surrounding rock are considered. Based on the 3D nonlinear contact theory, a hybrid model of the shield tunnel is constructed. Considering the fluid-solid coupling effect of water and soil, the influences of different water head differences on the mechanical performance and deformation of segments and joints in the shield tunnel are studied. The water gushing from the excavation face leads to vertical convergence of the cross-sectional area of the shield tunnel, and joint opening and dislocation result in sharp decrease of the waterproof capacity of joints. Meanwhile, the stress in the vicinity of segment joints increases sharply, and local cracks occur in the segment lining. The axial force, shear force, and bending moment in the joint bolt are also significantly increased. Based on the current metro standard and the computational results in this study, an emergency control criterion is put forward by means of controlling the discharge of water: the water head difference over the excavation face is required less than 4.6 M.

Symmetry ◽  
2020 ◽  
Vol 12 (8) ◽  
pp. 1246
Author(s):  
Zhongsheng Tan ◽  
Zonglin Li ◽  
Wei Tang ◽  
Xueying Chen ◽  
Junmeng Duan

With the intensive development of China’s high-speed railway network and intercity railway network, the construction of the large-diameter shield tunnels and cross-passages is gradually increasing. The construction of large diameter shield tunnels and the excavation of cross-passages puts forward higher requirements for the stability and safety of segment structure. Based on the Wangjing tunnel project, this paper studies the segment displacement and mechanical response of the shield tunnel with a diameter of 10.5 m in the process of shield construction and cross-passage construction. The results show that during the construction of large diameter shield tunnels, the vault and invert produce inward displacement, the invert uplift usually is more severe than the vault settlement, and the arch waist on both sides produces outward displacement. Near the segment K (capping block), the mechanical performance of the segment is close to that of the hinge or chain rod, which can only effectively transmit the axial force but cannot resist the bending moment and shear force. During construction of the cross-passage, the maximum deformation and stress of shield tunnel segment are symmetrically located at the interface of the main tunnel and cross-passage. The upper and lower edges of the segment at the interface tend to change from compression to tension. At the same time, the steel bars on the inside and outside of the segment vault and the arch waist change from compressive stress to tensile stress, which can easily lead to segment damage, so these positions can be reinforced by erecting section steel frames before construction.


2011 ◽  
Vol 368-373 ◽  
pp. 2533-2536
Author(s):  
Hua Yuan ◽  
Hai Tao Wan ◽  
Zhi Liang Zhao

A coupled numerical simulation of a river-crossing shield tunnel excavation in saturated soft clay with high groundwater has been performed using a three-dimensional finite difference model, which takes into account variation of soil permeability with stress, anisotropy of permeability, reduction effect of joints on segment bending stiffness and the hardening process of synchronized grouting material. Groundwater seepage conditions around the tunnel, bending moment, axial forces and strength safety factor of tunnel segment as well as deep soil displacement during tunnel diving are investigated numerically. The analyses provide valuable information concerning the mechanical behavior of tunnel segment and hydrological field in soil around tunnel during advancing. The result also is benefited to control groundwater for river-crossing tunnel in soft clay under high water table.


2019 ◽  
Vol 2019 ◽  
pp. 1-20
Author(s):  
Shusheng Lv ◽  
Wen Liu ◽  
Shihong Zhai ◽  
Peishuai Chen

The launching-arrival stage of the shield is the most dangerous construction stage in subway construction. During the conversion process of the soil and air medium in the shield machine, water inrush at the excavation surface often occurs because of the effect of groundwater. Previous research has focused on the overall stress and deformation of existing tunnels caused by water inrush from the excavation face of the shield machine excavation stage. However, the stress and deformation states of the segments and anchors at different assembly locations of the tunnel, as well as the interaction between the soil reinforcement region and the segments and anchors in the launching-arrival stage have not been considered in previous studies. In this study, the inrush model of the launching-arrival stage of the subway shield was established by utilizing the equivalent refinement modeling technology and ABAQUS simulation analysis with consideration of the fluid-solid coupling effect of water and soil to study the influences of different water head differences on the mechanical and deformation properties of segments and anchors in shield construction under the conditions of water inrush on the excavation surface. The results showed that the water inflow from the tunnel excavation surface caused significant surface subsidence at the tunnel portal, vertical convergence at the cross section of the shield tunnel, and significant increases in the axial and shear forces on the bolt. In addition, based on the existing subway regulation, combined with the simulation results of soil reinforcement measures at different depths, the emergency control criterion for controlling water inrush on the excavation surface was established by using the depth of soil reinforcement. The minimum depth of the reinforced soil from the ground surface at 15 m is recommended to ensure construction safety of the subway shield at the launching-arrival stage.


2012 ◽  
Vol 204-208 ◽  
pp. 1429-1434
Author(s):  
Xue Feng Li ◽  
Shou Ji Du ◽  
Ding Feng Zhang

A three-dimensional numerical analysis was conducted to investigate the effects of a new shield tunnel excavation on the internal forces and deformation induced in an existing parallel tunnel and soil plastic zones around it. Special attention was paid to the influence of relative positions between two tunnels. The results of the analysis show that the relative positions affect the mechanical behavior of the existing parallel tunnel and the soil mass behavior around it. When a new tunnel is driven below or above an existing parallel tunnel, important increments are induced in deformation and bending moment in the lining of existing tunnel at its crown and springline, compared to that of induced by new tunnel excavation in horizontally parallel to the existing one. The plastic zones around tunnels also extend larger when tunnels are driven in vertically parallel than they are in horizontally parallel. For the safety concern, it is concluded that horizontally parallel configuration model between two tunnels should be adopted in practice.


2020 ◽  
Vol 97 ◽  
pp. 103290 ◽  
Author(s):  
Linchong Huang ◽  
Jianjun Ma ◽  
Mingfeng Lei ◽  
Linghui Liu ◽  
Yuexiang Lin ◽  
...  

2021 ◽  
Vol 11 (7) ◽  
pp. 2919
Author(s):  
Massamba Fall ◽  
Zhengguo Gao ◽  
Becaye Cissokho Ndiaye

A pile foundation is commonly adopted for transferring superstructure loads into the ground in weaker soil. They diminish the settlement of the infrastructure and augment the soil-bearing capacity. This paper emphases the pile-driving effect on an existing adjacent cylindrical and semi-tapered pile. Driving a three-dimensional pile into the ground is fruitfully accomplished by combining the arbitrary Lagrangian–Eulerian (ALE) adaptive mesh and element deletion methods without adopting any assumptions that would simplify the simulation. Axial forces, bending moment, and lateral displacement were studied in the neighboring already-installed pile. An investigation was made into some factors affecting the forces and bending moment, such as pile spacing and the shape of the already-installed pile (cylindrical, tapered, or semi-tapered). An important response was observed in the impact of the driven pile on the nearby existing one, the bending moment and axial forces were not negligible, and when the pile was loaded, it was recommended to consider the coupling effect. Moreover, the adjacent semi-tapered pile was subjected to less axial and lateral movement than the cylindrical one with the same length and volume for taper angles smaller than 1.0°, and vice versa for taper angles greater than 1.4°.


Mathematics ◽  
2021 ◽  
Vol 9 (7) ◽  
pp. 704
Author(s):  
Wenjun An ◽  
Guquan Song ◽  
Shutong Chen

Given the influence of near-fault vertical seismic action, we established a girder-spring-damping-rod model of a double-span continuous girder bridge and used the transient wave function expansion method and indirect modal function method to calculate the seismic response of the bridge. We deduced the theoretical solution for the vertical and longitudinal contact force and displacement response of the bridge structure under the action of the near-fault vertical seismic excitation, and we analyzed the influence of the vertical separation of the bridge on the bending failure of the pier. Our results show that under the action of a near-fault vertical earthquake, pier-girder separation will significantly alter the bridge’s longitudinal displacement response, and that neglecting this separation may lead to the underestimation of the pier’s bending damage. Calculations of the bending moment at the bottom of the pier under different pier heights and cross-sectional diameters showed that the separation of the pier and the girder increases the bending moment at the pier’s base. Therefore, the reasonable design of the pier size and tensile support bearing in near-fault areas may help to reduce longitudinal damage to bridges.


2012 ◽  
Vol 28 (1) ◽  
pp. 97-106 ◽  
Author(s):  
J. D. Yau ◽  
S.-R. Kuo

ABSTRACTUsing conventional virtual work method to derive geometric stiffness of a thin-walled beam element, researchers usually have to deal with nonlinear strains with high order terms and the induced moments caused by cross sectional stress results under rotations. To simplify the laborious procedure, this study decomposes an I-beam element into three narrow beam components in conjunction with geometrical hypothesis of rigid cross section. Then let us adopt Yanget al.'s simplified geometric stiffness matrix [kg]12×12of a rigid beam element as the basis of geometric stiffness of a narrow beam element. Finally, we can use rigid beam assemblage and stiffness transformation procedure to derivate the geometric stiffness matrix [kg]14×14of an I-beam element, in which two nodal warping deformations are included. From the derived [kg]14×14matrix, it can take into account the nature of various rotational moments, such as semi-tangential (ST) property for St. Venant torque and quasi-tangential (QT) property for both bending moment and warping torque. The applicability of the proposed [kg]14×14matrix to buckling problem and geometric nonlinear analysis of loaded I-shaped beam structures will be verified and compared with the results presented in existing literatures. Moreover, the post-buckling behavior of a centrally-load web-tapered I-beam with warping restraints will be investigated as well.


Author(s):  
Diana Abdulhameed ◽  
Michael Martens ◽  
J. J. Roger Cheng ◽  
Samer Adeeb

Pipe bends are frequently used to change the direction in pipeline systems and they are considered one of the critical components as well. Bending moments acting on the pipe bends result from the surrounding environment, such as thermal expansions, soil deformations, and external loads. As a result of these bending moments, the initially circular cross-section of the pipe bend deforms into an oval shape. This consequently changes the pipe bend’s flexibility leading to higher stresses compared to straight pipes. Past studies considered the case of a closing in-plane bending moment on 90-degree pipe bends and proposed factors that account for the increased flexibility and high-stress levels. These factors are currently presented in the design codes and known as the flexibility and stress intensification factors (SIF). This paper covers the behaviour of an initially circular cross-sectional smooth pipe bend of uniform thickness subjected to in-plane opening/closing bending moment. ABAQUS FEA software is used in this study to model pipe bends with different nominal pipe sizes, bend angles, and various bend radius to cross-sectional pipe radius ratios. A comparison between the CSA-Z662 code and the FEA results is conducted to investigate the applicability of the currently used SIF factor presented in the design code for different loading cases. The study showed that the in-plane bending moment direction acting on the pipe has a significant effect on the stress distribution and the flexibility of the pipe bend. The variation of bend angle and bend radius showed that it affects the maximum stress drastically and should be considered as a parameter in the flexibility and SIF factors. Moreover, the CSA results are found to be un-conservative in some cases depending on the bend angle and direction of the applied bending moment.


Sign in / Sign up

Export Citation Format

Share Document